National Crane Corp. v. Ohio Steel Tube Co.

332 N.W.2d 39, 213 Neb. 782, 36 U.C.C. Rep. Serv. (West) 779, 1983 Neb. LEXIS 1024
CourtNebraska Supreme Court
DecidedMarch 25, 1983
Docket81-747
StatusPublished
Cited by55 cases

This text of 332 N.W.2d 39 (National Crane Corp. v. Ohio Steel Tube Co.) is published on Counsel Stack Legal Research, covering Nebraska Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
National Crane Corp. v. Ohio Steel Tube Co., 332 N.W.2d 39, 213 Neb. 782, 36 U.C.C. Rep. Serv. (West) 779, 1983 Neb. LEXIS 1024 (Neb. 1983).

Opinions

McCown, J.

This is an action under various tort and contract theories to recover all or a portion of the cost of conducting a retrofit program to replace all steel tubing manufactured and sold by the defendant to plaintiff and incorporated into cranes manufactured and sold to ultimate users or consumers by the plaintiff. The District Court sustained defendant’s demurrers and dismissed plaintiff’s petitions. The plaintiff has appealed.

The plaintiff, National Crane Corporation, is a Nebraska corporation which manufactures and sells a diversified line of cranes. The defendant, Ohio Steel Tube Company, is an Ohio corporation engaged in the business of designing and manufacturing various types of steel tubing.

During the period beginning in July 1970 and ending in May 1975, plaintiff purchased sections of welded steel tubing from the defendant for use in the tilt cylinder mechanism of cranes manufactured by plaintiff. During the period of time from January 1, 1971, to June 1, 1976, 1,232 cranes manufactured by plaintiff utilizing the steel tubing purchased from defendant were sold by the plaintiff to various customers.

Failures of the tilt cylinder mechanism of the cranes containing the steel tubing supplied by defendant commenced on April 4, 1973, when the first failure occurred. Three more failures occurred in 1974. Each failure was reported to defendant by plaintiff. Defendant represented to the plaintiff that the first failure was due to an inadequacy of material specification. In two 1974 cases defendant acknowledged the failure was due to an imperfection in the weld, and in the other reported that the [784]*784material met specifications and the weld was satisfactory.

In March 1975, following inquiry by plaintiff, defendant advised plaintiff that the tubing which had been and was still being furnished to plaintiff had been thoroughly and completely tested. The last tubing manufactured by the defendant and involved in this case was delivered to plaintiff in May 1975.

Between January 1976 and June 1976 four more cylinder failures occurred, each of which was also reported to defendant. All the cranes involved in this action were sold by June 1, 1976.

In July 1976 plaintiff launched its own internal investigation and analysis of the cylinder failures which were being reported. Three additional cylinder failures occurred between July 22 and November 5, 1976, in one of which a loss of life occurred.

By December 1976 plaintiff’s testing and investigation reflected that the failures' were not caused by overloading or piston seal leakage and that the cylinder design was adequate. Although plaintiff concluded that the cylinder failure problem must lie with the cylinder material, it was unable to reach specific, precise conclusions on which it could reasonably rely.

On December 29, 1976, plaintiff engaged independent engineering and testing consultants to assist in determining the precise cause of the cylinder failures. Thereafter, and throughout the year 1977, representatives of the plaintiff met with representatives of the defendant, and the defendant was advised of the status of the engineering testing and evaluation being carried on.

Between January 17 and December 7, 1977, four more cylinder failures occurred. In January 1978 defendant formally advised plaintiff that it would not participate in the testing and evaluation program because defendant believed the failures were [785]*785not the result of any defects in defendant’s manufacturing.

In May 1978 plaintiff was advised by its engineering and technical consultants that material and product defects existed in the welded tubing used in the manufacture of the boom cylinders for plaintiff’s cranes. Plaintiff was informed that unexpected failures of the cylinders could occur at any time without warning and that to insure the safety of others the cylinders-must be replaced.

Plaintiff undertook a retrofit program to replace all of the potentially dangerous cylinders with suitable and safe substitute cylinders, and expended $1,078,960 in testing and replacing the defective tubing manufactured by defendant and incorporated in cranes manufactured and sold by plaintiff.

Plaintiff filed its petition in this proceeding on June 20, 1980, seeking recovery of the costs and expenses of the retrofit program under three different theories based on the basic facts set out above. The 15 actual failures are not involved. The first cause of action was for breach of express and implied warranties. The second cause of action was for negligent manufacture of tubing known to be dangerous unless carefully made. The third cause of action was pleaded on the basis of strict liability.

The defendant demurred to the petition on the grounds that the first cause of action was barred by the statute of limitations and the other two causes of action were not available for the recovery of economic loss. The District Court sustained the demurrer on those grounds.

Plaintiff filed an amended petition alleging the same facts but seeking recovery under theories of indemnity and contribution. Defendant demurred to the causes of action in the amended petition upon the grounds that they either were barred by the applicable statute of limitations or were unavailable to the plaintiff, the plaintiff being a volunteer in the alleged action. The District Court sustained de[786]*786fendant’s demurrer to the amended petition. Plaintiff elected to stand on the original and amended petitions and the court dismissed them. Plaintiff has appealed.

Plaintiff contends that the principles of tort law should be extended to permit plaintiff to recover the economic losses incurred under the retrofit program involved here, and that plaintiff should not be limited to recovery on the contractual basis of express or implied warranties. The argument is that because the plaintiff and defendant might be liable to an ultimate user or consumer of plaintiff’s cranes under tort theories of liability if the defective tubing were not replaced, therefore the expense of eliminating that potential tort liability as between plaintiff and defendant is recoverable as a tort claim rather than being recoverable under contract law as a claim for the breach of express or implied warranties under the Uniform Commercial Code.

The great majority of courts which have considered the issue have held that the purchaser of a product pursuant to contract cannot recover economic losses from the manufacturer on claims based on principles of tort law, in the absence of property damage or personal injury from the use of the product. See Jones & Laughlin Steel v. JohnsManville Sales, 626 F.2d 280 (3d Cir. 1980), and cases and authorities there cited.

The line of demarcation between physical harm and economic loss has been said to reflect the line of demarcation between tort theory and contract theory. See Alfred N. Koplin & Co. v. Chrysler Corp., 49 Ill. App. 3d 194, 364 N.E.2d 100 (1977), and cases there cited. “Economic loss” in that case was defined by the court as “ ‘damages for inadequate value, costs of repair and replacement of the defective product or consequent loss of profits — without any claim of personal injury or damage to other property * * *.’ ” Id. at 199, 364 N.E.2d at 103.

Chief Justice Traynor analyzed the distinction

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Shipler v. General Motors Corp.
710 N.W.2d 807 (Nebraska Court of Appeals, 2006)
Hatleberg v. Norwest Bank Wisconsin
2005 WI 109 (Wisconsin Supreme Court, 2005)
Indemnity Ins. Co. v. American Aviation
891 So. 2d 532 (Supreme Court of Florida, 2004)
Compaq Computer Corp. v. Lapray
135 S.W.3d 657 (Texas Supreme Court, 2004)
Jay v. Moog Automotive, Inc.
652 N.W.2d 872 (Nebraska Supreme Court, 2002)
Kramer v. Aventis CropScience USA Holding, Inc.
212 F. Supp. 2d 828 (N.D. Illinois, 2002)
In Re StarLink Corn Products Liability Litigation
212 F. Supp. 2d 828 (N.D. Illinois, 2002)
Trgo v. Chrysler Corp.
34 F. Supp. 2d 581 (N.D. Ohio, 1998)
Steele v. Encore Manufacturing Co.
579 N.W.2d 563 (Nebraska Court of Appeals, 1998)
McGraw-Edison Co. v. Northeastern Rural Electric Membership Corp.
678 N.E.2d 1120 (Indiana Supreme Court, 1997)
Ritter v. Custom Chemicides, Inc.
912 S.W.2d 128 (Tennessee Supreme Court, 1995)
Oklahoma Gas & Electric Co. v. McGraw-Edison Co.
1992 OK 108 (Supreme Court of Oklahoma, 1992)
Murphy v. Spelts-Schultz Lumber Co.
481 N.W.2d 422 (Nebraska Supreme Court, 1992)

Cite This Page — Counsel Stack

Bluebook (online)
332 N.W.2d 39, 213 Neb. 782, 36 U.C.C. Rep. Serv. (West) 779, 1983 Neb. LEXIS 1024, Counsel Stack Legal Research, https://law.counselstack.com/opinion/national-crane-corp-v-ohio-steel-tube-co-neb-1983.