Morgan v. Stokely-Van Camp, Inc.

663 P.2d 1384, 34 Wash. App. 801, 36 U.C.C. Rep. Serv. (West) 1535, 1983 Wash. App. LEXIS 2452
CourtCourt of Appeals of Washington
DecidedMay 31, 1983
Docket10371-7-I
StatusPublished
Cited by18 cases

This text of 663 P.2d 1384 (Morgan v. Stokely-Van Camp, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals of Washington primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Morgan v. Stokely-Van Camp, Inc., 663 P.2d 1384, 34 Wash. App. 801, 36 U.C.C. Rep. Serv. (West) 1535, 1983 Wash. App. LEXIS 2452 (Wash. Ct. App. 1983).

Opinion

Callow, J.

Plaintiff Gene Morgan appeals a trial court judgment which found defendant Stokely-Van Camp, Inc., not liable for payment for 27 acres of Morgan's peas. The sole issue is whether the trial court erred when it admitted evidence extrinsic to the written contract.

In 1976, Gene Morgan, a Skagit County farmer, entered into a written contract (Morgan-Stokely contract) with Stokely-Van Camp, Inc., whereby Stokely agreed to purchase 336 acres of peas being grown by Morgan. The Morgan-Stokely contract was a form contract with a yearly "rider" attached specifying the variety of peas, acreage per variety, and the price schedule. That year, Stokely harvested only 301 acres of Morgan's peas. Morgan filed suit alleging that Stokely had bypassed 37 acres of his peas and had failed to pay him for the bypassed peas. Of the 37 acres in dispute, only 27 acres are relevant to this appeal.

The discrepancy between the 336 acres contracted for and the 301 acres harvested was not unusual. Testimony was admitted on the parties' course of dealing from 1973 to 1977. Except for the year 1977, the acres of peas harvested by Stokely usually differed from the acres contracted for. The difference between the two figures was due to the method by which Stokely contracted for the peas. Although the contract amount is expressed in terms of acres, the farmer is paid by the tonnage of peas harvested. Stokely arrived at the proposed contract figure by estimating the *803 yield of peas per acre of land. Then the farmers would look at the counter on their seed drill to find out how many acres of peas were actually planted. That figure would be submitted to Stokely as the final contract figure. There was ample testimony on the custom and usage between the farmers and processors in regard to the amount of acres contracted for and the amount harvested and paid for. Following is an excerpt of certain testimonies of Stokely employees—Elmer Overway, field superintendent, Bob Roedell, field man, and Clyde Miller, operations manager.

[Elmer Overway]
Q With regard to this trade and custom and usage we just talked about, you said the acreage would vary from the contract either plus or minus. Was it a common practice in the area to initial or amend the contract in writing?
A I have never seen it done, never have gone back with the contract.
Q Has Stokely experienced any problems with farmers in that regard?
A Never have.
[Bob Roedell]
Q Isn't it a fact that you didn't really contract a field. You were just contracting a total number of acres; isn't that what you do?
A Only when they give us an amount, oh, a large grower like that. The amount of acres is what we are after, yes, but when it comes to planting—
Q What I am asking you is did you contract for acres? Do you contract for fields? It is acres, isn't it?
A Under the approval that the field will meet our specs, yes.
Q Do you recall your deposition taken on June 24, 1980, page 10. I want you to look there on lines 16 and 17 where you say, "Here again we contract acres but we pay by the ton." Is that what you said on that day?
A Yes, that's a true statement.
[Clyde Miller]
Q Mr. Miller, do your records, Stokely records reflect whether or not the acres harvested, planted and har *804 vested for Mr. Morgan in any of the years that he was under contract, did they vary from the written number of acres shown?
A Yes, in the five years we contracted with Mr. Morgan, 1977 was the only year where it came out even, the acres contracted versus the acres harvested.
Q Do you recall how the years ran?
A In 1977, the acres harvested were 197.
Q Which year?
A 1973, and contracted were 200, the net difference is minus three. We contracted three more than we harvested. In 1974 the acres harvested was 346. Three hundred sixteen were contracted. That is plus 30 we harvested, 30 more than we contracted that year. In 1975 the acres harvested were 362. The acres contracted were 374. That is a net result of minus 12. We harvested 12 acres less than we contracted. ... In 1977, it came out even.
Q Were any of those contracts for those years you have talked about amended in writing?
A No.
Q Any notes or marks on them?
A No. I point out that in 1977 there were 67 acres contracted. That is a small amount so it is much more logical that we would come out even. When you are dealing in larger numbers, . . . you have much more room for diverging from the original.

The 27 acres of peas involved in this appeal were grown on a parcel of land commonly known as the "Wallace field." The first year in which Morgan farmed the Wallace field was 1976. Whenever a farmer wished to farm a new field, Stokely would check the new field before planting to ensure that the field was suitable for their purposes. Morgan claims that Stokely knew of his plan to include the Wallace field in his contract figure of 336 acres. On the other hand, Stokely denies assenting to Morgan's plans. Stokely claims that after they checked the field, they informed Morgan that the field was unsuitable for Stokely's purposes and that Morgan acknowledged the unsuitability and offered to find other acreage to complete the total contract figure but would nonetheless go ahead with his plan to cultivate the *805 Wallace field; if the peas matured on time, Stokely agreed to harvest the peas.

The peas on the Wallace field matured 10 days after Stokely had harvested Morgan's other acres of peas. Stokely never harvested or swathed the Wallace field since the peas did not mature until Stokely had moved its harvesting operation to another area.

The trial court found that the parties had a different agreement with respect to the Wallace field than that expressed in the written contract; that the risk of loss was upon Morgan; and because the Wallace field failed to mature at the same time as Morgan's other fields, Morgan assumed the risk of loss. Stokely was held not liable or responsible for the Wallace field.

The Morgan-Stokely contract is governed by the Uniform Commercial Code. Goods, as defined by the U.C.C., include "the unborn young of animals and growing crops and other identified things attached to realty as described in the section on goods to be severed from realty". RCW 62A.2-105.

(2) A contract for the sale apart from the land of growing crops . . . capable of severance without material harm [to the realty] is a contract for the sale of goods within this Article . .

Free access — add to your briefcase to read the full text and ask questions with AI

Related

SER U-Haul v. Hon. Paul Zakaib, Jr., Judge
West Virginia Supreme Court, 2013
State ex rel. U-Haul Co. v. Zakaib
752 S.E.2d 586 (West Virginia Supreme Court, 2013)
Spradlin Rock Products, Inc. v. Public Utility District No. 1
164 Wash. App. 641 (Court of Appeals of Washington, 2011)
SPRADLIN ROCK v. Public Utility Dist. No. 1
266 P.3d 229 (Court of Appeals of Washington, 2011)
Prime Start Ltd. v. MAHER FOREST PRODUCTS LTD.
442 F. Supp. 2d 1113 (W.D. Washington, 2006)
Lopez v. Reynoso
118 P.3d 398 (Court of Appeals of Washington, 2005)
Diamond v. Granite Falls School Dist.
70 P.3d 966 (Court of Appeals of Washington, 2003)
Diamond "B" Constructors, Inc. v. Granite Falls School District
70 P.3d 966 (Court of Appeals of Washington, 2003)
Allapattah Services, Inc. v. Exxon Corp.
61 F. Supp. 2d 1300 (S.D. Florida, 1999)
Graaff v. Bakker Bros. of Idaho, Inc.
934 P.2d 1228 (Court of Appeals of Washington, 1997)
U.S. for Use of Waldow v. Stan Palmer Const., Inc.
959 F.2d 243 (Ninth Circuit, 1992)
Bremerton Concrete Products Co. v. Miller
745 P.2d 1338 (Court of Appeals of Washington, 1987)
Emrich v. Connell
705 P.2d 288 (Court of Appeals of Washington, 1985)

Cite This Page — Counsel Stack

Bluebook (online)
663 P.2d 1384, 34 Wash. App. 801, 36 U.C.C. Rep. Serv. (West) 1535, 1983 Wash. App. LEXIS 2452, Counsel Stack Legal Research, https://law.counselstack.com/opinion/morgan-v-stokely-van-camp-inc-washctapp-1983.