OPINION
Before NESBETT, C. J., DIMOND and RABINOWITZ, JJ.
RABINOWITZ, Justice.
Involved in this appeal is construction of our mechanic’s and materialmen’s statutes.
The superior court entered a judgment in favor of appellee Ketchikan Spruce Mills establishing a materialmen’s lien in its behalf and decreeing that the lien be foreclosed against appellant Vaara’s interest in certain real property. We have concluded that the'case must be remanded to the trial court for more detailed and explicit findings of fact and conclusions of law.
The crux of this litigation concerns the applicability and interpretation of AS 34.-35.065(a) and (b) of our lien laws. Under this statute, before an owner’s interest in land can be subjected to a statutory ma-terialmen’s lien the owner must have had “knowledge” of the construction.
The evidence presented at the trial shows the following: The real property in question was conveyed to appellant on February 24, 1964.
Prior to April 24, 1964, appellant engaged Jewel Jolley, a salesman for Sullivan Realty, to find a buyer for the property.
Thereafter, Jolley obtained a $500 check from Richard Fuller as a down payment on an agreed $6,500 purchase price for the property.
As part of this transaction Jolley obtained Fuller’s signature to an “Earnest Money Receipt,” and then mailed the partially executed document to appellant for his approval and signature.
This “Earnest Money Receipt” in part provided that “Seller will post property & record copies of non-liability notices and post copies of same on premises.”
According to both Jolley’s testimony and the text of the “Earnest Money Receipt-,” the contemplated sale to Fuller included “The lot, full concrete basement and other minor improvements and some materials like logs to put up a log house.”
When
asked by appellee’s counsel whether it was understood that Fuller was going to complete the existing structure, Jolley testified:
Well there wasn’t necessarily any * * * agreement to that effect. The * * * buyer was supposed to buy the property — he put up a $500 check and he was supposed to pay the balance in cash and — -within 90 days.
Subsequent to the execution of the “Earnest Money Receipt,” Fuller entered into an oral contract with appellee Ketchikan Spruce for the delivery of building materials which were delivered to and used by Fuller to make improvements upon the existing structure on the lot in question.
On July 22, 1965, appellee Ketchikan filed a mechanic’s and materialmen’s lien against the subject property in the amount of $1,046.68 for labor and materials furnished.
Concerning the crucial knowledge issue, the record discloses the following: Appellee does not assert that appellant played any part in the ordering of the materials which were used by Fuller. During the period in question (and in particular between May 10 and May 12, 1965), appellant was in Seattle, Washington. Appellant’s testimony in brief is that until he was served with process
in
connection with this litigation he had no knowledge of the delivery to his real property of any materials and supplies by appellee.
Appellant’s agent, Mr. Jolley, testified that subsequent to April 24, 1965, he had occasion to visit the premises. Approximately ten days after April 24, 1965, he went to appellant’s property and at that time did not “observe any construction work being performed on this house.” About one month later, he again went to the site and this time observed that “there was construction * * * quite a bit had been done.”
Jolley also testified that he never notified appellant that materials “had been purchased by Mr. Fuller or that materials had been delivered to the premises of Lot 6 Block 2 Lemeta.” Jolley further stated that he did not notify appellant “that construction was taking place on this house prior to * * * May 10th or May 12th of 1965.”
Essentially on the basis of the foregoing evidence, the superior court found in ap-pellee’s favor. The only finding of the trial court which pertains to the “knowledge” requirements of AS 34.35.065(a) and (b)
reads as follows:
That the defendant, John R. Vaara, did not avail himself of the protections
of the lien laws of our State by posting the property as required by law, or by posting the property within three days after learning of the construction and improvements on the above described property. And that no other person or persons have a claim or lien on said property described hereinabove superior and prior to that of the plaintiff.
On the basis of our study of the record we are of the opinion that there is substantial evidence in the record to support the conclusion that appellant did not at any pertinent time post the premises with notices of nonresponsibility. On the other hand, we are not informed as to the factual basis of, or legal ground upon which the superior court determined that appellant had the requisite “knowledge” of Fuller’s construction under AS 34.35.065(a) and (b).
On the state of the record before us, it is not apparent what rule of law the superior court applied in reaching its conclusion that appellant possessed the. necessary knowledge of Fuller’s construction.
Rather early in our precedents it was established that the landowner must have actual knowledge of the construction before his interest could be subjected to a materialmen’s lien.
As yet undetermined in this jurisdiction is whether knowledge of intended construction would be sufficient to bring into operation the provisions of AS 34.35.065(a) and (b).
We
are not informed as to whether the trial judge decided that appellant Vaara had actual knowledge of Fuller’s construction, or of Fuller’s intention to commence construction on the premises.
A third approach to the “knowledge” issue in this litigation is suggested by Labay v. Northern Mining & Trading Co.
In that case Judge Tucker said in part:
Free access — add to your briefcase to read the full text and ask questions with AI
OPINION
Before NESBETT, C. J., DIMOND and RABINOWITZ, JJ.
RABINOWITZ, Justice.
Involved in this appeal is construction of our mechanic’s and materialmen’s statutes.
The superior court entered a judgment in favor of appellee Ketchikan Spruce Mills establishing a materialmen’s lien in its behalf and decreeing that the lien be foreclosed against appellant Vaara’s interest in certain real property. We have concluded that the'case must be remanded to the trial court for more detailed and explicit findings of fact and conclusions of law.
The crux of this litigation concerns the applicability and interpretation of AS 34.-35.065(a) and (b) of our lien laws. Under this statute, before an owner’s interest in land can be subjected to a statutory ma-terialmen’s lien the owner must have had “knowledge” of the construction.
The evidence presented at the trial shows the following: The real property in question was conveyed to appellant on February 24, 1964.
Prior to April 24, 1964, appellant engaged Jewel Jolley, a salesman for Sullivan Realty, to find a buyer for the property.
Thereafter, Jolley obtained a $500 check from Richard Fuller as a down payment on an agreed $6,500 purchase price for the property.
As part of this transaction Jolley obtained Fuller’s signature to an “Earnest Money Receipt,” and then mailed the partially executed document to appellant for his approval and signature.
This “Earnest Money Receipt” in part provided that “Seller will post property & record copies of non-liability notices and post copies of same on premises.”
According to both Jolley’s testimony and the text of the “Earnest Money Receipt-,” the contemplated sale to Fuller included “The lot, full concrete basement and other minor improvements and some materials like logs to put up a log house.”
When
asked by appellee’s counsel whether it was understood that Fuller was going to complete the existing structure, Jolley testified:
Well there wasn’t necessarily any * * * agreement to that effect. The * * * buyer was supposed to buy the property — he put up a $500 check and he was supposed to pay the balance in cash and — -within 90 days.
Subsequent to the execution of the “Earnest Money Receipt,” Fuller entered into an oral contract with appellee Ketchikan Spruce for the delivery of building materials which were delivered to and used by Fuller to make improvements upon the existing structure on the lot in question.
On July 22, 1965, appellee Ketchikan filed a mechanic’s and materialmen’s lien against the subject property in the amount of $1,046.68 for labor and materials furnished.
Concerning the crucial knowledge issue, the record discloses the following: Appellee does not assert that appellant played any part in the ordering of the materials which were used by Fuller. During the period in question (and in particular between May 10 and May 12, 1965), appellant was in Seattle, Washington. Appellant’s testimony in brief is that until he was served with process
in
connection with this litigation he had no knowledge of the delivery to his real property of any materials and supplies by appellee.
Appellant’s agent, Mr. Jolley, testified that subsequent to April 24, 1965, he had occasion to visit the premises. Approximately ten days after April 24, 1965, he went to appellant’s property and at that time did not “observe any construction work being performed on this house.” About one month later, he again went to the site and this time observed that “there was construction * * * quite a bit had been done.”
Jolley also testified that he never notified appellant that materials “had been purchased by Mr. Fuller or that materials had been delivered to the premises of Lot 6 Block 2 Lemeta.” Jolley further stated that he did not notify appellant “that construction was taking place on this house prior to * * * May 10th or May 12th of 1965.”
Essentially on the basis of the foregoing evidence, the superior court found in ap-pellee’s favor. The only finding of the trial court which pertains to the “knowledge” requirements of AS 34.35.065(a) and (b)
reads as follows:
That the defendant, John R. Vaara, did not avail himself of the protections
of the lien laws of our State by posting the property as required by law, or by posting the property within three days after learning of the construction and improvements on the above described property. And that no other person or persons have a claim or lien on said property described hereinabove superior and prior to that of the plaintiff.
On the basis of our study of the record we are of the opinion that there is substantial evidence in the record to support the conclusion that appellant did not at any pertinent time post the premises with notices of nonresponsibility. On the other hand, we are not informed as to the factual basis of, or legal ground upon which the superior court determined that appellant had the requisite “knowledge” of Fuller’s construction under AS 34.35.065(a) and (b).
On the state of the record before us, it is not apparent what rule of law the superior court applied in reaching its conclusion that appellant possessed the. necessary knowledge of Fuller’s construction.
Rather early in our precedents it was established that the landowner must have actual knowledge of the construction before his interest could be subjected to a materialmen’s lien.
As yet undetermined in this jurisdiction is whether knowledge of intended construction would be sufficient to bring into operation the provisions of AS 34.35.065(a) and (b).
We
are not informed as to whether the trial judge decided that appellant Vaara had actual knowledge of Fuller’s construction, or of Fuller’s intention to commence construction on the premises.
A third approach to the “knowledge” issue in this litigation is suggested by Labay v. Northern Mining & Trading Co.
In that case Judge Tucker said in part:
It may be true that actual or positive knowledge is not shown by the evidence to have been brought home to the defendant company, but in our view of the law and of section 694 that is not necessary. Such a construction of the statute is too narrow. Knowledge in a legal sense may be positive or implied. The implication of knowledge arises when the party to be charged is shown to have had knowledge of such facts and circumstances as would lead him by the exercise of due diligence to a knowledge of the principal fact. This is the general rule especially applicable to the case here.
Again we are uncertain as to whether the trial court adopted a rule of law analogous to Judge Tucker’s reasoning in the
Labay
case, and therefore concluded that AS 34.35.065’s requirements were met because appellant possessed such knowledge as would have put a reasonable man on inquiry.
Another unanswered aspect of this issue concerns knowledge acquired by appellant’s agent, Mr. Jolley. From the findings of fact and conclusions of law we cannot tell whether the trial judge imputed to appellant the knowledge of construction which
Jolley obtained approximately forty days after April 24. Nor do we know whether the trial court viewed Jolley’s agency as being general or limited in scope.
Before we can make a proper appellate adjudication of the merits of the case, we consider it essential that the trial judge articulate in his findings of fact the factual basis of appellant’s knowledge under AS 34.35.065. We also consider it important that the trial judge’s conclusions of law be expanded to reflect what rule or rules of law he relied upon for his conclusion that appellee’s lien should attach to appellant’s interest in the real property (in other words, the ground upon which appellant was held to have had knowledge).
The case is remanded for further proceedings not inconsistent with the foregoing.