Moran Towing Corp. v. M. A. Gammino Construction Co.

244 F. Supp. 729, 1965 U.S. Dist. LEXIS 7492
CourtDistrict Court, D. Rhode Island
DecidedAugust 12, 1965
DocketAdmiralty No. 1824; Civ. A. No. 2868
StatusPublished
Cited by9 cases

This text of 244 F. Supp. 729 (Moran Towing Corp. v. M. A. Gammino Construction Co.) is published on Counsel Stack Legal Research, covering District Court, D. Rhode Island primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Moran Towing Corp. v. M. A. Gammino Construction Co., 244 F. Supp. 729, 1965 U.S. Dist. LEXIS 7492 (D.R.I. 1965).

Opinion

DAY, District Judge.

These cases, involving common questions of law and fact, were consolidated for trial and were tried to the Court without a jury. In Admiralty No. 1824, the libellant Moran Towing Corporation (hereinafter called “Moran”) seeks to recover for damages allegedly caused to its dump scows, Moran 104 and Moran 106 and its tug, the Julia C. Moran, as the result of the alleged negligence and breach of contract by the respondent M. A. Gammino Construction Company (hereinafter called “Gammino”). It seeks recovery of the sum of $352,238.91 for alleged damages (including loss of use) to said scows, and the sum of $5,-127.68 for alleged damages (including loss of use) to said tug.

Civil Action No. 2868 is an action brought under the provisions of 40 U.S. C.A. § 270b (the Miller Act, so-called) for the use of Moran against Hartford Accident & Indemnity Company (hereinafter called “Hartford”) as the surety on a payment bond furnished by Gam-mino pursuant to its contract with the United States of America for the construction of a breakwater at Newport, Rhode Island. In this action Moran seeks judgment in its favor for like amounts against the surety. It claims that said damages to its scows and tug were caused by Gammino’s breach of their contract and that the labor and material required to repair said damages were labor and material furnished by it in the prosecution of the work provided for in Gam-mino’s contract for the construction of said breakwater.

The trial of these cases consumed many days and produced a voluminous record, including many exhibits. From the evidence adduced during said trial it appears that on February 5, 1960 Gammino entered into a contract with the United States of America to construct a breakwater at the United States Naval Base at Newport, Rhode Island, for the sum of $3,790,000. Pursuant to said contract, Gammino, as principal, and Hartford, as surety, executed and furnished to the United States of America a payment bond in the penal sum of $1,516,000, dated February 5, 1960, and conforming to the requirements of said Miller Act.

Subsequently, on or about April 21, 1960, Moran and Gammino entered into a written agreement in the form of a letter, prepared by Moran, addressed to Gammino, and then approved and accepted in writing by Gammino, under which Moran agreed to furnish the services of said steel bottom scows, Moran 104 and Moran 106, and a seagoing tug to transport breakwater stone as required under Gammino’s contract with the United States of America from a loading dock at Tiverton, Rhode Island, to said [731]*731breakwater site. The quantity of breakwater stone to be transported was estimated by the parties to be approximately 800,000 net tons.

Gammino agreed to pay for the services of said dump scows and tug at the rate of forty-three (43) cents per net ton of stone transported (determined by Moran on the basis of transporting 96,-000 net tons each two week period) with a specified minimum charge of $41,280. for each two week period that the scows and tug were used.

Other pertinent provisions of said agreement were as follows:

“1. You will provide a suitable loading berth with a minimum depth of water of 18 feet at mean low water, and with sufficient length for two (2) dump scows to lay safely alongside the dock whether light or loaded, and with sufficient depth of water to navigate between the regular channel and the loading berth.
“2. You are to provide facilities capable of loading the scows with 8,000 net tons per 24 hour period including time necessary for shifting at the loading berth. You are to properly load each scow to a draft determined and directed by Moran’s representative who will be present during load- • ing operation. We estimate that the two (2) dump scows can transport a minimum of 8,000 net tons per 24-hour period, weather permitting, based on 4-dumper loads of 2,000 tons each and a maximum in excess of 10,000 tons.
“3. The stone to be transported hereunder shall consist of quarry run stone 50% of a size 200 lbs. per piece or less, 45% of a size from 200 lbs. to 1000 lbs. per piece, and the remaining 5% of a size not in excess of 1500 lbs. per piece, provided, however, that if it is demonstrated through experience that pieces weighing more than 1000 lbs. are causing damage to the scows or interfering with the dumping process, then and in either event the limitations as to weight per piece shall be 1000 lbs.
“4. At the breakwater site, you shall arrange the operation so that the dump scows may be promptly unloaded and you shall provide a barge, properly moored at the dumping site, to which the dump scows shall be made fast by you prior to dumping. The captain of each dump scow shall release the load under your direction, and as your Agent. We shall not be responsible in any way whatsoever for the proper positioning of the dump scow prior to dumping. Immediately after the dumping has been accomplished, your personnel shall release the dump scow and the tug shall proceed to the loading berth without delay.
“5. It is estimated that each scow carrying a minimum of 2000 net tons will be drawing 15' of water and an additional 10' under the scow is required for the free dumping of the load. Accordingly no dumping will be done in any areas having less than 25' depth of water except that dumping in areas having less than 25' depth of water may be accomplished from the middle pocket of the scow (after all pockets except the middle pocket have been dumped) in areas having less than 25' depth of water provided there is at least 10' of water under the scow in such area and also provided such partial dumping does not result in substantial delay at the breakwater site.
“9. We shall be responsible for all ordinary wear and tear to our vessel equipment due to the nature of the material to be transported, but you shall be responsible for any damage to our vessel equipment due to your negligence, or for any damage to our vessel equipment whether or not due to your negligence that may be occasioned by loading or unloading of pieces weighing in excess of 1000 lbs. per piece.”

[732]*732Pursuant to this agreement, Moran furnished said dump scows, Moran 104 and Moran 106, and the tug Julia C. Moran, for the transportation of said stone from a loading berth at Tiverton, Rhode Island, to said breakwater site during the period beginning June 22, 1960 and ending December 3, 1960. The scows had been constructed in 1955 at a cost of approximately $272,000 each. Between March, 1955 and June, 1960, they had been used at the Moran dump board in the City of New York where they were loaded with waste materials of all types, such as rock and earth excavations, broken concrete, etc., for disposal at sea. At this board they were loaded from trucks which dumped their loads over the edge of the dump board a distance of between 25 and 30 feet into the hoppers of the scows. Each of the scows is 168 feet long, 43 feet wide and 151/2 feet deep, measured from the top of the deck to the underside of the bottom. Each has seven hoppers or pockets numbered 1 to 7, from bow to stern. Each hopper is 33 feet wide at the top, approximately 11 feet wide where the slope plates in each hopper meet the well plates, and has a fore and aft length of approximately 18 feet at the top.

Each hopper contains two sets of slope plates, two sets of well plates, two hopper doors at the bottom thereof, two sets of cables and two sets of chain guards.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
244 F. Supp. 729, 1965 U.S. Dist. LEXIS 7492, Counsel Stack Legal Research, https://law.counselstack.com/opinion/moran-towing-corp-v-m-a-gammino-construction-co-rid-1965.