Moss v. Tommasi Construction, Inc.

37 So. 3d 492, 9 La.App. 3 Cir. 1419, 2010 La. App. LEXIS 640, 2010 WL 1779692
CourtLouisiana Court of Appeal
DecidedMay 5, 2010
Docket09-1419
StatusPublished
Cited by8 cases

This text of 37 So. 3d 492 (Moss v. Tommasi Construction, Inc.) is published on Counsel Stack Legal Research, covering Louisiana Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Moss v. Tommasi Construction, Inc., 37 So. 3d 492, 9 La.App. 3 Cir. 1419, 2010 La. App. LEXIS 640, 2010 WL 1779692 (La. Ct. App. 2010).

Opinion

PICKETT, Judge.

| ,The defendant, Don Shaw, appeals a decision of a Workers’ Compensation Judge (WCJ) finding him, personally, the employer of the claimant, Gerald Moss, and liable for all compensation benefits plus $6,000.00 in penalties, $17,500.00 in attorney’s fees and the interest on all elements of the award. The claimant also appeals, listing five alleged legal errors made by the WCJ. The claimant, further, seeks additional attorney’s fees for this appeal. We affirm the decision of the WCJ and award the claimant $4,000.00 in additional attorney’s fees for work on this appeal.

FACTS

The claimant, Moss, who was employed by Leonard Darson, was severely injured when he fell off a scaffold on January 5, 2008, while installing Hardi Plank (a synthetic wood) siding. He had been hired by Darson to install the siding on an apartment complex which was being built by Don Shaw, a Lake Charles businessman. After the accident, Darson disappeared and, as of the trial, was still missing.

In order to build the complex, building permits were required. Shaw, who is not a contractor, and thus, who was unable to obtain the necessary permits, entered into a verbal agreement with a friend, Louis “Tony” Tommasi, owner of Tommasi Construction to “pull” the necessary permits and to “oversee” the project. During the trial of this matter, one of the contested issues was the nature of that agreement. Shaw claimed he hired Tommasi as his general contractor, while Tommasi maintained that he was engaged as a “consultant” to oversee the project and to obtain the needed permits, which could only be obtained by a person/firm holding a general contractor’s license. Tommasi and Shaw had collaborated before on several projects. The two | ¿never worked via written contracts, but by verbal agreement. From the depositions of the two men, it appears that Tommasi performed some functions of a general contractor, ie. he obtained the needed permits listing himself as contractor on the project, and he supervised the work of the subcontractors. However, Tommasi neither paid for the building materials nor paid the subcontractors, but rather he verified to Shaw that work had been completed so that Shaw would pay the subcontractors.

Shaw also performed some functions of a general contractor, although he is not licensed as such. Shaw hired all the subcontractors, signed any written contracts that were entered into with the subcontractors (for instance, electrical and plumbing), paid for materials, and paid the subcontractors as Tommasi reported their work was completed.

Neither Shaw nor Tommasi inquired if any of the subcontractors carried workers’ compensation insurance. Shaw stated that the “thought didn’t cross my mind.” Both Shaw and Tommasi were insured by LEM-IC Insurance Company — Shaw for his insurance business and Tommasi for his contracting business.

*495 The apartment project was progressing amicably, without incident, until the claimant fell off the scaffold on which he was working, severely injuring his ankle and sustaining additional injuries to his leg and knee.

When the claimant looked to Darson for workers’ compensation benefits, it was discovered that Darson had no workers’ compensation insurance. Shortly thereafter, Darson disappeared. The claimant then looked to Shaw, Tommasi, and/or LEMIC for benefits. All denied coverage, and this suit commenced.

| «ASSIGNMENTS OF ERROR

On appeal Gerald Moss, the claimant, filed two briefs, one as appellant and one as appellee. As appellant, Moss argues the WCJ committed several errors: (1) in not finding Tommasi the general contractor for the project; (2) in not finding Dar-son, Shaw and Tommasi Construction soli-dary obligors; (3) in not awarding him an increase of 50% of the indemnity amount as per La. R.S. 23:1171.2; (4) in allowing Shaw to rely on the fee schedule and to pay the medical providers directly; and (5) in not finding that LEMIC Insurance Company, provided coverage for this claim. The claimant also seeks additional attorney’s fees for work necessitated by this appeal.

As appellee, Moss completely agrees with the WCJ that Darson was his direct employer, but, under the circumstances of this case, Shaw is his employer by law and, as such, is responsible for any sums for which Darson is liable. We agree with Moss’s argument as appellee, and we reject most of his arguments as appellant.

Don Shaw also appears as both appellant and appellee. As appellee, he argues that the WCJ was correct in ordering payment of medical expenses to be paid per the fee schedule, directly to the medical providers. As appellant, he argues that the WCJ erred in finding him liable for the benefits owed Moss, in awarding Moss penalties and attorney’s fees, and in finding that his workers’ compensation policy with LEMIC did not provide coverage for this claim.

We agree with Shaw’s arguments as ap-pellee, but we reject his arguments as appellant.

|„LAW AND DISCUSSION

The standard of review applicable in workers’ compensation cases was set out by our supreme court in Dean v. Southmark Const., 03-1051, p. 7 (La.7/6/04), 879 So.2d 112, 117 (citations omitted), wherein the court stated:

In worker’s compensation cases, the appropriate standard of review to be applied by the appellate court to the OWC’s findings of fact is the “manifest error-clearly wrong” standard. Accordingly, the findings of the OWC will not be set aside by a reviewing court unless they are found to be clearly wrong in light of the record viewed in its entirety. Where there is conflict in the testimony, reasonable evaluations of credibility and reasonable inferences of fact should not be disturbed upon review, even though the appellate court may feel that its own evaluations and inferences are as reasonable. The court of appeal may not reverse the findings of the lower court even when convinced that had it been sitting as the trier of fact, it would have weighed the evidence differently. The determination of whether injury occurred in the course and scope of employment is a mixed question of law and fact.

The case before us rests mainly on the conflicting testimony of two of the parties: Don Shaw, the owner and financier of the *496 project, and Tony Tommasi, the owner of Tommasi Construction, Inc. We have no contracts to examine between Shaw, Tom-masi, and Darson, and there is no evidence that Darson carried workers’ compensation insurance. The record shows that both Shaw and Tommasi carried workers’ compensation insurance, Shaw for his insurance business and Tommasi for his construction company.

In Rosell v. ESCO, 549 So.2d 840, 844-45 (La.1989) (citations omitted) our supreme court explained the manifest error/clearly wrong standard:

When findings are based on determinations regarding the credibility of witnesses, the manifest error — clearly wrong standard demands great deference to the trier of fact’s findings; for only the factfinder can be aware of the variations in demeanor and tone of voice that bear so heavily on the listener’s understanding and belief in what is said.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
37 So. 3d 492, 9 La.App. 3 Cir. 1419, 2010 La. App. LEXIS 640, 2010 WL 1779692, Counsel Stack Legal Research, https://law.counselstack.com/opinion/moss-v-tommasi-construction-inc-lactapp-2010.