Nello L. Teer Co. v. North Carolina Department of Transportation

625 S.E.2d 135, 175 N.C. App. 705, 2006 N.C. App. LEXIS 281
CourtCourt of Appeals of North Carolina
DecidedFebruary 7, 2006
DocketCOA04-1615
StatusPublished
Cited by10 cases

This text of 625 S.E.2d 135 (Nello L. Teer Co. v. North Carolina Department of Transportation) is published on Counsel Stack Legal Research, covering Court of Appeals of North Carolina primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Nello L. Teer Co. v. North Carolina Department of Transportation, 625 S.E.2d 135, 175 N.C. App. 705, 2006 N.C. App. LEXIS 281 (N.C. Ct. App. 2006).

Opinion

GEER, Judge.

Defendant North Carolina Department of Transportation (“DOT”) appeals from the order of the trial court that allowed plaintiff Nello L. Teer Company (“Teer”) to amend its complaint to add a verification and denied DOT’S motion to dismiss. DOT argues that it is entitled to bring this interlocutory appeal because the trial court’s ruling implicates its sovereign immunity. Even assuming, without deciding, that a failure to comply with the statutory requirements of N.C. Gen. Stat. § 136-29 (2005) violates the State’s sovereign immunity, the effect of the General Assembly’s amendment to § 136-29 in 1987 was to make the time limitations in that statute a statute of limitations and not a condition precedent to suit. As such, any failure to comply with § 136-29’s time limits does not implicate the State’s sovereign immunity, but rather requires application of the law governing statutes of limitations. Accordingly, we dismiss DOT’s appeal.

Teer won a contract from DOT for the construction of certain road improvements to Interstate 85 from the Orange County line east to Cole Mill Road in Durham. The construction was complete on 6 June 1999, and DOT paid the final estimate for the work done on 17 May 2003. On 15 July 2003, Teer submitted a verified claim to DOT seeking an adjustment to the final estimate and payment in accordance with N.C. Gen. Stat. § 136-29(a). The State Highway Adminis *707 trator evaluated the claim and, in a letter dated 3 November 2003, denied Teer’s claim for additional compensation.

On 11 December 2003, Teer filed an unverified complaint against DOT for the additional compensation in Wake County Superior Court. On 12 February 2004, DOT filed an answer that asserted a defense of sovereign immunity generally, but did not specifically address the failure of Teer to verify its complaint under N.C. Gen. Stat. § 136-29(c). On 25 May 2004, after the time limitation in § 136-29(c) had run, DOT filed a motion to dismiss the complaint based on Teer’s failure to file a verification within the time prescribed by the statute. In response, Teer filed a motion, pursuant to Rule 15 of the Rules of Civil Procedure, for leave to amend its complaint to add a verification.

A hearing was held on the two motions before Judge Howard E. Manning, Jr. on 11 August 2004. In his order entered 31 August 2004, Judge Manning denied DOT’s. motion to dismiss, granted Teer’s motion to amend its complaint, and ordered that the verification relate back to the date the complaint was originally filed. DOT filed a notice of appeal from the trial court’s order on 16 September 2004. Teer has moved to dismiss that appeal as interlocutory.

An interlocutory order is an order made during the pendency of an action that does not dispose of the case, but rather requires further action by the trial court to finally determine the rights of all the parties involved in the controversy. Veazey v. City of Durham, 231 N.C. 357, 362, 57 S.E.2d 377, 381 (1950). Generally, there is no right to appeal from an interlocutory order unless (1) the trial court made the required certification under Rule 54 of the Rules of Civil Procedure, or (2) the order affects a substantial right that would be lost without immediate review. Eckard v. Smith, 166 N.C. App. 312, 316, 603 S.E.2d 134, 137-38 (2004), aff’d per curiam, 360 N.C. 51, 619 S.E.2d 503 (2005).

DOT argues that the trial court’s ruling on the two motions affects DOT’s sovereign immunity. Our appellate courts have consistently recognized that “[w]here the appeal from an interlocutory order raises issues of sovereign immunity . . . such appeals affect a substantial right sufficient to warrant immediate appellate review.” Peverall v. County of Alamance, 154 N.C. App. 426, 429, 573 S.E.2d 517, 519 (2002), disc. review denied, 356 N.C. 676, 577 S.E.2d 632 (2003). DOT contends, without citing any authority, that its “appeal is squarely based upon the defense of sovereign immunity. Allowing *708 Teer to proceed with its suit without compliance with N.C. Gen. Stat. § 136-29, which must be strictly construed, violates NCDOT’s sovereign immunity.”

We do not find this assertion as obvious as DOT does. We note that the State has waived its sovereign immunity with respect to claims against DOT arising from construction contracts by enacting N.C. Gen. Stat. § 136-29. We also acknowledge that because “acts permitting suit are in derogation of the sovereign right of immunity, . . . they should be strictly construed.” Floyd v. N.C. State Highway & Pub. Works Comm’n, 241 N.C. 461, 464, 85 S.E.2d 703, 705 (1955).

Nonetheless, it does not necessarily follow that, once an act permits suit, any failure to comply with that statute gives rise to a defense of sovereign immunity as opposed to simply no recovery or other defenses, such as a lack of subject matter jurisdiction, a failure to exhaust administrative remedies, or a violation of the statute of limitations. See, e.g., Middlesex Constr. Corp. v. State, 307 N.C. 569, 575, 299 S.E.2d 640, 644 (1983) (holding that when the plaintiff failed to comply with N.C. Gen. Stat. § 143-135.3 (Supp. 1981), the trial court should have dismissed the case “for lack of jurisdiction”). At the very least, DOT’s proposition — fundamental to its right to bring this interlocutory appeal — requires citation of authority. We need not, however, resolve this question since even if we assume, without deciding, that DOT has a right to appeal, its argument regarding the trial court’s subject matter jurisdiction — the lynchpin for its invocation of sovereign immunity — fails.

DOT’s analysis presumes that the failure to file a verified complaint within the time limitation set forth in N.C. Gen. Stat. § 136-29 deprives the trial court of subject matter jurisdiction because the time limit is a condition precedent and not a statute of limitations. As our Supreme Court has explained, “[ordinary statutes of limitation are clearly procedural, affecting only the remedy directly and not the right to recover,” while “a condition precedent establishes a time period in which suit must be brought in order for the cause of action to be recognized.” Boudreau v. Baughman, 322 N.C. 331, 340-41, 368 S.E.2d 849, 857 (1988). With respect to conditions precedent, if the plaintiff does not file suit within the specified time frame, “the plaintiff ‘literally has no cause of action. The harm that has been done is damnum absque injuria — a wrong for which the law affords no redress.’ ” Id. at 341, 368 S.E.2d at 857 (quoting Rosenberg v. Town of North Bergen, 61 N.J. 190, 199, 293 A.2d 662

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Untitled Case
M.D. North Carolina, 2026
Smith v. Volkswagen Southtowne
2024 UT App 33 (Court of Appeals of Utah, 2024)
McAuley v. N.C. A&T State Univ.
Supreme Court of North Carolina, 2022
Morris v. Rodeberg
Court of Appeals of North Carolina, 2022
McAuley v. NC A&T State Univ.
Court of Appeals of North Carolina, 2021
State v. Shannon
642 S.E.2d 516 (Court of Appeals of North Carolina, 2007)
Glass v. Anniston City Bd. of Educ.
957 So. 2d 1143 (Court of Civil Appeals of Alabama, 2006)

Cite This Page — Counsel Stack

Bluebook (online)
625 S.E.2d 135, 175 N.C. App. 705, 2006 N.C. App. LEXIS 281, Counsel Stack Legal Research, https://law.counselstack.com/opinion/nello-l-teer-co-v-north-carolina-department-of-transportation-ncctapp-2006.