NBZ Enterprises, Inc. v. City of Shakopee

489 N.W.2d 531, 1992 Minn. App. LEXIS 846, 1992 WL 189085
CourtCourt of Appeals of Minnesota
DecidedAugust 11, 1992
DocketC0-91-2455
StatusPublished
Cited by32 cases

This text of 489 N.W.2d 531 (NBZ Enterprises, Inc. v. City of Shakopee) is published on Counsel Stack Legal Research, covering Court of Appeals of Minnesota primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
NBZ Enterprises, Inc. v. City of Shakopee, 489 N.W.2d 531, 1992 Minn. App. LEXIS 846, 1992 WL 189085 (Mich. Ct. App. 1992).

Opinion

OPINION

NORTON, Judge.

NBZ Enterprises, Inc., et ah, challenge the trial court judgment that a ready-mix concrete operation is not permitted under the Conditional Use Permit and Mineral *533 Extraction and Land Rehabilitation Permit issued by respondent, City of Shakopee. The City of Shakopee filed a notice of review challenging the trial court’s reinstatement of appellant’s Conditional Use Permit.

FACTS

Appellants, NBZ Enterprises, Inc., et al. (hereafter NBZ), own and operate a sand and gravel mining business in the City of Shakopee, respondent. The sand and gravel pit is located in an area zoned as an Agricultural Preservation District pursuant to City of Shakopee Zoning Ordinance section 11.24. Section 11.24, subd. 3 requires a Conditional Use Permit (CUP) to mine the sand and gravel. A Mineral Extraction and Land Rehabilitation Permit (MELRP) is required for all commercial mining operations under City of Shakopee Zoning Ordinance section 11.07, subd. 7.

On September 21, 1984, NBZ applied for a CUP to extract gravel from its land. Merila & Associates, the engineers who prepared NBZ’s application for the CUP, submitted a plan to the Shakopee City Council on April 30, 1985. This plan specifically stated that NBZ had no intention to mix asphalt or cement on the property. Shakopee issued a CUP and MELRP to NBZ on April 5, 1988 pursuant to this court’s order. Scott County Lumber Co., Inc. v. City of Shakopee, 417 N.W.2d 721, 728 (Minn.App.1988), pet. for rev. denied (Minn. Mar. 23, 1988). Since that date, NBZ has mined, crushed and washed gravel on the property.

The GUP and MELRP are subject to renewal every three years. On May 9, 1991, Shakopee renewed the permits subject to NBZ’s 1991 application for renewal describing the mining operation as “mining, crushing, washing and processing of aggregate.”

In June 1991, NBZ erected on the property a ready-mix concrete plant estimated at taller than 35 feet. Shakopee subsequently received complaints that a ready-mix plant was being operated on NBZ’s property. In a June 13, 1991 letter, Shakopee informed NBZ that the ready-mix plant was considered a nonpermitted use on the property which must be removed by June 24, 1991. NBZ ceased operation of the ready-mix plant. But, due to the significant financial investment, NBZ refused to disassemble the plant until a neutral third party decided the dispute as to whether the ready-mix plant violated the CUP and MELRP.

On August 20, 1991, Shakopee revoked the CUP. After a hearing on August 21, 1991, the trial court granted a temporary restraining order enjoining NBZ from operating the ready-mix plant, and Shakopee from revoking NBZ’s CUP.

In its October 16, 1991 judgment, the trial court ordered Shakopee to reinstate NBZ’s CUP because there was no repeated or substantial violation giving Shakopee the authority to revoke the CUP. The trial court also ordered NBZ to dismantle its ready-mix concrete plant and remove it from the property by December 15, 1991 because neither the MELRP nor CUP authorized a ready-mix concrete plant on the property.

ISSUES

I. Does the term “processing” in NBZ’s renewal application for the MELRP show NBZ’s intent to operate a ready-mix concrete plant at the site of its gravel mine and bind Shakopee?

II. Does the term “processing” in Shak-opee’s zoning ordinance section 11.05, subd. 7 C 6 include the mixing of sand, gravel and cement into concrete?

III. Is the ready-mix concrete plant a permitted accessory use to NBZ’s sand and gravel operation?

IV. Did Shakopee have a sufficient basis to revoke NBZ’s CUP?

ANALYSIS

I.

NBZ argues that the trial court erred in finding that it had no intent to operate a ready-mix concrete plant at the time the MELRP was originally issued and its renewal was intended to be a major amendment to allow a ready-mix plant at its gravel mine site. The trial court found NBZ to *534 not be in compliance with the MELRP issued and renewed by Shakopee, thereby requiring the dismantling and removal of the ready-mix concrete plant from the gravel mine site.

The trial court’s finding that there was no intent to operate a ready-mix concrete plant on NBZ’s property is a finding of fact. Findings of fact will not be set aside unless clearly erroneous with due regard given to the opportunity of the trial court to judge the credibility of the witnesses. Minn.R.Civ.P. 52.01. On appeal, this court will reverse only, if upon reviewing the evidence, it is left with the firm conviction that a mistake has been made. City of Minnetonka v. Carlson, 298 N.W.2d 763, 766 (Minn.1980).

NBZ argues that the Merila report stating NBZ’s intention not to mix concrete on its property is not part of the original or renewal application for the MELRP.

The record shows that when application was made for the CUP and the MELRP in 1985, NBZ submitted a report prepared by Merila & Associates describing NBZ’s plans for its sand and gravel business located in an area zoned agricultural preservation district (AG). This report specifically states “[tjhere is no intent to mix asphalt or concrete at this site.”

The Merila report stating that NBZ had no intent to mix concrete at the site was a part of the original 1985 application to mine gravel at this site and the original application is referred to in the 1991 renewal application. The description of the operation on the 1985 application for the MELRP states “extraction of gravel from the site (See report).” NBZ was referring Shako-pee to its Merila report. In its 1991 application for the renewal of the MELRP, NBZ refers Shakopee to its 1985 application.

NBZ also did not request the addition of a ready-mix concrete plant at the time of the renewal of its application. At the May 9, 1991 planning commission meeting which reviewed and approved the renewal of the CUP and MELRP, NBZ only requested amendments to the CUP. These amendments included the addition of two security lights on the property and extended operating hours.

Additionally, any structure in excess of 35 feet in height in an AG zone requires a CUP. Shakopee, Minn., Zoning Ordinance § 11.24, subd. 3 M (1989). There was testimony at trial that NBZ’s ready-mix concrete plant exceeds 35 feet in height. Since NBZ did not request a CUP for a structure in excess of 35 feet in height, Shakopee could reasonably conclude that the term “processing” as used in the MELRP renewal application did not include the ready-mix plant. Also, the MELRP application requires maps of the entire site which are to include any structures to be erected. The maps submitted by NBZ did not include ready-mix cement plant.

When NBZ included the term “processing” in the description of its mining operation on the renewal application for its MELRP, Shakopee could conclude that NBZ meant processing of gravel in regard to its extraction as had been done for the prior three years.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Ash Grove Cement Co. v. Nebraska Dept. of Rev.
306 Neb. 947 (Nebraska Supreme Court, 2020)
White v. City of Elk River
822 N.W.2d 320 (Court of Appeals of Minnesota, 2012)
R.A. Putnam & Associates, Inc. v. City of Mendota Heights
510 N.W.2d 264 (Court of Appeals of Minnesota, 1994)

Cite This Page — Counsel Stack

Bluebook (online)
489 N.W.2d 531, 1992 Minn. App. LEXIS 846, 1992 WL 189085, Counsel Stack Legal Research, https://law.counselstack.com/opinion/nbz-enterprises-inc-v-city-of-shakopee-minnctapp-1992.