Moores v. Alaska Metal Buildings, Inc.

448 P.2d 581, 1968 Alas. LEXIS 132
CourtAlaska Supreme Court
DecidedDecember 20, 1968
Docket962
StatusPublished
Cited by5 cases

This text of 448 P.2d 581 (Moores v. Alaska Metal Buildings, Inc.) is published on Counsel Stack Legal Research, covering Alaska Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Moores v. Alaska Metal Buildings, Inc., 448 P.2d 581, 1968 Alas. LEXIS 132 (Ala. 1968).

Opinion

OPINION

RABINOWITZ, Justice.

This appeal concerns a mechanic’s and materialman’s lien foreclosure action. After trial to the court, findings of fact and conclusions of law generally favorable to appellee were entered by the superior court. In this appeal appellants attack the adequacy of the trial court’s findings of fact, as well as several of the conclusions of law which were reached below.

The record discloses that appellants are the owners of real property which is located *582 on the Seward Highway outside the city of Anchorage. In December of 1965, appellants leased this property to Roy B. Hammett, pursuant to a written lease which contemplated the erection of a building by the lessee. Hammett intended to use the building and the real property in connection with a franchise he was purportedly granted by Hobb’s Trailers.

In the fall of 1965, Hammett first contacted Warren Slater, the president of ap-pellee Alaska Metal Buildings, concerning the possibility of purchasing a building to be erected on the premises Hammett had leased from appellant. It is' undisputed that on January 6, 1966, Hammett and Slater agreed upon the purchase and sale of a metal building for $9,500. Hammett and Slater also discussed the necessity of a foundation for this building and according to Warren Slater’s testimony, it was mutually agreed appellee would provide a foundation for $2,663. 1 As part of this January 6, 1966, letter agreement, it was further provided that “The costs of this work shall be itemized and * * * the actual

amounts charged with 10% contractors Overhead and Profit added to the total amounts incurred.” Warren Slater testified that the $2,663 contract price was based on the premise that the foundation would be built in the summer of 1966. According to Slater some five days after the January 6, 1966, letter agreement had been entered into, Hammett indicated he wanted the work on the foundation commenced and completed as soon as possible. Since this involved increased costs and construction time resulting from problems inherent in cold weather construction, Hammett agreed, on January 11, 1966, to the following additional provision to the original contract:

It is further understood that when the project costs near the above total cost of $2,663, and it will be necessary to exceed this figure, we will contact you for further authorization to proceed.

In addition to the foregoing evidence given by Warren Slater, Bruce Slater, who was appellee’s foreman in charge of construction of the foundation project, testified he was present during the January 1966 conversations which took place between his father and Hammett. According to Bruce Slater, the upshot of these talks was that appellee was to construct the foundation on a cost-plus basis. In his deposition, Hammett took the position that the January 6, Í966, letter calling for construction by ap-pellee of the foundation for a total price of $2,663 constituted his “complete” agreement with Slater. In this same deposition Hammett subsequently admitted, after construction of the foundation had commenced, that he agreed to pay appellee $3,200 to complete the foundation. The evidence showed that appellee began construction of the foundation on January 12, 1966, and finished on February 5, 1966. Shortly after completion of the foundation, Hammett left for Texas to obtain additional financing and thereafter never returned to Alaska. On April 25, 1966, appellee filed a claim of lien on appellants’ property in the total amount of $16,379.16. Several of the items which were included in this total amount were subsequently determined to be non-lienable by the trial court in the foreclosure action. In this appeal, appellants contend the trial court erred in failing to make a specific finding as to what was the actual agreement between Hammett, appellants’ statutory agent, and appellee. More particularly, appellants argue that the trial court’s findings were deficient regarding the price agreed upon for construction of the foundation. Appellants also assert that appellee’s commingling of several nonlienable items in its lien claim voided the entire lien and that the trial court committed prejudicial error in not holding appellee’s entire lien claim void.

We agree with appellants’ initial contention that the trial judge had the duty, *583 under Civil Rule 52(a), to make sufficiently detailed and explicit findings of fact in order to afford this court a clear understanding of the basis for his decision. 2 We have heretofore recognized and applied this same rule in mechanic’s and material-men’s foreclosure actions. 3 Appellants next cite AS 34.35.095 of our statutes which provides that:

A contractor may recover upon a lien filed by him only the amount due to him according to the terms of his contract, after deducting all claims of other persons for work done and materials furnished.

On the basis of the text of AS 34.-35.095, appellants contend that appellee’s lien was limited to the agreed contract price of $2,663. In construing this statute in Clay v. Sandal, 4 this court said:

By statute, the maximum a contractor may establish as a lien can not exceed the amount due to him under the terms of his contract. But there must be a contract with the person from whom the contract lien recovery is sought, or someone privy to him, otherwise the contractor’s lien recovery may be limited to the reasonable value of the labor and materials furnished.

Appellee has no quarrel with AS 34.-35.095 nor with the reference to this statute in the Clay case. Appellee’s position is that the trial court’s findings of fact and conclusions of law are sufficiently explicit. Appellee contends they demonstrate that the court found Hammett had agreed to a cost-plus contract price for any labor or materials furnished over the original contract price of $2,663. Here we agree with ap-pellee’s position. In its findings of fact, the trial court stated, in Finding of Fact VII:

That the plaintiff expended the sum of $2,778.06 for materials for the project which is fair value for same. That plaintiff’s employee Bruce Slater earned the total sum of $918.00 on the project but $96.00 of said amount represents time spent on errands for Hammett and is not a lienable item therefore reducing recoverable amount for Bruce Slater’s labor to $822.00. That plaintiff should recover the following amounts expended for the following employees on the job:
Carlson $ 220.56
Larson 52.53
Pickens-White 22.12
Bruce Slater 822.00
Total labor $ 1117.21
That plaintiff is entitled to 10% profit on material, labor and sub-contractor Shock’s labor in the amount of $583.92. That plaintiff is entitled to a total recovery of $4,479.19 under his lien.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Byrd v. United States
870 A.2d 71 (District of Columbia Court of Appeals, 2005)
Nystrom v. Buckhorn Homes, Inc.
778 P.2d 1115 (Alaska Supreme Court, 1989)
City of Kenai v. Filler
566 P.2d 670 (Alaska Supreme Court, 1977)

Cite This Page — Counsel Stack

Bluebook (online)
448 P.2d 581, 1968 Alas. LEXIS 132, Counsel Stack Legal Research, https://law.counselstack.com/opinion/moores-v-alaska-metal-buildings-inc-alaska-1968.