Mulhern v. Philadelphia Indemnity Insurance

802 F. Supp. 2d 317, 2011 U.S. Dist. LEXIS 90304, 2011 WL 3563126
CourtDistrict Court, D. Massachusetts
DecidedAugust 15, 2011
DocketCivil Action No. 10-10125
StatusPublished
Cited by4 cases

This text of 802 F. Supp. 2d 317 (Mulhern v. Philadelphia Indemnity Insurance) is published on Counsel Stack Legal Research, covering District Court, D. Massachusetts primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Mulhern v. Philadelphia Indemnity Insurance, 802 F. Supp. 2d 317, 2011 U.S. Dist. LEXIS 90304, 2011 WL 3563126 (D. Mass. 2011).

Opinion

MEMORANDUM AND ORDER ON CROSS-MOTIONS FOR PARTIAL SUMMARY JUDGMENT

STEARNS, District Judge.

The case arises from defendant Philadelphia Indemnity Insurance Company’s (Philadelphia Indemnity’s) denial of coverage for structural damage sustained by a building (Building) leased to Habit OPCO, Inc. (Habit). The damage is alleged to have been caused by construction at an adjacent site owned by Greater Boston Food Bank (GBFB).1 On January 27, 2010, Habit and Peter J. Mulhern, as trustee of Hermes Realty Trust and owner of the property (Property) on which the Building is located, brought this diversity action in the district court claiming breach of contract (Count I), and a violation of the Massachusetts Unfair or Deceptive Practices Act, Mass. Gen. Laws ch. 93A, § 11 (Count II). The parties filed cross-motions for partial summary judgment as to Count I on October 15, 2010. A hearing on the motions was held on January 11, 2011.

BACKGROUND

The material facts, in the light most favorable to the respective nonmoving parties, are as follows. In the early 1900s, portions of the Property were seasonally submerged. In 1931, the land surface was shored up with a layer of “urban fill.”2 When the Building leased to Habit was constructed, its exterior walls and interior column piers were buttressed with concrete piles driven deep enough into the earth to carry the Building’s weight. The floor was made of concrete slabs 4-6 inches thick and supported by pile caps, which were spaced between 12 to 25 feet apart. Each pile cap rested on 2-3 piles, spaced 1.3 to 1.5 feet apart. In the gaps [319]*319between the pile caps and the exterior foundation walls, the concrete slabs were supported by 2-A feet of urban fill.

In 1997, Mulhern converted the Building from a warehouse to a patient care facility and leased it to Habit. During the reconstruction, the concrete floor slabs were leveled, partition walls were erected, and a suspended ceiling system was installed. On October 27, 2007, Habit purchased a Commercial Lines Policy (Policy) from Philadelphia Indemnity to insure the Building against structural damage. The Policy ran from October 27, 2007 to October 27, 2008, and listed Mulhern as a loss payee.

On December 7, 2007, GBFB began construction of a new facility on property adjacent to Habit. The work required the sinking of concrete piles into the GBFB property. Between December of 2007 and mid-March of 2008, the builders drove 288 concrete piles to depths of almost 190 feet.

Habit employees first noticed signs of structural damage sometime between December 19, 2007, and January 17, 2008; however, the extent of the damage is disputed.3 The parties agree only that two door frames had cracked where the door jamb met the header and that some Building walls and sections of the clinic floor were no longer level. Philadelphia Indemnity also acknowledges that “[tjhese conditions did not exist before the pile driving began on the GBFB Property.” Stipulation of Facts ¶ 14. Habit complained on at least two occasions to the subcontractor responsible for the pile driving, who investigated and photographed the damage.

According to plaintiffs, on February 1, 2008, “the Building was hit by pile driving vibrations that were likely triple or more the federal damage threshold.”4 Id. By mid-February, Habit’s entrance hallway and its “motivation” room were showing distinct floor heaves, while the ceiling tiles were shifting and additional walls had begun cracking. On February 29, 2008, Habit wrote to Mulhern to complain about the structural damage. On March 11, 2008, Habit’s insurance broker formally notified Philadelphia Indemnity of the claim. Philadelphia Indemnity began an investigation. It hired McArdle Gannon Associates, Inc. (McArdle), to perform an analysis and recommend remedial steps. The investigation revealed

movement, heaving and cracking of the concrete floor slab, movement and separation of the interior partition walls from the concrete floor slab, upward movement of the suspended ceiling system attached to partition walls, and the distortion of door frames. The Building’s masonry block walls and interior columns (both of which were set on piles) did not sustain any damage.

Stipulation of Facts ¶ 17. McArdle determined that

vibrations from pile driving on the GBFB Property traveled through the ground and caused alterations to the [320]*320layer of urban fill and organic deposits beneath the Building’s concrete floor slabs. This, in turn, caused the Building’s concrete floor slab to lose its structural support in areas not supported by pile caps. Without that support, the concrete floor slabs shifted, settled and developed structural cracks. As the floor slabs settled, the Building’s interior partition walls (built atop the slabs), its suspended ceiling system and door frames also moved and sustained structural damage.

Id. ¶ 20. McArdle’s final report concluded that “pile driving operations directly adjacent to the site for the Greater Boston Food Bank Project [are] primarily responsible for the floor slab settlement experienced to date.” Am. Compl. ¶ 20. McArdle estimated the cost of repair of the subsurface damage at $1,200,000, exclusive of reconstruction costs. McArdle warned that any short term repair, such as slab jacking, would only mask the underlying problems.5

On July 7, 2008, Habit filed a claim by email with Philadelphia Indemnity after the three-year-old rubber roof of the Building developed a split of .75 inches along forty feet of its center. The split compromised the nearby storm drains. Habit also reported water bubbling up through the floor near the dispensary. Habit repaired the roof immediately, although the expense was out-of-pocket because the effects of the GBFB construction had voided the roofs warranty. On July 21, 2008, Habit filed another claim by email when a different portion of the roof cracked, leading to severe flooding that forced Habit to shut down patient counseling sessions for the day. Habit again made immediate repairs at a cost of $115,000 to keep the clinic open.

On November 24, 2008, Philadelphia Indemnity issued a check in the amount of $30,000 to compensate for water damage as of a “loss” date of July 20, 2008. On December 15, 2008, Philadelphia Indemnity denied the claim for structural damage, citing the Policy’s “Earth Movement” exclusion. The exclusion states:

1. We will not pay for loss or damage caused directly or indirectly by any of the following. Such loss or damage is excluded regardless of any other cause or event that contributes concurrently or in any sequence to the loss....
b. Earth Movement
(1) Earthquake, including any earth sinking, rising or shifting related to such event;
(2) Landslide, including any earth sinking, rising or shifting related to such event;
(3) Mine subsidence, meaning subsidence of a man-made mine, whether or not mining activity has ceased

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Nurse v. Omega US Insurance, Inc.
38 N.E.3d 759 (Massachusetts Appeals Court, 2015)
Espedito Realty, LLC v. National Fire Insurance
849 F. Supp. 2d 179 (D. Massachusetts, 2012)

Cite This Page — Counsel Stack

Bluebook (online)
802 F. Supp. 2d 317, 2011 U.S. Dist. LEXIS 90304, 2011 WL 3563126, Counsel Stack Legal Research, https://law.counselstack.com/opinion/mulhern-v-philadelphia-indemnity-insurance-mad-2011.