NECO, Inc. v. Larry Price & Associates, Inc.

597 N.W.2d 602, 257 Neb. 323, 1999 Neb. LEXIS 131
CourtNebraska Supreme Court
DecidedJuly 23, 1999
DocketS-98-553
StatusPublished
Cited by12 cases

This text of 597 N.W.2d 602 (NECO, Inc. v. Larry Price & Associates, Inc.) is published on Counsel Stack Legal Research, covering Nebraska Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
NECO, Inc. v. Larry Price & Associates, Inc., 597 N.W.2d 602, 257 Neb. 323, 1999 Neb. LEXIS 131 (Neb. 1999).

Opinion

Hendry, C.J.

INTRODUCTION

ÑECO, Inc., and NASCO, Inc., brought suit for fraudulent and/or negligent misrepresentation against Larry Price & Associates, Inc., and Larry Price, individually (collectively Price). The district court granted Price’s motions for summary judgment, finding that the action was barred by the statute of *325 limitations. NECO and NASCO appealed this decision to the Nebraska Court of Appeals. We removed the case to our docket pursuant to our power to regulate the Court of Appeals’ caseload and that of this court. See Neb. Rev. Stat. § 24-1106(3) (Reissue 1995). Viewing the evidence in a light most favorable to NECO and NASCO, we find summary judgment to be inappropriate. We therefore reverse, and remand for further proceedings.

BACKGROUND

This case involves an unsuccessful commercial real estate agreement between Price and Don Nielsen, the president of NECO and NASCO. NECO is a family-owned corporation that provides and monitors fire safety and security systems, while NASCO serves as the administrative arm of NECO. (Hereinafter, we will refer to appellants collectively as Nielsen, since Nielsen controls and acts for NECO and NASCO.) After executing a purchase agreement, Nielsen refused to complete the agreement because the subject property was not located in a building with a complete fire sprinkler system. Nielsen brought a fraud claim against Price, asserting that he had represented to them that the building would have a complete sprinkler system, when in fact he knew he would be installing only a partial system.

In 1985, Price purchased and began renovating the Stuart Building, located on the southeast comer of 13th and P Streets in Lincoln, Nebraska. The building was renamed “University Towers.” Price was granted permission from the city of Lincoln to complete the renovation in stages. This renovation involved converting several floors of a 12-story commercial building into residential units, making University Towers a combination of commercial and residential spaces.

On February 22,1990, Nielsen executed an agreement to purchase units Nos. 130, 901, 902, and 903 in University Towers. The purpose of the purchase was to allow NECO to move its monitoring headquarters for all of its operations to University Towers and additionally, to have NECO provide the monitoring for the fire safety system in University Towers.

In 1986, when the remodeling process began, Price contracted with NIFCO Mechanical Systems, Inc. (NMSI), to *326 install the building’s sprinkler system. A written memorandum was created, based on a meeting between NMSI and the Lincoln Fire Prevention Bureau. The memo is dated April 1, 1986, and was written by either Mark Long or Mike Coon, employees of NMSI. The memo states, “Sprinkler entire building, with these exceptions: 1. University Club dining area, restrooms, public areas. 2. Space above 10th floor if not combustible. 3. Theater seating areas or restrooms. 4. Barrymore’s fly gallery if it is above 55' and it is.” This document did not surface until the pretrial discovery process.

Nielsen initiated discussions with Price about relocating NECO to University Towers as early as 1987 or 1988. Nielsen testified in his deposition that during this time, he discussed the sprinkler system with Price and Price’s architect, Bob Gibb.

Price gave Nielsen some articles published for promotional purposes concerning University Towers. These articles discuss the fire safety sprinkler system as a selling point for the facility. In particular, one article states, “It was not required that we install [fire] sprinklers____However, the best possible fire control is the water sprinkler system, which we chose.” Another article states, “Fire service people across the country have found that a totally operable and fully sprinklered facility has never had multiple loss of life.”

Also included in the articles was a signed statement by Price stating,

Our City Code did not require me to install a sprinkler fire system. When I purchased the Stuart Building and started to plan how I would refurbish the structure, the first decision that I made was to do everything possible to make it fire safe----1 would have never considered selling apartments without this fire system.

Gibb also wrote a letter to Nielsen stating that “the building has a new sprinkler system.” Based on all of this information, Nielsen concluded that Price had voluntarily chosen to sprinkler the entire building. Nielsen asserts that Price’s decision to sprinkler the entire building was a key factor in Nielsen’s decision to purchase the units. In contrast, Price asserts in his deposition that the two parties never spoke about NECQ’s sprinkler needs during negotiations.

*327 In 1989, Nielsen submitted information on University Towers to NECO’s insurance provider, Underwriters Laboratories, Inc. (UL). Based on the provided information, UL determined that the new location would be satisfactory for NECO’s main operations, in part because the building would have a complete sprinkler system.

After the discussions with Price and the positive response from UL, Nielsen entered into the purchase agreement in 1990. The total purchase price was $260,872.33 for units Nos. 130, 901, 902, and 903. Nielsen paid a $20,751.70 downpayment and $5,616.07 in closing costs. Nielsen also paid condominium fees and real estate taxes of $34,338.22. The remainder of the purchase price was set out in the agreement to be paid in three equal payments due in August 1990 and February and August 1991.

In early 1991, Nielsen visited the building to install an entryway security system. He noticed that the sprinkler system was not yet finished but testified that he was not concerned because he knew the sprinkler system was being added on an ongoing basis. As of 1992, and possibly later, NMSI was still installing portions of the sprinkler system at University Towers.

On April 18,1991, Price sent a letter to Nielsen asking him to make a payment on the promissory note secured by the four units. Price had also sent a similar letter in November 1990. In response to Price’s April 18 letter, Nielsen wrote back that he would do what he could to “allow for an earlier occupancy” and that “there would be no problem in moving up the payment schedule.” Nielsen testified that their understanding was that “as soon as ... we get to the point where we can beneficially start some activity about moving into the building, that [sic] we’ll get it paid.”

As a result of a series of communications with Price about the timetable for NECO’s relocation, Nielsen sent Price a letter on November 12, 1991. This letter set out a timetable for the remodeling of units Nos. 901, 902, and 903; a final walk-through inspection by UL; and the actual relocation date of ÑECO as December 1992. At the bottom of the letter, Nielsen noted his concerns regarding the sprinkler system. The letter stated that there were certain areas of the building that had not yet been sprinklered and that approval for the site from UL was *328

Free access — add to your briefcase to read the full text and ask questions with AI

Related

BLB Aviation South Carolina, LLC v. Jet Linx Aviation LLC
900 F. Supp. 2d 972 (D. Nebraska, 2012)
Agri Affiliates, Inc. v. Bones
660 N.W.2d 168 (Nebraska Supreme Court, 2003)
Outlook Windows Partnership v. York International Corp.
112 F. Supp. 2d 877 (D. Nebraska, 2000)
Wait v. Cornette
612 N.W.2d 905 (Nebraska Supreme Court, 2000)
Fossett v. Board of Regents of University of Nebraska
605 N.W.2d 465 (Nebraska Supreme Court, 2000)
Parnell v. Madonna Rehabilitation Hospital, Inc.
602 N.W.2d 461 (Nebraska Supreme Court, 1999)
Ferguson v. Union Pacific Railroad
601 N.W.2d 907 (Nebraska Supreme Court, 1999)
Knudsen v. Mutual of Omaha Insurance
601 N.W.2d 725 (Nebraska Supreme Court, 1999)
City of Omaha v. Morello
602 N.W.2d 1 (Nebraska Supreme Court, 1999)
Bargmann v. State, Dept. of Roads
600 N.W.2d 797 (Nebraska Supreme Court, 1999)

Cite This Page — Counsel Stack

Bluebook (online)
597 N.W.2d 602, 257 Neb. 323, 1999 Neb. LEXIS 131, Counsel Stack Legal Research, https://law.counselstack.com/opinion/neco-inc-v-larry-price-associates-inc-neb-1999.