Firmin v. Garber

343 So. 2d 245, 1977 La. App. LEXIS 4665
CourtLouisiana Court of Appeal
DecidedFebruary 14, 1977
DocketNo. 10874
StatusPublished
Cited by3 cases

This text of 343 So. 2d 245 (Firmin v. Garber) is published on Counsel Stack Legal Research, covering Louisiana Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Firmin v. Garber, 343 So. 2d 245, 1977 La. App. LEXIS 4665 (La. Ct. App. 1977).

Opinion

SARTAIN, Judge.

This is an appeal from a judgment of the district court affirming an arbitrator’s award. • We reverse and remand.

On September 16, 1968, Kenneth R. Gar-ber (appellant) entered into a contract with James L. Firmin (appellee) whereby the latter was to prepare plans and specifications for the construction of a residence. The instrument itself is AIA Document B131, entitled “Standard Form of Agreement Between Owner and Architect.” It provided for a fee of ten percent of the construction cost to be paid according to the following percentages:

Schematic Design Phase.15%
Design Development Phase .... 357„
Construction Documents Phase . . 757
Bidding or Negotiation Phase . . 807
Construction Phase .100%

The contract itself does not provide for a cost limitation. It simply states, “It is the intention of the Owner to erect a new residence near Patterson, Louisiana.” The question of cost is an issue. Appellant contends that the construction limit was to be $60,000.00.

The lowest bid received was $110,270.00. Efforts to reduce the cost by modifying the original plans proved unsuccessful. A second set of plans was prepared. Initially, appellant and his wife assisted appellee. However, before these plans were ready for bidding appellant advised the architect that he and his wife had decided to wait a “couple of years” before proceeding with the construction of a new home. Communication between appellant and appellee ceased. Nonetheless, appellee obtained a negotiated bid on these later plans in the amount of $79,240.00. This bid was obtained on October 20, 1970.

[247]*247Under date of August 30, 1971, the following letter was sent by appellee to appellant:

“Mr. Kenneth R. Garber
P. 0. Box 815
Morgan City, Louisiana 70380
Re: Proposed Residence for Patterson, Louisiana
Dear Ken:
We have obtained from Fangue Bros., Inc., a cost estimate on the second set of plans for your proposed residence in Patterson, (Drawings dated 20 October 1970). At the time that I delivered prints of these drawings to you, 28 October 1970, you advised that you would obtain an estimate within two weeks and would send me a copy. As of today we have not received it so we had the Fangue’s run an estimate to settle the matter.
To review briefly, we opened bids on the initial set of plans, (Dated 15 August 1969), on 13 November, 1969 and received a bid of $103,200.00 for the house and $7,320.00 for drives, septic tank, and field lines. The bid for the house was well above the amount you wished to spend and our efforts in negotiations with the low bidder, Fangue Bros., were unsuccessful in reducing the cost to an acceptable figure. We then agreed to prepare a second set of drawings for the house such that it would have cost $60,000.00 in the construction market of November 1969. You then decided not to build the house until some future date. The second set of drawings were completed and delivered to you on 28, October 1970, as previously stated. The new budget including drives, septic tank, etc., was then $60,-000.00 + $7,320.00 plus the percentage increase in construction costs from November 1969. Construction has risen in our area approximately 18% in the two years hence which increases the budget at this date to $79,437.60. ($67,320.00 X 1.18 = $79,437.60).
The estimate that we .received from Fan-gue Bros., was $79,240.00, which is slightly below the budget maximum. Our part of the agreement has been full-filled, having prepared two sets of drawings and specifications with the final set being within the cost guidelines. We therefore again respectfully submit our invoice in the amount of $3,800.00 for the remainder of the fee due for this work. Your remittance will be appreciated. Very truly yours,
James L. Firmin AIA”

Appellee explained that the attached statement for architectural services rendered in the amount of $3,800.00 represented eighty percent of a ten percent fee for the construction of a residence at a cost of $60,-000.00, less a previous payment of $1,000.00. ($60,000.00 X 10% X 80% - $1,000.00 = $3,800.00).

The contract between the parties provides that any dispute would be “. decided by arbitration in accordance with the Construction Industry Arbitration Rules of the American Arbitration Association . ”. Accordingly, this matter was submitted to arbitration under the auspices of American Arbitration Association on January 24, 1975.

In opening statements before the arbitrator appellee submitted that (1) there was no cost limitation; and (2) if there was, appel-lee had complied with his contractual obligations. Stated another way, appellee was entitled to receive his fee based on the first bid of $110,270.00 or, alternatively, based on the second bid of $79,437.00.

Appellant’s position was (1) that there was a cost limitation of $60,000.00; and (2) that appellee’s failure to provide plans for construction of a residence within this limitation precluded his right to recovery. Rosenthal v. Gauthier, 224 La. 341, 69 So.2d 367 (1973).

Following a hearing the matter was submitted pending the filing of the transcript and briefs. On March 17, 1975, the arbitrator, without oral or written reasons, filed his “Award” in favor of appellee and against appellant in the amount of $7,821.60 and costs. This award is based on the first bid price of $110,270.00. ($110,270.00 X 10% X 80% - $1,000.00 = $7,821.60).

[248]*248Appellee then petitioned the district court to have the arbitrator’s award confirmed and to obtain a judgment against appellant in like amount. At the confirmation hearing the record of the arbitration proceedings together with the exhibits there offered were placed in this record. Oral argument was had and the matter submitted.

The trial judge, in his written reasons for judgment, stated that the contract entered into between these parties is “clear, concise and unambiguous and contains no provision for a ‘cost limit’.” He therefore concluded that parol evidence was inadmissible to vary its written terms and affirmed the award. Cited as authority were C.C. Art. 2276 and Moossy v. Huckabay Hospital, Inc., 283 So.2d 699 (La.1973). Implicit in this ruling is the conclusion that parol evidence was inadmissible at the hearing conducted by the arbitrator.

Without discussing the factors which we consider distinguish Moossy, above, from the facts in the instant matter, it suffices here to say that the parol evidence rule is not applicable. We must therefore hold that the decision of the trial judge is in error.

The parol evidence rule, C.C. Art. 2276, was injected in this controversy for the first time when the matter was before the district court. At this juncture, any objection as to the purported use of parol evidence to vary or modify the terms of a written contract must be considered as having been waived. Southern Scrap Mat. Co. v. Commercial Scrap Mat. Corp., 239 La. 958, 120 So.2d 491 (1960); and, In re Industrial Homestead Assn., 198 So. 528 (La.App.Orl. 1940); writs refused, February 3, 1941.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Wiener v. Anderson
370 So. 2d 665 (Louisiana Court of Appeal, 1979)
Firmin v. Garber
345 So. 2d 905 (Supreme Court of Louisiana, 1977)

Cite This Page — Counsel Stack

Bluebook (online)
343 So. 2d 245, 1977 La. App. LEXIS 4665, Counsel Stack Legal Research, https://law.counselstack.com/opinion/firmin-v-garber-lactapp-1977.