Natex Corp. v. Paris Independent School District

326 S.W.3d 728, 2010 Tex. App. LEXIS 8720, 2010 WL 4273909
CourtCourt of Appeals of Texas
DecidedNovember 1, 2010
Docket06-10-00052-CV
StatusPublished
Cited by32 cases

This text of 326 S.W.3d 728 (Natex Corp. v. Paris Independent School District) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Natex Corp. v. Paris Independent School District, 326 S.W.3d 728, 2010 Tex. App. LEXIS 8720, 2010 WL 4273909 (Tex. Ct. App. 2010).

Opinion

OPINION

Opinion by

Justice MOSELEY.

This is an interlocutory appeal by Natex Corporation, d/b/a Natex Corporation Architects (Natex), a defendant architectural firm, of a denial of a motion to dismiss the suit brought against it by Paris Independent School District (PISD). Natex maintains that dismissal is required because PISD failed to file a certificate of merit pursuant to Section 150.002 of the Texas Civil Practice and Remedies Code when suit was initially filed against it. For the reasons set forth within, we affirm the trial court’s judgment.

I. FACTUAL AND PROCEDURAL HISTORY

In June 2007, PISD and Natex entered into eight separate American Institute of *730 Architects form contracts for architectural design services related to renovations of certain school buildings in the district and for the construction of a new athletic stadium, there being separate contracts prepared for each of the seven buildings and the new stadium. The contracts specified the financial parameters of the work to be done, clarified the overall budgets in dollar amounts, and set forth the obligations of the parties, but left the time parameters of the contracts to be determined at a later date. Under the contracts, Natex was to provide “Schematic Design Documents based on the mutually agreed-upon program, schedule, and budget for the Cost of the Work.”

After the passage of about a year, PISD called Natex to inquire about an “exit strategy” from the relationship because it believed that the architectural work under the contract was not being completed in a timely manner and “time [wa]s of the essence.” Natex responded by sending the district invoices for work it alleged that it had completed. A few days later, the PISD Board of Trustees resolved to terminate the agreements for what it deemed as Natex’s breach of the contracts. PISD gave written notice to Natex that termination was due to failure to provide “schematic design development documents for approval,” failure to “provide a schedule for any of the projects except the high school project,” failure to “complete any of its work in accordance with the schedule,” and for requests for “payment to which it is not entitled.”

PISD filed a suit against Natex, alleging that Natex had breached the contracts, asking the trial court for a declaration of the parties’ rights, and seeking recovery of sums already paid. The original petition alleged that Natex failed to timely provide them with necessary documents to allow the district to timely bid the project, causing them to suffer increased costs of labor and material. When Natex “finally did produce some ‘construction documents,’ they were so out of touch with Plaintiffs budget for the project that the documents that were produced were unusable.” PISD claimed Natex “failed to perform any substantial work pursuant to any of these contracts” despite having “been paid in excess of seven hundred thousand dollars for its work on the high school and stadium projects.” The petition complained that Natex had “requested additional sums of money in excess of that which it is due under the Agreement[s].” PISD further prayed the trial court to enter a declaration of rights of the parties under the contracts, reasonable attorney’s fees, and consequential damages for increased costs of construction due to the breach.

Natex answered the suit, claiming that delays were attributable to PISD’s failure to acquire lands for the projects in a timely manner and that PISD had also made demands of the designs which, if incorporated, would exceed the budget. Natex also filed a counterclaim for breach of contract for nonpayment of fees “currently due and owing by the District to Natex [in the] amount [of] $1,018,800.48 plus prejudgment interest.”

After the parties had conducted discovery for several months, PISD filed an amended petition adding claims of negligence, negligent misrepresentation, breach of fiduciary duty, and money had and received. In this amended petition, PISD claimed that Natex was negligent because it

failed to perform its duties with reasonable care, technical skill, ability, and diligence when it failed to timely coordinate a design team and employ professional engineers for the Projects, when it submitted billings to PISD that was not *731 supported by actual work performed on the Projects, and when it failed to communicate with PISD as is required to maintain an adequate progression of the work required on the Projects.

“Natex negligently represented that it could design the drawings and plans and specifications for the Projects with reasonable care, technical skill, ability, and diligence ordinarily required of Architects. It further negligently represented through billing invoices that it performed certain work on the Projects, when in fact, it had not.” PISD alleged further that Natex had breached a fiduciary duty and had received money “for work that it did not perform on the Projects and for alleged ‘construction documents’ that are useless to PISD and interest on those amounts.” To its amended petition, PISD attached the affidavit of Bruce Weir, “licensed Architect in the States [sic] of Texas.”

Weir’s supporting affidavit recited the usual predicatory statements of age and mental competency and then stated, “I am currently a practicing architect in good standing. I have over 28 years of experience in the design/construetion industry and have been a licensed practicing architect since 1990.” Weir’s affidavit opined that after having reviewed several documents itemized in his affidavit, he had concluded that the documents “indicate[d] that Natex failed to timely coordinate a design team and employ engineering professions [sic] for the Projects. Further, Natex failed to perform any of its duties for improvements to Travis Junior High School, Paris High School Renovations, Justiss Elementary School, Givens Elementary School, Crockett Elementary School, and the New Paris Athletic Stadium.” His affidavit recited that he had deduced that Natex’s failures to timely coordinate a design team and employ engineering professionals “[wa]s a departure from the reasonable care, technical skill, ability, and diligence required of Architects in the same or similar circumstances and constitutes negligence,” and that the “billing to PISD that was not supported by the actual work that was performed” and that its failure to communicate with PISD was also a departure from the standard of care.

Natex filed a motion to dismiss the suit based on Section 150.002 of the Texas Civil Practice and Remedies Code because when PISD filed its “Original Petition[,] the District failed to contemporaneously file a Certificate of Merit as required by the statute.” Alternatively, Natex argued that although “Plaintiffs First Amended Petition did attach an affidavit,” “that affidavit did not purport to serve as a certificate of merit, and it did not meet the specific requirements” of the statute. The trial court denied Natex’s motion to dismiss. Natex reasserts these arguments on appeal to support its complaint that the trial court erred in failing to dismiss PISD’s suit. 1

II. ANALYSIS

A. Standard of Review

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Dunham Engineering, Incorporated v. the Sherwin-Williams Company
404 S.W.3d 785 (Court of Appeals of Texas, 2013)
Morrison Seifert Murphy, Inc. v. Zion
384 S.W.3d 421 (Court of Appeals of Texas, 2012)
JJW Development, L.L.C. v. Strand Systems Engineering, Inc.
378 S.W.3d 571 (Court of Appeals of Texas, 2012)
M-E Engineers, Inc. v. City of Temple
365 S.W.3d 497 (Court of Appeals of Texas, 2012)
Pro Plus, Inc. v. Crosstex Energy Services, L.P.
388 S.W.3d 689 (Court of Appeals of Texas, 2012)
Sanders v. Wood
348 S.W.3d 254 (Court of Appeals of Texas, 2011)
Hardy v. Matter
350 S.W.3d 329 (Court of Appeals of Texas, 2011)

Cite This Page — Counsel Stack

Bluebook (online)
326 S.W.3d 728, 2010 Tex. App. LEXIS 8720, 2010 WL 4273909, Counsel Stack Legal Research, https://law.counselstack.com/opinion/natex-corp-v-paris-independent-school-district-texapp-2010.