Moossy v. Huckabay Hospital, Inc.

283 So. 2d 699, 1973 La. LEXIS 6319
CourtSupreme Court of Louisiana
DecidedSeptember 24, 1973
Docket52868
StatusPublished
Cited by13 cases

This text of 283 So. 2d 699 (Moossy v. Huckabay Hospital, Inc.) is published on Counsel Stack Legal Research, covering Supreme Court of Louisiana primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Moossy v. Huckabay Hospital, Inc., 283 So. 2d 699, 1973 La. LEXIS 6319 (La. 1973).

Opinion

283 So.2d 699 (1973)

Louis E. MOOSSY
v.
HUCKABAY HOSPITAL, INC.

No. 52868.

Supreme Court of Louisiana.

September 24, 1973.
Rehearing Denied October 26, 1973.

*700 C. P. Brocato, Brocato & Mangham, W. Gene Carlton, Shuey, Smith & Carlton, Shreveport, for plaintiff-applicant.

Henry Bethard, III, Bethard & Bethard. Coushatta, for defendant-respondent.

BARHAM, Justice.

We are required to interpret a written contract between these parties to determine if it is the complete agreement between them and if it expresses the intent of the parties, especially in regard to the price for services rendered by one of the parties. The trial and appellate courts resorted to parol evidence to fix the contractual terms. We conclude the written contract is the complete agreement of the parties, and that the parol evidence was erroneously considered.

On January 13, 1966, Huckabay Hospital, Inc., through its President, Jackie D. Huckabay, M. D., entered into a contract with Louis E. Moossy, an architect, for the architectural services necessary for constructing a 40-bed hospital in Coushatta, Louisiana. The contract was made on the standard American Institute of Architects form but required work of the architect under three phases, rather than the usual four provided under that standard form. The architect was to provide, under the preliminary design phase, preliminary design studies and a general description of the Project for approval by the Owner. The design phase clause also provided that the architect "* * * should submit to the Owner a statement of the probable project construction cost based on current area, volume or other unit costs". Phase 2 was the Construction Documents Phase, which required the final design setting forth in detail the information necessary for bidding and letting of a contract, and required the Architect to keep the Owner informed of any adjustments to previous statements of the probable project construction cost. Phase 3 provided for the construction phase of the hospital and included the obligation of the Architect to assist the Owner in obtaining proposals from contractors and in awarding and preparing the construction contracts.

The Architect's fee for the basic services was to be calculated at 7% of the project construction cost. Extra services were under a separate contract, and services rendered in connection with air conditioning were to be calculated on a different basis. The standard termination clause in the contract was altered by the following insertion:

"The following shall be a part of this contract, and if this Section D is in conflict with any other provision or provisions of this contract Section D shall control and govern.
1. The owner may terminate this contract at any stage by giving written notice to the Architect and thereafter the Architect will perform no further service.
2. In the event this contract is terminated, the Architect shall be paid only for such services as he has performed and for such obligations and expenses that he has incurred (including fees of *701 engineers) to the date of the termination. In the event such termination should come after completion of the preliminary studies the fee shall be as stated in the contract and should the termination be made after the completion of final plans and specifications the fee shall be as stated in the contract.
3. The Architect shall perform no extra services or incur any extra expense whatsoever, and the Owner shall not be responsible for the payment of any sums beyond the seven per cent. (7%) of the project construction cost and the four per cent. (4%) of the cost of air conditioning and for work let under separate contract, unless the Owner specifically authorizes the extra work and extra expense in writing and which authorization shall specifically state the extra work and expense and the sum or sums the Owner is to pay therefor."

In regard to the basic services fee of 7 per cent of the "project construction cost", the contract dictated that the "project construction cost" would be determined by one of the following (priority to be determined by the order in which the provisions appear):

(a) The lowest acceptable bona fide bid;
(b) The estimate of project construction cost if under a fixed limit.
(c) The Architect's latest statement of probable project construction cost.
Although the contract provided:
"If the estimated project construction cost or the lowest bona fide proposal is in excess of any limit stated herein, the Owner shall give written approval of an increase in the limit, or he shall cooperate in revising the project scope or quality, or both, to reduce the cost as required",

no limit of construction cost was in the contract. The Architect's fee was to be paid as follows:

"Upon completion of preliminary studies a sum equal to 25% of the basic rate computed upon a reasonable estimated cost.
* * Construction Document Phase:
Upon completion of specifications and working drawings a sum sufficient to increase payments on the fee to 75% of the basic rate and other rates arising from this agreement, computed upon a reasonable cost estimated on such completed specifications and drawings, or if bids have been received, then computed upon the lowest bona fide bid or bids.
* * * Construction Phase:
From time to time during the course of construction and in proportion to the amount of service rendered by the Architect, payments shall be made until the aggregate of all payments made on account of the fee shall a sum equal to the basic rate and other rates arising from this agreement, computed upon the entire and final cost of the work."

The preliminary plans were completed on March 1, 1966, submitted to the Owner, and on April 8, 1966, Dr. Huckabay paid $5,250, pursuant to a billing of March 31, 1966, for that amount, with a note stating:

"Note: Preliminary estimate equals $442,486.00. However, as a consideration to Dr. Jackie D. Huckabay at this time, the figuer of $300,000 will be used and the architectural fee will be adjusted according to the actual construction cost after bids are taken." (Emphasis here and elsewhere supplied).

On September 12, 1966, the second cost estimate of $499,210.00 was submitted to Dr. Huckabay. It was noted:

"The above estimate is approximate and general. The above estimate does not include paving, future expansion or demolishing or altering existing buildings. A more accurate estimate may be obtained upon completion of working drawings and specifications."

*702 After receiving this revised cost estimate, a plan sheet, # 2, which indicated alterations and changes made in response to requests by Dr. Huckabay, was submitted. Dr. Huckabay wrote to Moossy on September 21, 1966 as follows:

"* * * The changes look fine to me, and I am pleased with the plans thus far."

Later, on November 7, 1966, Dr. Huckabay, in a letter to Moossy requesting some changes which would incur additional costs, stated additionally:

"* * * Otherwise, everything seems to be in good order and I am generally well pleased, except, of course, I would like to have had the plans completed sooner.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Crupe v. Huval Bakery, Inc.
544 So. 2d 119 (Louisiana Court of Appeal, 1989)
Parlay Enterprises v. Rb-Co., Inc.
504 So. 2d 660 (Louisiana Court of Appeal, 1987)
Williams Engineering, Inc. v. Goodyear
496 So. 2d 1012 (Supreme Court of Louisiana, 1986)
Williams Engineering, Inc. v. Goodyear
480 So. 2d 772 (Louisiana Court of Appeal, 1985)
Ortolano v. Snowizard Mfg., Inc.
476 So. 2d 359 (Louisiana Court of Appeal, 1985)
Jacoby v. State
434 So. 2d 570 (Louisiana Court of Appeal, 1983)
RG Claitor's Realty v. Juban
391 So. 2d 394 (Supreme Court of Louisiana, 1980)
Farnet v. Minyard
383 So. 2d 440 (Louisiana Court of Appeal, 1980)
Rhodes v. National Homes Corp.
263 S.E.2d 84 (West Virginia Supreme Court, 1979)
Kleinschmidt, Brassette & Associates v. Ayres
368 So. 2d 1153 (Louisiana Court of Appeal, 1979)
Lawrence v. St. Mary's Dominican College
343 So. 2d 1204 (Louisiana Court of Appeal, 1977)
Firmin v. Garber
343 So. 2d 245 (Louisiana Court of Appeal, 1977)

Cite This Page — Counsel Stack

Bluebook (online)
283 So. 2d 699, 1973 La. LEXIS 6319, Counsel Stack Legal Research, https://law.counselstack.com/opinion/moossy-v-huckabay-hospital-inc-la-1973.