Munson v. Duval

11 V.I. 615, 1975 U.S. Dist. LEXIS 5580
CourtDistrict Court, Virgin Islands
DecidedApril 15, 1975
DocketCivil No. 598-1973
StatusPublished
Cited by10 cases

This text of 11 V.I. 615 (Munson v. Duval) is published on Counsel Stack Legal Research, covering District Court, Virgin Islands primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Munson v. Duval, 11 V.I. 615, 1975 U.S. Dist. LEXIS 5580 (vid 1975).

Opinion

CHRISTIAN, Chief Judge

MEMORANDUM OPINION

This case in tort arises from an accident which occurred August 5, 1972. .Plaintiff, Lyle Munson, was engaged at [620]*620that time as a sandblaster for third-party defendant Communication Systems & Maintenance Corporation (CSM), of which he was also vice-president. CSM had been retained by defendant Liberty Hall Realty Company to do sandblasting on an old building in Frederiksted, St. Croix, Liberty Hall, which that company had recently purchased with the intention of remodeling and renovating it. Defendant Andre Duval, at all times pertinent to this action, was both a partner in Liberty Hall Realty Co., and the owner of the construction company hired by Liberty Hall as the independent contractor in the renovation project. Mun-son has brought suit against defendants seeking damages for alleged serious and permanent injuries he sustained when he fell some fifteen feet from a scaffold to the ground, while performing his job.1

The contract was negotiated by Ernest Whittaker, president of CSM, and Duval, who signed the contract as “Owner”. The contract, a standard form used in the regular course of business and prepared by CSM, contained the following provision as to scaffolding:

If scaffolding or swing staging is needed to do this work, it will be furnished by [CSM] unless otherwise arranged.

Whittaker testified, and Duval conceded at trial, after vehement denials in the pleadings, that the parties had agreed that since Duval would in any event provide scaffolding at the site for his own workmen, the initial contract price of $8,000 for the sandblasting job would be reduced to $6,000 in exchange for CSM’s use of the scaffolding already erected by Duval. Although the arrangement regarding the scaffolding was never reduced to writing, the written contract [621]*621did recite the lower figure, $6,000, as the price to be paid to CSM.

Whittaker testified that at the outset his men had attempted to do their work on normal working days when Duval’s crew was also on the site. However, from all accounts, sandblasting is a dirty, dusty and unpleasant job, and Whittaker claims that defendant’s foreman instructed him to do that work on weekends only in order to avoid interference with the other work going on at the site. Whittaker, Munson and Robert Jones all refer to defendant’s foreman as Ernie Smith. Duval denied that any person so named ever worked for him, and that his foreman’s name in fact was Ernie Miner. In light of the fact that all parties stated they dealt with someone of the same first name, I find that Ernie Smith and Ernie Miner are one and the same person, and was employed by defendant as foreman on the construction site. Whittaker does not recall whether or not Duval was present at the time of this conversation. Pursuant to this request, Munson and a crew of two arrived at Liberty Hall the weekend prior to the accident and proceeded, without event, to do sandblasting on the front of the building as required by the contract. When they arrived, they used the scaffolding provided by Duval, in place as they found it. On that day Munson himself had done the sandblasting, and had used a wooden ladder found near the place they were working, to climb to the upper tiers of the scaffolding. He stated at trial that he had used that ladder rather than the one built into the scaffold because it could be tilted at an angle, which made it easier to reach the platform on the very top of the structure. The scaffolding itself was of the metal, tubular sort, made up of three tiers, each of which was about six feet high. At each tier there was a platform made of plywood, on which the worker stood or sat while performing his job. At either side of the structure was a built-in metal ladder, which extended [622]*622up to just'a little short of the top of the scaffolding. That is, it ended approximately one foot below the platform of the uppermost tier. As shown on pictures admitted into evidence, there were no handrails extending past the last rung of these built-in ladders.

The following weekend, the day of the accident, Munson arrived at work with only one Robert Jones as crew. Both men were salaried employees of CSM, as opposed to the two men who had helped Munson the week before, who were paid by the hour. The scaffold was in a different location from where it had been when Munson had worked on the previous weekend, and I find that it had been moved by Duval’s crew sometime during .the week. Plaintiff says he and Jones used it exactly where they found it that Saturday morning. While Jones was on the scaffold, doing the actual sandblasting, plaintiff was on the ground tending the blasting pot.2 Jones, working on the second .tier of the scaffold, had looped the hose over the top of the structure and tied it with a rope to a pin of the scaffolding in order to keep it steady while he applied the nozzle. Noticing that the hose had become “snagged,” making it impossible to proceed further with his work, Jones called down to Munson asking him to go up and free the hose. After shutting down the blasting pot, Munson climbed to the third tier using the metal ladder built into the scaffolding. He said he did not use the wooden one he had used the previous week because it was not visible on the site. As he got to the top of the ladder he grabbed on to a piece of 2 x 4 which he supposed to be a toeboard, intending to support his weight on it and thus hoist himself up onto the platform. The 2x4 [623]*623which he grabbed, was not adequately secured and. he fell backwards down the full twelve to fifteen feet to the steps of the building. When he hit the ground, landing on his feet, he “crumbled up” and knocked his chin against a truck which was parked there. Jones testified that while Munson was lying injured.on the ground, he asked him what had happened, to which plaintiff replied that he had grabbed the toeboard and fallen. Jones further testified that when he looked up, he was able to see the toeboard “turned around” and sticking out at an angle from the scaffolding.

A toeboard, as used in the industry, is a piece of timber, in this case a 2 x 4, which is fastened by means of nails to the end of the platform on each level of the scaffold. According to all the parties and a witness, one Luis Suarez, who was accepted by the Court as -a safety expert, toe-boards serve three functions with regard to scaffolds. The first is to prevent tools or anything else from rolling over the side of the platform and down to the ground. The second is to warn workmen on the platform that they .are approaching the edge. Thirdly, and all persons except Duval agreed, toeboards are often used by workmen to hoist themselves up onto platforms, which is exactly what Munson attempted.to do.

Plaintiff bases his claim on the theory that defendants owed, him a duty of providing him with a safe place, and safe instrumentalities, with, and on which to work. He alleges several violations of that duty, namely the unsecured toeboard, the absence of handrails, and the failure of the attached ladder to extend at least thirty-six inches above the platform.

Defendant Liberty Hall moved, at the conclusion of the testimony, to have the Case dismissed as to it, a motion which was taken under advisement and is still pending. Plaintiff advances three arguments which he urges justify finding liability against the owner of the building. The first [624]

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Proctor v. North Shore Partners, Inc.
232 F. Supp. 2d 472 (Virgin Islands, 2002)
Figueroa v. Hess Oil Virgin Islands Corp.
198 F. Supp. 2d 632 (Virgin Islands, 2002)
Gass v. Virgin Islands Telephone Corp.
149 F. Supp. 2d 205 (Virgin Islands, 2001)
Monk v. Virgin Islands Water & Power Authority
53 F.3d 1381 (Third Circuit, 1994)
Harris v. No. 1 Contracting Corp. Excavation Construction Co.
22 V.I. 3 (Supreme Court of The Virgin Islands, 1986)
Gibson v. Sullivan Trail Coal Co.
608 F. Supp. 390 (Virgin Islands, 1985)
Schindel v. Pelican Beach Inc.
16 V.I. 237 (Supreme Court of The Virgin Islands, 1979)

Cite This Page — Counsel Stack

Bluebook (online)
11 V.I. 615, 1975 U.S. Dist. LEXIS 5580, Counsel Stack Legal Research, https://law.counselstack.com/opinion/munson-v-duval-vid-1975.