Morse Boulger Destructor Co. v. Arnoni

101 A.2d 705, 376 Pa. 57, 1954 Pa. LEXIS 412
CourtSupreme Court of Pennsylvania
DecidedJanuary 11, 1954
DocketAppeals, Nos. 93, 108 and 109
StatusPublished
Cited by25 cases

This text of 101 A.2d 705 (Morse Boulger Destructor Co. v. Arnoni) is published on Counsel Stack Legal Research, covering Supreme Court of Pennsylvania primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Morse Boulger Destructor Co. v. Arnoni, 101 A.2d 705, 376 Pa. 57, 1954 Pa. LEXIS 412 (Pa. 1954).

Opinion

Opinion by

Mr. Justice Chidsey,

There are three appeals in this case, the appeal of Mariano C. Arnoni, the appeal of Caesar P. Arnoni, and the joint appeal of Mariano C. Arnoni and Caesar P. Arnoni. All appeals are from the order of the court below granting plaintiff’s motion for a new trial after the court directed a verdict in favor of Caesar P. Arnoni and the jury had found a verdict in favor of Mariano C. Arnoni. ....

In February, 1947, suit was instituted by the plaintiff a Delaware corporation, against Mariano C. Arnoni and his son, Caesar P. Arnoni, individually ánd [59]*59as partners trading under the name of M. C. Arnoni and Son.1 In November, 1946, defendant Mariano C. Arnoni retained one John F. Laboon as a consulting engineer for the proposed erection of a garbage and refuse incinerator in Snowden Township, Allegheny County, Pennsylvania. Laboon prepared specifications for the construction of the incinerator, and sent copies thereof to prospective bidders. The plaintiff corporation’s bid of |105,600 was embodied in a letter sent by the plaintiff on February 12, 1947 to M. C. Arnoni and Sons. At the bottom of the letter appeared the words “Dated” and “Accepted”. Following these words respectively are the date of “Feb. 13, 1947” and the signature of M. C. Arnoni. The letter of February 12th lists certain changes from a sketch previously submitted by plaintiff to defendants, and then provides in the last paragraph: “It is understood and agreed that there are no other changes involved besides those outlined above. The acceptance of this order is contingent upon a mutual agreement as to terms of payment, and the approval of same by the Morse Boulger Destructor Company credit department.”.

On February 24, 1947 there was another letter from the plaintiff corporation to M. C. Arnoni & Sons which set forth additional modifications. This letter provided in part: “. . . The modifications as included above shall be considered as a part of the contractual agreement of Feb. 12th as accepted by Mr. Arnoni on behalf of M. C. Arnoni & Sons and J. P. Beacom for the Morse Boulger Destructor Company. . . . Terms of payment —85% of the value of material delivered and work in place, or according to a payment schedule approved by [60]*60Mr. Laboon and the final payment to be made within 30 days after the completion of the work of this contract.”. At the bottom of this letter appears the following :

“Accepted for M. C. Arnoni & Sons
(Signed) M. C. Arnoni
Accepted for Morse Boulger Destructor Company
(Signed) T. J. Kelley & (Signed) J. P. Beacom
Dated 2-25-47”

On March 4, 1947, Laboon sent a letter to plaintiff corporation in which he requested it to execute three copies of an enclosed formal agreement with the explanation that an agreement in such form was required for financing purposes. The three copies were executed by plaintiff and returned to defendants on March 13, 1947. Neither of the defendants ever executed or returned these formal agreements.

The factual issue presented was whether the letters of February 12, 1947 and February 24, 1947, each of which, as above appears, was addressed to M. C. Arnoni & Sons and accepted in writing by M. C. Arnoni, together were intended by the parties to constitute a complete contract.

Plaintiff introduced testimony by Thomas J. Kelley, vice-president and sales manager of the plaintiff corporation, and Patrick J. Beacom, its field representative, both of whom signed the letters on behalf of plaintiff, and also the testimony of John F. Laboon, the consulting engineer for the defendants, all of which was to the effect that it was intended and understood by all of the parties that upon the execution of the acceptance by M. C. Arnoni appearing on plaintiff’s letter of February 24, 1947, the contract was finally and fully agreed upon. Mariano C. Arnoni and Caesar P. Arnoni testified that they had no intention to enter a binding contract until the plan's and specifications [61]*61liad been approved by the Commissioners of Allegheny County, and it was not until they were assured by Beacom that the contract was not binding that Mariano C. Arnoni affixed his signature to the letter of February 24th.

Laboon, Kelley and Beaeom all testified that the final agreement was arrived at and accepted by Mariano C. Arnoni in Baboon’s office in the City-County Building in Pittsburgh, and that those three and both Arnonis were present at that time. Mariano C. Arnoni testified that Kelley, Beaeom and Laboon were present when he signed his acceptance upon the letter of February 24, 1947, as well as his son, Caesar P. Arnoni, and that he had no recollection of whether he signed the letter in the City-County Building or in Baboon’s office in the Berger Building. Caesar P. Arnoni testified that at the time Mariano C. Arnoni’s acceptance was noted on the letter of February 24, 1947, only he, his father and Beaeom were present and that the meeting was in the Berger Building.

There was therefore a decided conflict in the testimony as to the place where the letter of February 24, 1947 was signed as accepted by M. C. Arnoni, the surrounding circumstances and the intention of the parties at that time. Baboon’s testimony that following the events of February 24th and 25th, plaintiff proceeded to enter into subcontracts and order material was uncontradicted. Defendants admitted in the pleadings, and it was read into the testimony that certain materials were delivered on the site and refused by Mariano C. Arnoni on or about July, 1947.

In connection with the conflict in the testimony, it should be noted that John F. Laboon, whose testimony supported plaintiff’s version, had been retained by the defendants as consulting engineer to be in charge of the construction of the garbage disposal plant. De[62]*62fendants suggest no reason -why the testimony of La-boon, who was acting on their behalf, was completely contrary in all material respects to their own testimony. Among other points of such conflict was the testimony concerning the financing of the project by the defendants. Both Arnonis- testified that on February 25th, prior to the date Mariano C. Arnoni signed his acceptance on the letter of February 24th, there was a discussion concerning the financing of the construction and that the agreement was contingent upon their ability to obtain the necessary financing. Laboon testified that the question of financing first arose sometime in March.

Where there is an appeal from an order granting a new trial, the question before this Court is whether there has been a palpable abuse of discretion by the court below: Gawron v. Levine, 373 Pa. 384, 96 A. 2d 149. The presumption is that the grant of a new trial is justified even when the reason given therefor is insufficient, unless the Court expressly states it is the only reason: Foster v. Waybright, 367 Pa. 615, 80 A. 2d 801.

In the opinion of the lower court, four reasons were assigned for the grant of a new trial: (1) that the court erred in affirming defendants’ 15th point for charge; (2) a remark made by one of the jurors as the jury retired for its deliberations; (3) in justice a new trial should be granted; and (4) “It is significant that Mr.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Barrie v. Pennsylvania Liquor Control Board
5 Pa. D. & C.4th 174 (Alleghany County Court of Common Pleas, 1990)
Porter v. Commonwealth
309 A.2d 709 (Supreme Court of Pennsylvania, 1973)
Sechan Limestone v. Commonwealth
288 A.2d 553 (Commonwealth Court of Pennsylvania, 1972)
Wilson v. Pennsylvania Railroad
219 A.2d 666 (Supreme Court of Pennsylvania, 1966)
Penneys v. Segal
189 A.2d 185 (Supreme Court of Pennsylvania, 1963)
Williams Retail Stores, Inc. v. Toltzis
184 A.2d 596 (Superior Court of Pennsylvania, 1962)
Corn Exchange National Bank & Trust Co. v. Burkhart
165 A.2d 612 (Supreme Court of Pennsylvania, 1960)
Murosky v. Spaulding
166 A.2d 34 (Supreme Court of Pennsylvania, 1960)
HAYES v. Stephenson
161 A.2d 900 (Superior Court of Pennsylvania, 1960)
Geelen v. Pennsylvania Railroad
161 A.2d 595 (Supreme Court of Pennsylvania, 1960)
Frontage, Inc. v. Allegheny County
162 A.2d 1 (Supreme Court of Pennsylvania, 1960)
Hyndman v. Pennsylvania Railroad
152 A.2d 251 (Supreme Court of Pennsylvania, 1959)
Bizich v. Sears, Roebuck & Co.
139 A.2d 663 (Supreme Court of Pennsylvania, 1958)
Sherman v. Manufacturers Light & Heat Co.
132 A.2d 255 (Supreme Court of Pennsylvania, 1957)
Smith v. L. Blumberg's Son, Inc.
130 A.2d 437 (Supreme Court of Pennsylvania, 1957)
Werner v. Aunkst
115 A.2d 416 (Superior Court of Pennsylvania, 1955)
Edelson v. Ochroch
111 A.2d 455 (Supreme Court of Pennsylvania, 1955)
Rice v. Ford
2 Pa. D. & C.2d 543 (Schuylkill County Court of Common Pleas, 1954)

Cite This Page — Counsel Stack

Bluebook (online)
101 A.2d 705, 376 Pa. 57, 1954 Pa. LEXIS 412, Counsel Stack Legal Research, https://law.counselstack.com/opinion/morse-boulger-destructor-co-v-arnoni-pa-1954.