W. E. Hedger Transp. Co. v. Columbia Transp. Co.

64 F. Supp. 191, 1945 U.S. Dist. LEXIS 1614
CourtDistrict Court, W.D. New York
DecidedAugust 3, 1945
DocketNo. 2155
StatusPublished
Cited by2 cases

This text of 64 F. Supp. 191 (W. E. Hedger Transp. Co. v. Columbia Transp. Co.) is published on Counsel Stack Legal Research, covering District Court, W.D. New York primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
W. E. Hedger Transp. Co. v. Columbia Transp. Co., 64 F. Supp. 191, 1945 U.S. Dist. LEXIS 1614 (W.D.N.Y. 1945).

Opinion

KNIGHT, District Judge.

Libellant sues to recover damages claimed to have been sustained at Buffalo, Erie County, New York, September 24, 1943, by reason of negligence in the unloading of pig iron from the steamer G. G. Post, owned by the respondent, the Columbia Transportation Company, onto the libellant’s barges Broadway and Earl F. Foster.

The claimant had agreed with the American Steel and Wire Company to transport the pig iron from Duluth, Minn., to Buffalo, New York, and libellant engaged with the latter company to transport the same from Buffalo via such barges.

[192]*192The Post is of steel construction and of the type of ship known as self-unloader, in which the unloading is done by means of a crane or cranes on the deck. The Post is equipped with two cranes mounted on a circular tract, so that the crane can revolve for a full 360 degrees, and fitted with a long boom, each crane having free swinging magnets 77 inches in diameter, 15 inches high, each weighing about 8 tons, with capacity to carry about 11 or 12 tons of pig iron suspended by a cable on a boom. The magnets are raised, lowered and otherwise operated by machinery by a wheelsman or mate in a cab built in the structure of the crane. In the method of the operation of the crane, the magnet is dropped into the hold of- the vessel being unloaded; the magnet attracts the load; the load is lifted and swung into a position' in which it is deposited in the barge or vessel alongside. So-called crane No. 1 was employed in the loading of both barges.

The Earl F. Foster is a barge 117 feet long, 30.9 feet beam, and 12.9 feet deep with seven hatch openings of about 12 feet between beams. The cargo hold flooring in the Foster is three by twelve fir or pine, and the bottom planks 4" by 10". The keelsons run fore and aft, enclosed between the floor of the cargo compartment and the bottom planking. The center keelson is 12" by 12", and there are ten sister keelsons each 6" by 12" spaced evenly between the center keelson and either side of the barge. The bottom planks run athwartship the barge and áre spiked to the underside of the keelson.

The barge Broadway is 111.3 feet long, 30.5 feet wide, and 12.5 feet deep.

Besides the men who were regularly employed on the Post, respondent for the purpose of expediting the work engaged several stevedores to assist in the unloading, and one of these was a so-called signalman whose duty it was to direct the unloading. While the unloading of the Foster was going on, and when about 70 tons of pig had been placed in two of the aft hatches, it was discovered that water had risen in the cargo space for a height of several feet, and an employee of the libellant called libellant’s manager of its fleet of barges then at the dock, and at the latter's suggestion, pig to the weight of about 25 tons was put in No. 1 hatch, for the purpose of trying to even the barge up, but this did not relieve the condition. Water in the cargo hold continued to rise to a height of about 6 feet at the stern end and about 2 or 3 feet at the bow. Pumps were employed to remove the water, and the pig was thereafter transferred back to the Post by the use of both cranes and magnets. It was then found a steel rail about 3 feet in length was stuck in a vertical position in the flooring of the barge, and later investigation revealed that it had penetrated through the bottom planking about 4 inches. This penetration was between the fifth and sixth cargo hold stanchions, between the first and second keelsons to port of the center keelson. Later examination of the barge disclosed that one bottom plank under No. 4 cargo hold was down 2 inches from the center line and for an athwartship distance of 10 feet, and one bottom plank under No. 5 cargo hold stanchion was sprung down 1 inch at the center line and for an athwartship distance of 6 feet, and the caulking in the vicinity of these planks had been opened up. A piece of pig was found imbedded in the floor at a point between No. 3 and No.. 4 keelsons to port of the center keelson between No. 4 and No. 5 stanchions. The hanging knees on No. 5 and No. 6 cargo holds under the main beams, port side, were found to have been pulled down and the fastening started. No. 8 cargo hold stanchion was split for a distance of about 6 feet, and the barge was discovered to be hogged in the center. The “bilge” ceiling (or floor) was broken to ah extent requiring replacement of 384 lineal feet. The foregoing statement is substantially uncontradicted.

The evidence given by several witnesses called by the libellant was to the effect that the interior of the cargo hold of the Foster had been examined by them shortly prior to the loading in question, that the holds had been swept clean; there was no material break in them; that braces between the stanchions through the center of the barge and between the center stanchions and the king posts had been installed shortly before this loading for the purpose of strengthening the barge for carrying pig, and further that the barge did not leak before the loading in question. The Foster had carried several cargoes of pig prior to this time during the 1943 season. Its last cargo before the day in question had been “Bauxite” ore -in the form of a powder.

Surveyors called by the respondents, one representing the insurance underwriters and the other representing the respondents, testified that the center keelson under the [193]*193center post was rotted to a depth of 8 inches, that the stanchions had settled in this keelson 1 inch, that one of the sister keelsons showed a rotted condition, that several king posts at the sides of the cargo hold showed rot, and some of the knees, other than those above mentioned, were in the same condition, that caulking was loose on the side of the interior of the barge, and that there were numerous holes in the floor of the cargo hold. It is undenied that the butts of the deck planking at the stern end of the barge had been pulled away from the covering board about 2 inches in the center and about 1% inches at each side, and had been filled and caulked in, and further that this was an old separation. One of the surveyors called by the respondents in his report stated that the beam knees No. 4, 5 and 6 on the port side were down and “there were indications that that was a fresh separation.” This statement agrees with the report and testimony of the libellant’s surveyor.

It is admitted that damage was done through the unloading. By reason of the location and the position of the iron rail in the floor and bottom, it is reasonably concluded that the iron rail was unloaded with the pig. The position in which it was found, penetrating as it did, both the floor and the bottom planking, is sufficient proof that it was either dropped with great force from the magnet, or that after being dropped it was driven through the floor and the botton plank by the weight of the load of the magnet dropped on it. Clearly this penetration was the first source of leakage and primal cause of damage. As respondents’ captain said: “There’s your trouble.”

It is claimed that in the loading of the Broadway, which preceded the loading of the Foster, the magnet of the crane hit the A frames of the barge, struck under the deck and swung against the cabin, breaking partitions and a window glass. The report of the captain of the Broadway said “damage done to ‘A’ frame. Posts 1, 3, 4, 6 bent over. Forward side and center of Captain’s cabin bent in and lining broken and one small window broken.” The “A” frame is a superstructure on the top of the hatch kams 4 or 5 feet in height.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Moran Towing Corp. v. M. A. Gammino Construction Co.
244 F. Supp. 729 (D. Rhode Island, 1965)

Cite This Page — Counsel Stack

Bluebook (online)
64 F. Supp. 191, 1945 U.S. Dist. LEXIS 1614, Counsel Stack Legal Research, https://law.counselstack.com/opinion/w-e-hedger-transp-co-v-columbia-transp-co-nywd-1945.