National Labor Relations Board v. Interboro Contractors, Inc.

388 F.2d 495, 67 L.R.R.M. (BNA) 2083, 1967 U.S. App. LEXIS 4047
CourtCourt of Appeals for the Second Circuit
DecidedDecember 22, 1967
Docket31213-31214_1
StatusPublished
Cited by110 cases

This text of 388 F.2d 495 (National Labor Relations Board v. Interboro Contractors, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals for the Second Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
National Labor Relations Board v. Interboro Contractors, Inc., 388 F.2d 495, 67 L.R.R.M. (BNA) 2083, 1967 U.S. App. LEXIS 4047 (2d Cir. 1967).

Opinion

LUMBARD, Chief Judge:

This case comes before us by petition of the National Labor Relations Board, pursuant to Section 10(e) of the National Labor Relations Act, for enforcement of an order issued against respondent on March 31, 1966. 157 NLRB No. 110. The Board determined that respondent had violated Section 8(a) (1) of the Act by discharging two employees, John and William Landers, for engaging in activities which were protected under the Act; respondent was ordered to cease and desist from the unfair labor practice found and to grant the Landers reinstatement and back pay. The question presented to this court is whether there was substantial evidence to súpport the Board’s findings that the Landers’ presentation of complaints about respondent’s alleged violations of the collective bargaining contract was concerted activity protected under Section 7 and that these complaints were the reason for the discharges. We conclude that the Board’s findings are supported by substantial evidence on the record considered as a whole and enforce the Board’s order.

The testimony at the hearing before the trial examiner revealed the following facts. On March 23, 1965, brothers John and William Landers were hired over the telephone by respondent’s president Kleinhans to work as steamfitters on a construction project at Tratman Avenue in the Bronx. According to John, Klein-hans said that it would be an “8-hour job” and would pay “expense money”; 1 Kleinhans testified that he did not give any such promises.

When they arrived at the jobsite on March 25, the Landers brothers met No-vak, who was also employed by respond *497 ent as a steamfitter. John found that Novak had been working alone for several days while his partner Koster — who was respondent’s only other employee on this job — had been absent because of sickness; the collective bargaining contract and the New York City Fire Regulations require that steamfitters work in pairs.

A short while later Soebke, respondent’s supervisor, visited the jobsite. John asked him about the “8-hour job” and “expense money.” Soebke answered that the Landers would have to speak to Kleinhans about this.

Soebke assigned John to do some welding and William to do some other work. The Landers refused to work separately, claiming that the contract required them to work together. John pointed out to Soebke that Novak had been working without a partner and expressed doubt that Novak was an “A-man” qualified to work as a steamfitter. 2 John also said that he was going to get the union business agent to visit the jobsite. Soebke then assigned both Landers to work together and left the site. John afterwards called the union business agent.

On the following day, Koster, who was the foreman, returned and John repeated the complaints to him. John also told Koster of his conversation with Kleinhans concerning the overtime and expense money; Koster confirmed Soebke’s statement that Kleinhans rarely appeared at the jobsite. John made one phone call to Kleinhans’ office in order to discuss the 8-hour day and expense money, but he was unable to reach Klein-hans.

The same day, the union business agent arrived at the site and heard John’s complaints. The agent told Koster that the men were to work in pairs and that another steamfitter would be sent to replace Novak, who was not an “A-man”; he also ordered Koster before the executive board of the union for a briefing on a foreman’s duties. John also had claimed that a prefabricated boiler which was being delivered to the jobsite violated the contract. 3 Koster confirmed that a prefabricated boiler was being delivered; the agent said that he would look into the matter when the boiler arrived.

On the same day, March 26, John requested Koster to supply him with protective leather equipment and Koster agreed to do so. 4 John testified that, despite his repeated requests and Koster’s repeated promises, he never received the equipment. Kleinhans testified that the requested equipment was provided, but John claimed that only one set was ever provided and that was used by Collins, the steamfitter who replaced Novak.

On March 29, the union business agent called Kleinhans and told him of the investigation and the action taken. Klein-hans asked who had made the complaints; the agent answered that it was irrelevant. Kleinhans then said that it looked like he had a couple of “troublemakers” on the job.

On March 30, Kleinhans came to the jobsite and John, with William in attendance, asked about the 8-hour job and expense money. Kleinhans said he could see no reason for it, but might consider the request later.

On Friday, April 2, Soebke paid the employees for the work through the previous Tuesday. The Landers and Collins complained that the contract required *498 that they be paid through Wednesday. 5 After a discussion and a threat by John that the three of them would notify the union and would wait at the site until they received the money, Soebke agreed to bring the extra day’s pay on Monday.

The prefabricated boiler arrived on April 7 and John called the union, after he found that Koster did not intend to do so, in order to have the boiler inspected. Eventually, a union business agent did discuss the matter with Kleinhans, but he found that no violation was involved. 6

Between April 7 and April 15, the Lan-ders, Collins and Koster moved the boiler and a refrigerator unit into place. John complained to Koster that the rollers and blocks available were not the standard equipment which should be provided for such an operation; William and Collins made similar complaints.

On Thursday, April 15, Soebke paid the Landers in full and told them they were discharged. When asked for the reason, Soebke said he had no reason but was merely carrying out orders.

On April 20, John and William filed unfair labor practice charges against respondent.

For three months, respondent avoided stating any concrete reasons for the discharges. Kleinhans, when questioned by a union agent shortly after the discharges, said he had fired the Landers for “different reasons,” but declined to specify the reasons. He refused to reinstate the Landers, saying that “these guys even went to the National Labor Relations Board.” Kleinhans also refused to give any reason for the discharges when subsequently questioned by a Board agent. In its answer and amended answer filed in the Board proceedings, respondent defended the discharges simply on the ground that under the contract it had the right to discharge “any person whom the employer, in its sole discretion, may deem fit.”

At the hearing, Kleinhans and Soebke testified that the Landers had been taking long lunch hours and had been leaving early, and that this was the reason for the discharges.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Unite Here v. National Labor Relations Board
546 F.3d 239 (Second Circuit, 2008)
Alabama State Personnel Bd. v. Hardeman
893 So. 2d 1173 (Court of Civil Appeals of Alabama, 2004)
City of Hartford v. Hartford Municipal Employees Ass'n
788 A.2d 60 (Supreme Court of Connecticut, 2002)
Anderson v. Department of Public Safety & Correctional Services
623 A.2d 198 (Court of Appeals of Maryland, 1993)
Holo-Krome Co v. National Labor Relations Board
947 F.2d 588 (Second Circuit, 1991)
Roadway Express, Inc. v. National Labor Relations Board
742 F.2d 591 (Eleventh Circuit, 1984)
Personnel Bd. of State v. King
456 So. 2d 80 (Court of Civil Appeals of Alabama, 1984)
Nash-DeCamp Co. v. Agricultural Labor Relations Board
146 Cal. App. 3d 92 (California Court of Appeal, 1983)

Cite This Page — Counsel Stack

Bluebook (online)
388 F.2d 495, 67 L.R.R.M. (BNA) 2083, 1967 U.S. App. LEXIS 4047, Counsel Stack Legal Research, https://law.counselstack.com/opinion/national-labor-relations-board-v-interboro-contractors-inc-ca2-1967.