Moscatiello v. Pittsburgh Contractors Equipment Co.

595 A.2d 1198, 407 Pa. Super. 378, 16 U.C.C. Rep. Serv. 2d (West) 86, 1991 Pa. Super. LEXIS 2175
CourtSuperior Court of Pennsylvania
DecidedJuly 30, 1991
Docket1556
StatusPublished
Cited by20 cases

This text of 595 A.2d 1198 (Moscatiello v. Pittsburgh Contractors Equipment Co.) is published on Counsel Stack Legal Research, covering Superior Court of Pennsylvania primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Moscatiello v. Pittsburgh Contractors Equipment Co., 595 A.2d 1198, 407 Pa. Super. 378, 16 U.C.C. Rep. Serv. 2d (West) 86, 1991 Pa. Super. LEXIS 2175 (Pa. Ct. App. 1991).

Opinion

HESTER, Judge:

Curbmaster, Inc. appeals from the judgment entered on the August 21,1990 order of the Allegheny County Court of Common Pleas which denied appellant’s post-trial motions and awarded appellee, Pittsburgh Contractors Equipment Co. (“PCEC”), the right to indemnification from appellant. *381 Appellant raises numerous allegations of trial court error. We remand on the issue of set-off of damages, but in all other respects, we affirm.

The action underlying this appeal was a breach of contract suit which appellee, Franco Moscatiello i/a, t/d/b/a Moscatiello Construction Company (“Moscatiello”), filed against PCEC to recover damages incurred from the purchase of a defective concrete spreading machine (“paver”). The paver was sold by PCEC and manufactured by Curb-master for use by Moscatiello in the reconstruction of a road in Pittsburgh.

On or about May 19, 1987, Moscatiello and PCEC entered into a contract for the purchase of a Curbmaster concrete spreader machine for a total price of $85,125.42. Approximately one month before the contract was executed, Franco Moscatiello and his superintendent, Jay Palino, met with the vice president of PCEC to discuss the purchase of the paving machine. At the time of the meeting, PCEC was aware that Moscatiello had been awarded a contract by the Pennsylvania Department of Transportation (“PennDot”) to reconstruct a road and that PennDot required that the concrete surface of the road be laid by a certain type of paving machine.

Appellant also participated in these preliminary discussions. The vice president of Curbmaster had a telephone conversation with PCEC and Moscatiello in which he suggested that either of two machines manufactured by Curb-master would be suitable for the PennDot job. Reproduced Record (“R.R.”) at 92-93a, 340-41a, 432a, 492a.

The purchase agreement executed by Moscatiello and PCEC stated on the reverse side that no warranties were offered on equipment sold and that any implied warranties were excluded in favor of the manufacturer’s offer of warranties. The contract also contained a provision which limited the buyer’s remedy solely to return of the purchase price, less wear and use of the machine. In addition, all consequential and incidental damages were expressly excluded. Moscatiello had no previous dealings with PCEC *382 and was not on notice that the sales agreement relinquished warranties and limited damages.

In order to obtain the paver for Moscatiello, PCEC entered into a second sales agreement (the “Curbmaster contract”) with the manufacturer of the machine, Curbmaster. Pursuant to the Curbmaster contract, Curbmaster agreed to manufacture the paver and sell it to PCEC for $68,-693.42. Curbmaster also warranted that the product would be free from defects in material and workmanship under normal use and service for ninety days. The warranty specifically and expressly disclaimed all other warranties, express, implied or statutory, including warranties of merchantability and fitness. It limited the buyer’s remedies to repair, replacement, or return of the purchase price, and excluded liability for all consequential damages.

The trial court found, however, that the Curbmaster warranty agreement was a different document than the sales agreement. The testimony at trial established that the warranty agreement typically is found as an attachment to the Curbmaster owners and parts manual. No witness could establish with certainty that the warranty agreement ever reached either PCEC or Moscatiello.

The paver was manufactured by Curbmaster at its plant in Iowa and shipped to Pittsburgh, arriving at Moscatiello’s job site on June 15, 1987. A Curbmaster employee was present when the paver arrived, assisted Moscatiello employees in assembling it, instructed Moscatiello employees on how to operate the machine, and was present when the machine was used for the first time.

According to the testimony of four witnesses during the trial, from the time that the machine first was used in June, 1987, to on or about November 12, 1987, when it was used last, it failed to lay concrete evenly. Furthermore, the product which resulted was unacceptable to PennDot. Throughout the five-month period of the paver’s operation, Moscatiello made numerous complaints to PCEC about the paver’s failure to produce an acceptable product. During this period, PCEC and Curbmaster unsuccessfully attempt *383 ed numerous times to remedy the defects in the machine. The machine finally was returned to Curbmaster in December, 1987. As a result of the failure of the paver to perform its functions properly, Moscatiello incurred increased labor costs in order to produce a product acceptable to PennDot.

On February 8, 1988, Moscatiello filed a complaint against PCEC asserting breach of contract, breach of express warranty, breach of implied warranty of merchantability, and breach of implied warranty of fitness for a particular purpose. PCEC joined Curbmaster as an additional defendant, asserting breach of express warranty, breach of implied warranties of merchantability and fitness for a particular purpose, and negligence. By agreement of the parties, PCEC dismissed its negligence claim against Curbmaster and amended its complaint to add a claim against Curbmaster for breach of contract.

Following a bench trial, the trial court issued an opinion and order dated March 14, 1990, awarding $146,811.43 in damages plus interest to Moscatiello and against PCEC and Curbmaster jointly. Both PCEC and Curbmaster filed timely post-trial motions for relief, and on August 21, 1990, the trial court issued an opinion and order denying Curbmaster’s post-trial motions and granting PCEC’s post-trial motion only insofar as it related to PCEC’s right of indemnification from Curbmaster. Curbmaster filed this timely appeal from the trial court’s order of August 21, 1990. 1

Curbmaster first argues that the trial court erroneously based its grant of indemnification to PCEC upon a principle of tort rather than contract law. Curbmaster asserts that the “mere conduit” theory whereby the manufacturer of defective goods must indemnify the seller acting as a mere conduit between the consumer and the manufacturer applies only to tort actions for personal injury or property damage and not to complaints, such as the instant *384 action, alleging economic losses resulting from a breach of contract.

In granting PCEC the right of indemnification from Curb-master, the trial court relied upon several landmark cases in this area of law, including Kassab v. Central Soya, 432 Pa. 217, 246 A.2d 848 (1960), Spagnol Enterprises, Inc. v. Digital Equipment Corp., 390 Pa.Super. 372, 568 A.2d 948 (1989), Walasavage v. Marinelli, 334 Pa.Super. 396, 483 A.2d 509 (1984), and Klages v. General Ordnance Equipment Corp., 240 Pa.Super. 356,

Related

Bachtell v. General Mills, Inc.
M.D. Pennsylvania, 2019
Buttaccio v. American Premier Underwriters, Inc.
175 A.3d 311 (Superior Court of Pennsylvania, 2017)
Traxler v. PPG Industries, Inc.
158 F. Supp. 3d 607 (N.D. Ohio, 2016)
Lombard Metals Corp. v. AMG Resources Corp.
Superior Court of Pennsylvania, 2015
Ulmer, D. v. L.F. Driscoll Co.
Superior Court of Pennsylvania, 2015
Berg Chilling Systems, Inc. v. Hull Corp.
369 F.3d 745 (Third Circuit, 2004)
Messer Griesheim Industries, Inc. v. Cryotech of Kingsport, Inc.
131 S.W.3d 457 (Court of Appeals of Tennessee, 2003)
Messer Griesheim dba MG Industries v. Cryotech
Court of Appeals of Tennessee, 2003
Weiler v. SmithKline Beecham Corp.
53 Pa. D. & C.4th 449 (Philadelphia County Court of Common Pleas, 2001)
Greiner v. Erie Insurance Exchange
57 Pa. D. & C.4th 312 (Philadelphia County Court of Common Pleas, 2001)
Montgomery County v. MicroVote Corp.
152 F. Supp. 2d 784 (E.D. Pennsylvania, 2001)
Green v. Saturn Corp.
50 Pa. D. & C.4th 347 (Philadelphia County Court of Common Pleas, 2000)
Duall Bldg. v. 1143 EAST JERSEY
652 A.2d 1225 (New Jersey Superior Court App Division, 1995)
Israel Phoenix Assur. Co., Ltd. v. SMS Sutton, Inc.
787 F. Supp. 102 (W.D. Pennsylvania, 1992)
Moscatiello v. Pittsburgh Contractors Equipment Co.
595 A.2d 1190 (Superior Court of Pennsylvania, 1991)

Cite This Page — Counsel Stack

Bluebook (online)
595 A.2d 1198, 407 Pa. Super. 378, 16 U.C.C. Rep. Serv. 2d (West) 86, 1991 Pa. Super. LEXIS 2175, Counsel Stack Legal Research, https://law.counselstack.com/opinion/moscatiello-v-pittsburgh-contractors-equipment-co-pasuperct-1991.