Tracie Erickson, Relators v. Minnesota Department of Natural Resources

Court of Appeals of Minnesota·Decided July 20, 2015·No. A14-1732·Unpublished

Opinion

This opinion will be unpublished and may not be cited except as provided by Minn. Stat. § 480A.08, subd. 3 (2014).

STATE OF MINNESOTA

IN COURT OF APPEALS

A14-1732

Tracie Erickson, et al.,

Relators,

vs.

Minnesota Department of Natural Resources, Respondent.

Filed July 20, 2015

Reversed

Smith, Judge

Minnesota Department of Natural Resources

Julie N. Nagorski, HKM, P.A., St. Paul, Minnesota (for relators)

Lori Swanson, Attorney General, Karen D. Olson, Assistant Attorney General, St. Paul, Minnesota (for respondent)

Considered and decided by Hudson, Presiding Judge; Worke, Judge; and Smith, Judge.

UNPUBLISHED OPINION

SMITH, Judge We reverse the department of natural resources’ decision that relators’ silica sand-

mining operation is subject to the setback-permit provision of Minn. Stat. § 103G.217 (2014) because relators’ silica sand-mining operation is not a “new project” within the

meaning of the statute and because there is no indication that any environmental review at the site had been noticed for public comment after April 30, 2013.

FACTS

In January 1992, Alan Thorson petitioned Houston County for a conditional use permit (CUP) to allow him to mine silica sand on his property. At a public hearing, he told the county planning commission that he was seeking to bid on a contract for a bridge-construction project, and that, if successful, he would use the CUP to extract 8,000-10,000 cubic yards of sand for the bridge and “continue to use the pit after completion of the bridge.” Although some neighbors raised aesthetic concerns, the planning commission unanimously recommended that the county board of commissioners issue the CUP. The county board approved the CUP, subject to the condition that the sand mining operation be “permitted for 5 years subject to review for possible extension beyond the 5 years.” The CUP did not state a limit on the volume of sand that could be extracted from the site. The county “extended” the CUP in 1997, 2003, and 2008.

Relators Tracie and Michelle Erickson purchased the property in 2009. The Ericksons contracted with Minnesota Sands, LLC, to extract 2 million cubic yards of sand and process the sand onsite. Responding to concerns that activities on the Ericksons’ property had “materially changed,” the county board held a hearing on June 19, 2012. The board struggled to establish a baseline for determining whether there had in fact been a material change in the sand mine’s operations in light of the lack of documentation regarding activities at the mine at the time of the CUP issuance in 1992 and in each of its “renewal years.” A representative of neighboring property owners

testified that “his clients purchased property with a belief that an estimated 10,000 cubic yards of material would be removed,” and that the proposed increase to 2 million cubic yards was “a dramatic change and a change in the scope of the operation.”

In July 2012, the county enacted a moratorium on “the issuance of any conditional use permit for new silica sand mining,” “the conversion of existing non-silica sand mining operations into silica sand-mining operations,” and all sand processing operations “not expressly authorized by the terms of an existing conditional use permit.” The moratorium was later extended to 2014. The county’s environmental services director later recalled that the ordinance was perceived as necessary to address the problem of “operators . . . attempting to utilize old pre-existing permits for small construction sand or shale quarry operations to end-run the moratorium.”

On July 10, 2012, the county board voted to order that sand-mining and sand-

processing work on the Erickson property be stopped, based on its finding that the Ericksons’ arrangement with Minnesota Sands included “screening and crushing . . . which is an expansion of the original CUP,” and its conclusion that “an [environmental assessment worksheet] should have been required” in 1992 and “this requirement has not been fulfilled.” On August 7, 2012, the county board voted to have an environmental assessment worksheet (EAW) completed regarding sand-mining operations on the Erickson property. The Ericksons and Minnesota Sands unsuccessfully moved the district court for injunctive relief.

In November 2012, after receiving a letter from the county notifying them that the CUP would expire on January 8, 2013, the Ericksons requested another five-year

extension of their original CUP. The county delayed considering the extension, pending completion of the EAW.

The Ericksons and Minnesota Sands terminated their agreement in September 2013, and the Ericksons provided a copy of the termination agreement to the county on February 27, 2014. The county then agreed to consider the Ericksons’ application for extension of the original CUP because “the project to which environmental review attached has been abandoned.” As part of the county board’s consideration of the CUP extension, the county zoning administrator noted that extension approval delayed past the “exact 5 year renewal deadline . . . happens quite often” in the county and that mines were allowed to continue operating under a prior CUP during such a delay. On June 24, 2014, the county granted the Ericksons’ request to extend their CUP, finding that the EAW requirement did not apply to the “limited mining allowed under the . . . 1992 CUP, as renewed,” and that the county’s “moratorium involving silica sand, as amended, does not apply to the proposed renewal because it is not new mining.” The county added, however, a condition expressly limiting the extraction to 10,000 cubic yards per year.

Respondent Minnesota Department of Natural Resources (DNR) sent a letter to the Ericksons to inform them of changes in state law that DNR contended would require the Ericksons to obtain a trout stream setback permit before resuming silica sand mining. DNR also wrote to the county zoning administrator, requesting confirmation that the county had not extended the Ericksons’ CUP until after its expiration date. The zoning administrator replied that, in the view of the county and in light of its practices and its

interpretation of state statutes, the CUP had not expired because the Ericksons’ had not violated any of the CUP’s conditions and had timely filed an extension request.

Notwithstanding the zoning administrator’s opinion, DNR notified the Ericksons that, because their 1992 CUP had lapsed, the mine “qualifies as a new project and is subject to the setback permit requirements.” DNR ordered the Ericksons to cease mining until they obtained the setback permit. On September 11, 2014, DNR issued its final decision, rejecting the Ericksons’ and the county’s characterization of the CUP extension and reiterating its finding that the Ericksons’ mine was a “new project” subject to the setback permit requirement.

DECISION

I.

A. Standard of Review The Ericksons challenge DNR’s determination that their sand mine is subject to the setback-permit requirement in Minn. Stat. § 103G.217. When reviewing an agency’s interpretation of a statute that it is charged with administering, we generally defer to the agency when its determination “involv[es] application of an agency’s expertise, technical training, and experience.” Minn. Ctr. for Envtl. Advocacy v. Minn. Pollution Control Agency, 644 N.W.2d 457, 463-64 (Minn. 2002). But we review de novo the determination of whether an agency has the statutory authority to act at all in a particular case. In re Hubbard, 778 N.W.2d 313, 318 (Minn. 2010); see also id. at 318 n.4 (expressly rejecting an agency’s argument that judicial deference should extend to “the threshold question of whether the legislature has granted an agency the authority to take

the action at issue”). We still defer, however, to an agency’s factual findings, provided that they are supported by substantial evidence. Saif Food Mkt. v. Comm’r, State, Dep’t of Health, 664 N.W.2d 428, 430 (Minn. App. 2003).

Free access — add to your briefcase to read the full text and ask questions with AI

Tracie Erickson, Relators v. Minnesota Department of Natural Resources, (Mich. Ct. App. 2015).

Tracie Erickson, Relators v. Minnesota Department of Natural Resources (Tracie Erickson, Relators v. Minnesota Department of Natural Resources) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

In Re the Excess Surplus Status of Blue Cross & Blue Shield of Minnesota
624 N.W.2d 264 (Supreme Court of Minnesota, 2001)
NBZ Enterprises, Inc. v. City of Shakopee
489 N.W.2d 531 (Court of Appeals of Minnesota, 1992)
Saif Food Market v. Commissioner, State, Department of Health
664 N.W.2d 428 (Court of Appeals of Minnesota, 2003)
Brua v. MINNESOTA JOINT UNDERWRITING ASS'N
778 N.W.2d 294 (Supreme Court of Minnesota, 2010)
In Re Hubbard
778 N.W.2d 313 (Supreme Court of Minnesota, 2010)
City of Morris v. Sax Investments, Inc.
749 N.W.2d 1 (Supreme Court of Minnesota, 2008)
American Family Insurance Group v. Schroedl
616 N.W.2d 273 (Supreme Court of Minnesota, 2000)
Lee v. Fresenius Medical Care, Inc.
741 N.W.2d 117 (Supreme Court of Minnesota, 2007)
Reserve Mining Co. v. Minnesota Pollution Control Agency
364 N.W.2d 411 (Court of Appeals of Minnesota, 1985)