Vaara v. Ketchikan Spruce Mills

432 P.2d 618, 1967 Alas. LEXIS 153
CourtAlaska Supreme Court
DecidedOctober 30, 1967
Docket829
StatusPublished
Cited by5 cases

This text of 432 P.2d 618 (Vaara v. Ketchikan Spruce Mills) is published on Counsel Stack Legal Research, covering Alaska Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Vaara v. Ketchikan Spruce Mills, 432 P.2d 618, 1967 Alas. LEXIS 153 (Ala. 1967).

Opinion

OPINION

Before NESBETT, C. J., DIMOND and RABINOWITZ, JJ.

RABINOWITZ, Justice.

Involved in this appeal is construction of our mechanic’s and materialmen’s statutes. 1 The superior court entered a judgment in favor of appellee Ketchikan Spruce Mills establishing a materialmen’s lien in its behalf and decreeing that the lien be foreclosed against appellant Vaara’s interest in certain real property. We have concluded that the'case must be remanded to the trial court for more detailed and explicit findings of fact and conclusions of law.

The crux of this litigation concerns the applicability and interpretation of AS 34.-35.065(a) and (b) of our lien laws. Under this statute, before an owner’s interest in land can be subjected to a statutory ma-terialmen’s lien the owner must have had “knowledge” of the construction. 2

The evidence presented at the trial shows the following: The real property in question was conveyed to appellant on February 24, 1964. 3 Prior to April 24, 1964, appellant engaged Jewel Jolley, a salesman for Sullivan Realty, to find a buyer for the property. 4 Thereafter, Jolley obtained a $500 check from Richard Fuller as a down payment on an agreed $6,500 purchase price for the property. 5 As part of this transaction Jolley obtained Fuller’s signature to an “Earnest Money Receipt,” and then mailed the partially executed document to appellant for his approval and signature. 6

This “Earnest Money Receipt” in part provided that “Seller will post property & record copies of non-liability notices and post copies of same on premises.” 7 According to both Jolley’s testimony and the text of the “Earnest Money Receipt-,” the contemplated sale to Fuller included “The lot, full concrete basement and other minor improvements and some materials like logs to put up a log house.” 8 When *620 asked by appellee’s counsel whether it was understood that Fuller was going to complete the existing structure, Jolley testified:

Well there wasn’t necessarily any * * * agreement to that effect. The * * * buyer was supposed to buy the property — he put up a $500 check and he was supposed to pay the balance in cash and — -within 90 days. 9

Subsequent to the execution of the “Earnest Money Receipt,” Fuller entered into an oral contract with appellee Ketchikan Spruce for the delivery of building materials which were delivered to and used by Fuller to make improvements upon the existing structure on the lot in question. 10 On July 22, 1965, appellee Ketchikan filed a mechanic’s and materialmen’s lien against the subject property in the amount of $1,046.68 for labor and materials furnished. 11

Concerning the crucial knowledge issue, the record discloses the following: Appellee does not assert that appellant played any part in the ordering of the materials which were used by Fuller. During the period in question (and in particular between May 10 and May 12, 1965), appellant was in Seattle, Washington. Appellant’s testimony in brief is that until he was served with process in connection with this litigation he had no knowledge of the delivery to his real property of any materials and supplies by appellee. 12 Appellant’s agent, Mr. Jolley, testified that subsequent to April 24, 1965, he had occasion to visit the premises. Approximately ten days after April 24, 1965, he went to appellant’s property and at that time did not “observe any construction work being performed on this house.” About one month later, he again went to the site and this time observed that “there was construction * * * quite a bit had been done.” 13 Jolley also testified that he never notified appellant that materials “had been purchased by Mr. Fuller or that materials had been delivered to the premises of Lot 6 Block 2 Lemeta.” Jolley further stated that he did not notify appellant “that construction was taking place on this house prior to * * * May 10th or May 12th of 1965.”

Essentially on the basis of the foregoing evidence, the superior court found in ap-pellee’s favor. The only finding of the trial court which pertains to the “knowledge” requirements of AS 34.35.065(a) and (b) 14 reads as follows:

That the defendant, John R. Vaara, did not avail himself of the protections *621 of the lien laws of our State by posting the property as required by law, or by posting the property within three days after learning of the construction and improvements on the above described property. And that no other person or persons have a claim or lien on said property described hereinabove superior and prior to that of the plaintiff.

On the basis of our study of the record we are of the opinion that there is substantial evidence in the record to support the conclusion that appellant did not at any pertinent time post the premises with notices of nonresponsibility. On the other hand, we are not informed as to the factual basis of, or legal ground upon which the superior court determined that appellant had the requisite “knowledge” of Fuller’s construction under AS 34.35.065(a) and (b). 15 On the state of the record before us, it is not apparent what rule of law the superior court applied in reaching its conclusion that appellant possessed the. necessary knowledge of Fuller’s construction.

Rather early in our precedents it was established that the landowner must have actual knowledge of the construction before his interest could be subjected to a materialmen’s lien. 16 As yet undetermined in this jurisdiction is whether knowledge of intended construction would be sufficient to bring into operation the provisions of AS 34.35.065(a) and (b). 17 We *622 are not informed as to whether the trial judge decided that appellant Vaara had actual knowledge of Fuller’s construction, or of Fuller’s intention to commence construction on the premises. 18

A third approach to the “knowledge” issue in this litigation is suggested by Labay v. Northern Mining & Trading Co. 19 In that case Judge Tucker said in part:

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Lakloey, Inc. v. Ballek
211 P.3d 662 (Alaska Supreme Court, 2009)
Miller v. Ogden
896 P.2d 596 (Court of Appeals of Oregon, 1995)
Wigger v. Olson
533 P.2d 6 (Alaska Supreme Court, 1975)
Moores v. Alaska Metal Buildings, Inc.
448 P.2d 581 (Alaska Supreme Court, 1968)

Cite This Page — Counsel Stack

Bluebook (online)
432 P.2d 618, 1967 Alas. LEXIS 153, Counsel Stack Legal Research, https://law.counselstack.com/opinion/vaara-v-ketchikan-spruce-mills-alaska-1967.