Mount Shasta Bioregional Ecology Center v. County of Siskiyou

210 Cal. App. 4th 184, 148 Cal. Rptr. 3d 195, 42 Envtl. L. Rep. (Envtl. Law Inst.) 20217, 2012 Cal. App. LEXIS 1088
CourtCalifornia Court of Appeal
DecidedSeptember 26, 2012
DocketNo. C064930
StatusPublished
Cited by31 cases

This text of 210 Cal. App. 4th 184 (Mount Shasta Bioregional Ecology Center v. County of Siskiyou) is published on Counsel Stack Legal Research, covering California Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Mount Shasta Bioregional Ecology Center v. County of Siskiyou, 210 Cal. App. 4th 184, 148 Cal. Rptr. 3d 195, 42 Envtl. L. Rep. (Envtl. Law Inst.) 20217, 2012 Cal. App. LEXIS 1088 (Cal. Ct. App. 2012).

Opinion

Opinion

HULL, J.

In November 2008, defendant Siskiyou County (County) approved a project to expand an existing wood veneer manufacturing facility owned by real party in interest Roseburg Forest Products Co. (Roseburg) in order to permit cogeneration of electricity for resale (Project). Plaintiffs Mount Shasta Bioregional Ecology Center (MSBEC) and Weed Concerned Citizens (WCC) filed a petition for writ of mandate against the County and [190]*190the County Board of Supervisors (Board) claiming approval of the Project and certification of the environmental impact report (EIR) for the Project violated the California Environmental Quality Act (CEQA) (Pub. Resources Code, § 21000 et seq.). The trial court denied the petition.

Plaintiffs appeal, contending the EIR for the Project failed to include an adequate analysis of alternatives and failed to fully disclose, analyze and mitigate air quality, noise and water impacts of the Project. We agree there are some minor deficiencies and inaccuracies in the EIR for the Project but conclude they did not prejudice the environmental review process. We therefore affirm the judgment of the trial court.

Facts and Proceedings

In the mid-1980’s, Roseburg purchased an existing wood products manufacturing facility on more than 300 acres adjacent to the City of Weed in an unincorporated area of the County and converted it into a softwood veneer processing operation. In 1996, Roseburg replaced eight boilers at the facility with a single, 120,000-pound-per-hour boiler.

In 2006, Roseburg sought approval of an expansion of the existing facility to accommodate a biomass-fueled cogeneration powerplant, whereby heat generated in the boiler could be used both for the veneer manufacturing process and for the generation of electricity for resale. The proposed Project “would include upgrading and retrofitting the existing power facility within the existing boiler house with a 15-megawatt steam-driven cogeneration system, including a General Electric turbine generator, a new exterior cooling tower, and a new electrical substation consisting of a 50-foot tall communications tower and control building.” The Project equipment would be housed on less than one acre of the total 300-acre site, and the closest residence to the Project site would be approximately 250 feet away.

Much of the fuel for the Project will be generated at the facility and other manufacturing facilities from the bark and trim removed from logs used in the wood veneer production. Other fuel would come from forest management activities in the surrounding region, including community fuel breaks and firesafe thinning.

As stated in the EIR for the Project: “The overarching objective of the proposed project is to generate and sell excess power that is efficiently produced using sustainably-harvested renewable resources, offsetting the need for additional electricity generated from the burning of fossil fuels to support Roseburg’s own facility operations. The purpose of the proposed project is also to aid the state power grid as a whole and help reduce regional energy [191]*191shortfalls, and meet state air quality attainment goals by reducing air pollutants and greenhouse gas emissions.”

On December 6, 2006, the County Planning Commission (Planning Commission) approved a categorical exemption from CEQA and a conditional use permit for the Project. Nine days later, MSBEC and others appealed the Planning Commission’s decision.

Roseburg later withdrew its application and submitted a new one. On June 29, 2007, the County issued a notice of preparation of an EIR for the Project.

On April 18, 2008, the County, as the lead agency, released for public review and comment a draft environmental impact report (DEIR) for the Project. Among other things, the DEIR estimates that, with implementation of the Project, approximately 15 truck trips per day, five days per week, with a peak of 27 trips per day during four months in the fall and winter, will be required to bring additional fuel to the facility. The DEIR also explains that “steam and resulting condensate (steam that has cooled and has converted back to a liquid state) would be processed in a closed-loop system, resulting in no off-site discharge of water product from the boiler or turbine.”

Regarding the source for Project water, the DEIR states; “Water usage for Roseburg originates from Boles and Beaughton Creeks, both of which are adjudicated. Beaughton Creek serves a portion of the City of Weed, as well as a local water bottling plant. The dominant water use on site comes from Boles Creek, which is used for sprinkling the log decks through a recirculated sprinkler system. Additional uses include water for the log vats, dryer washing and boiler operation.” The DEIR indicates current water consumption at the facility is 64,000 gallons per day (gpd) and the Project will require an additional 56,000 gpd. However, because this total of 120,000 gpd is below historic water usage during the 1990’s of 123,000 gpd and below the current maximum allowable consumption by Roseburg of 1,467 million gallons per year (mgy), the DEIR concludes no mitigation of water impacts will be needed.

Regarding air quality issues, the DEIR indicates; “The proposed project will also include the installation of pollution control equipment. [County Air Pollution Control District] Rule 6.1 requires that best available control technology for [nitrogen oxides (NOx)] be applied as part of the project. This will include selective non-catalytic reduction equipment to control emissions of NOx from the boiler. In addition, the project applicant has committed to installing filtration to control diesel particulate matter emissions from the fuel handling equipment (i.e., Bobcat and front-end loader).”

On the issue of Project noise, the DEIR indicates major information comes from two noise studies, one prepared by Environmental and Occupational [192]*192Risk Management (EORM) dated February 19, 2007 (the EORM Report), and one prepared by ExperShare dated July 27, 2007 (the ExperShare Report). The DEIR contains a table, “Table 3.7-2,” summarizing 15-minute average sound levels at various locations in the community around the Project site, as reflected in the EORM Report. Another table, “Table 3.7-3,” summarizes noise measurements from the ExperShare Report. According to the DEIR, the daytime noise measurements are below the County’s daytime noise standard but above Weed’s daytime noise standard in some locations, whereas all nighttime noise measurements are above Weed’s nighttime noise standard.

The DEIR adopts a significance standard for Project noise that requires both that the new equipment increase noise in adjacent areas by at least 3.0 decibels (dB) and that overall noise in such areas exceeds the applicable County or Weed noise standard. Based on the EORM Report, the DEIR indicates predicted noise increases from the new Project equipment will be 0.5 A-weighted decibels (dBA), which represents an overall frequency-weighted sound level in dB that approximates the frequency response of the human ear. The DEIR also predicts noise increases from Project equipment and increased truck traffic together to be only 1.0 dBA. Hence, the DEIR concludes the noise impact from the Project will not be significant.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Russian Riverkeeper v. City of Ukiah CA1/3
California Court of Appeal, 2024
Hammond Landowners Assn. v. City of Weed CA3
California Court of Appeal, 2022
Martis Camp Community Assn. v. County of Placer
California Court of Appeal, 2020
San Franciscans for Livable Neighborhoods v. City & Cnty. of S.F.
236 Cal. Rptr. 3d 893 (California Court of Appeals, 5th District, 2018)
Tehachapi First v. City of Tehachapi CA5
California Court of Appeal, 2016
Japanese Village v. Los Angeles County MTA CA2/5
California Court of Appeal, 2015

Cite This Page — Counsel Stack

Bluebook (online)
210 Cal. App. 4th 184, 148 Cal. Rptr. 3d 195, 42 Envtl. L. Rep. (Envtl. Law Inst.) 20217, 2012 Cal. App. LEXIS 1088, Counsel Stack Legal Research, https://law.counselstack.com/opinion/mount-shasta-bioregional-ecology-center-v-county-of-siskiyou-calctapp-2012.