Municipality of Anchorage v. United States

980 F.2d 1320, 1992 WL 359737
CourtCourt of Appeals for the Ninth Circuit
DecidedDecember 9, 1992
DocketNos. 91-35321, 91-35643
StatusPublished
Cited by30 cases

This text of 980 F.2d 1320 (Municipality of Anchorage v. United States) is published on Counsel Stack Legal Research, covering Court of Appeals for the Ninth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Municipality of Anchorage v. United States, 980 F.2d 1320, 1992 WL 359737 (9th Cir. 1992).

Opinion

WIGGINS, Circuit Judge:

OVERVIEW

Plaintiffs challenge the district court’s dismissal of their claims that the Environmental Protection Agency (EPA) and the Army Corps of Engineers (the Corps) violated the Administrative Procedure Act (APA) and the National Environmental Policy Act (NEPA) in adopting a Memorandum of Agreement (MOA). The district court dismissed plaintiffs’ claims on defendants’ motion. We affirm.

BACKGROUND

Section 404(b)(1) of the Clean Water Act (CWA) requires the Administrator of the EPA, in conjunction with the Secretary of the Army, to develop guidelines for the-issuance of dredge and fill permits. 33 U.S.C. § 1344(b)(1) (1988). Pursuant to that section, the EPA promulgated dredge and fill permit guidelines in 1980, and the Corps adopted similar guidelines that were later revised in 1986.

In November, 1989, the EPA and the Corps signed an MOA, setting forth the policy and procedures to be used in determining the type and level of mitigation that would be required to comply with section 404(b)(1) guidelines. The purpose of the MOA was to provide guidance to field personnel in the exercise of their discretion under the guidelines, thereby making permit decisions more consistent and predictable. Because the. EPA and the Corps were convinced that the MOA was either an interpretation of the existing guidelines or a general policy statement and therefore exempt from the procedural requirements of 5 U.S.C. § 553, the MOA was adopted and published without the notice and comment period required for rulemaking under the Administrative Procedure Act (APA). See 5 U.S.C. § 553 (1988). In addition, because the EPA and the Corps believed that the MOA was exempt from the requirements of NEPA, they did not prepare an environmental impact statement (EIS) or otherwise comply with NEPA in adopting the MOA. See 42 U.S.C. § 4332 (1988).

Plaintiffs filed lawsuits alleging that adoption of the MOA violated 5 U.S.C. §§ 553 and 706 and 42 U.S.C. § 4332. After the district court consolidated the cases, EPA and the Corps moved to dismiss the claims. Plaintiffs also moved jointly for summary judgment. The district court granted the EPA and the Corps’ motion to dismiss, holding that the case was not ripe for adjudication. Plaintiffs appeal from that dismissal. This court has jurisdiction over this appeal pursuant to 28 U.S.C. § 1291.

DISCUSSION

Plaintiffs raise three issues on appeal. First, they contend that their APA challenges to the adoption of the MOA are ripe. Second, they argue that the MOA, in fact, violated the APA. Finally, they maintain that the EPA and the Corps failed to follow certain procedures required by NEPA in adopting the MOA.

I. Ripeness of Plaintiffs’ APA Claims

The first issue we address is the ripeness of plaintiffs’ APA claims. Ripe[1323]*1323ness for federal adjudication being a question of law, we review the district court’s decision de novo. See Southern Pac. Transp. Co. v. Los Angeles, 922 F.2d 498, 502 (9th Cir.1990) (citing Hoehne v. San Benito, 870 F.2d 529, 531 (9th Cir.1989)), cert. denied, — U.S.-, 112 S.Ct. 382, 116 L.Ed.2d 333 (1991).

The Supreme Court has indicated that ripeness is to be determined by the application of a two prong test. See Abbott Laboratories v. Gardner, 387 U.S. 136, 149, 87 S.Ct. 1507, 1515-16, 18 L.Ed.2d 681 (1967). In Abbott, the Court held that we must “evaluate both the fitness of the issues for judicial decision and the hardship to the parties of withholding court consideration.” Id.; see also Assiniboine & Sioux Tribes v. Board of Oil & Gas Conservation, 792 F.2d 782, 788 (9th Cir.1986). “[Rjipeness will prevent review if the systemic interest in postponing adjudication due to lack of fitness outweighs the hardship on the parties created by postponement.” Chavez v. Director, OWCP, 961 F.2d 1409, 1414 (9th Cir.1992) (citations omitted).

A. Fitness for Review

We will determine first the fitness for judicial review of plaintiffs' claim that the EPA and the Corps violated the notice and comment requirement of the APA. See 5 U.S.C. § 553 (1988). Generally, agency action is fit for review if the issues presented are purely legal and the regulation at issue is a final agency action. Abbott, 387 U.S. at 149, 87 S.Ct. at 1516; see also Assiniboine & Sioux Tribes, 792 F.2d at 789 (“Review is not premature if the agency action is final, and is ‘purely legal.’ ” (quoting Abbott)). However, the Supreme Court has indicated that there are instances when a purely legal challenge to a final agency action will not be considered ripe. In Toilet Goods Association v. Gardner, 387 U.S. 158, 87 S.Ct. 1520, 18 L.Ed.2d 697 (1967), decided the same day as Abbott, the Court held that a legal challenge to final agency action was not ripe because “judicial appraisal ... is likely to stand on much surer footing in the context of a specific application of th[e] regula-tion_” Id. at 164, 87 S.Ct. at 1524; see also Lujan v. Nat’l Wildlife Fed’n, 497 U.S. 871, 891, 110 S.Ct. 3177, 3190, 111 L.Ed.2d 695. (1990) (indicating that agency regulations are not ordinarily ripe for review until the “factual components [have been] fleshed out, by some concrete action applying the regulation_”); Trustees For Alaska v. Hodel, 806 F.2d 1378, 1381 (9th Cir.1986) (stating that agency action is fit for review if further factual development is not required).

In this case, the parties agree that the challenge to the MOA presents purely legal issues. We agree. However, whether the MOA is a final agency action is less clear. Just before oral argument in this case, President Bush proposed an amendment to the MOA that would change the agencies’ position substantially if adopted. The proposed amendment raises question as to whether the MOA can be characterized as a “definitive statement” of any agency’s position. See Mt. Adams Veneer Co. v. U.S.,

Free access — add to your briefcase to read the full text and ask questions with AI

Related

In re: Rose A. Romeo
Ninth Circuit, 2018
OKLEVUEHA NATIVE AMERICAN CHURCH v. Holder
676 F.3d 829 (Ninth Circuit, 2012)
Columbia v. Gregory, et al.
2008 DNH 167 (D. New Hampshire, 2008)
Verizon California Inc. v. Peevey
413 F.3d 1069 (Ninth Circuit, 2005)
City of Shoreacres v. Waterworth
332 F. Supp. 2d 992 (S.D. Texas, 2004)
City of Arcadia v. United States Environmental Protection Agency
265 F. Supp. 2d 1142 (N.D. California, 2003)
Democratic National Committee v. Watada
199 F. Supp. 2d 1018 (D. Hawaii, 2002)
Murphy v. Kenops
99 F. Supp. 2d 1255 (D. Oregon, 1999)
No. 98-35720
189 F.3d 1107 (Ninth Circuit, 1999)
Ross v. Alaska
189 F.3d 1107 (Ninth Circuit, 1999)
Association of American Medical Colleges v. United States
34 F. Supp. 2d 1187 (C.D. California, 1998)
Cross Timbers Concerned Citizens v. Saginaw
991 F. Supp. 563 (N.D. Texas, 1997)
Chief Probation Officers v. Shalala
118 F.3d 1327 (Ninth Circuit, 1997)
Conant v. McCaffrey
172 F.R.D. 681 (N.D. California, 1997)

Cite This Page — Counsel Stack

Bluebook (online)
980 F.2d 1320, 1992 WL 359737, Counsel Stack Legal Research, https://law.counselstack.com/opinion/municipality-of-anchorage-v-united-states-ca9-1992.