Donnybrook Building Supply Co. v. Alaska National Bank of the North

736 P.2d 1147, 4 A.L.R. 5th 1139, 1987 Alas. LEXIS 258
CourtAlaska Supreme Court
DecidedMay 15, 1987
DocketS-1385
StatusPublished
Cited by9 cases

This text of 736 P.2d 1147 (Donnybrook Building Supply Co. v. Alaska National Bank of the North) is published on Counsel Stack Legal Research, covering Alaska Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Donnybrook Building Supply Co. v. Alaska National Bank of the North, 736 P.2d 1147, 4 A.L.R. 5th 1139, 1987 Alas. LEXIS 258 (Ala. 1987).

Opinion

OPINION

MOORE, Justice.

This case involves a dispute between a construction lender and a material supplier under Alaska’s stop-payment notice statute, AS 34.35.062, as it read in 1985. 1

Donnybrook Building Supply, Inc., (Donnybrook) provided $46,000 worth of building supplies on credit to a contractor for two houses financed by Alaska National Bank of the North (ANB). Donnybrook, asserting that it had not been paid by the recently-bankrupt contractor, sued ANB to recover the $46,000 under the stop-payment notice statute and other theories.

The trial court granted partial summary judgment on liability in favor of ANB. The court held that ANB could not be liable under the stop-payment notice statute because it had made no disbursals from the construction funds after receiving the stop-payment notices. 2 Without considering Donnybrook’s other theories of recovery, the court entered final judgment against Donnybrook. 3

Donnybrook appeals. It claims that the stop-payment statute guarantees its interest in undisbursed construction funds and that the statute is not its exclusive remedy.

We affirm. A stop-payment notice does not give a supplier an interest in undis-bursed construction funds. 4 A construction lender becomes directly liable to a supplier only if it has disbursed construction funds after receipt of a stop-payment notice. Additionally, the statutory mechan *1149 ics’ lien scheme, of which the stop-payment statute is a part, constitutes a complete remedy that preempts common law and equitable remedies.

FACTS AND PROCEEDINGS

Donnybrook sold building supplies on open account to Eugene Cain and Violet Mullen, doing business as Executive Builders (Cain/Mullen), for houses they built in Fairbanks in 1981 and 1982. Cain/Mullen’s first projects were financed by Interior City Branch, First National Bank (ICB); their last three projects were financed by ANB. Donnybrook established a separate charge account for each house project.

In mid-October 1982, Donnybrook was advised that ANB was the construction lender for the last three houses. At that time, several of Cain/Mullen’s other accounts with Donnybrook were in arrears. ANB issued two checks for $25,000 each payable to Mullen, Cain and Donnybrook on October 27, intending that they be applied to the accounts for two of the ANB-financed houses. Instead, Donnybrook applied the money to Cain/Mullen’s accounts with the oldest balances. These were for houses financed by ICB.

Donnybrook filed Notices of Right to Lien pursuant to AS 34.35.064 for the two house projects at issue here on October 29. In December, Cain left Fairbanks, leaving the two houses incomplete. The market value of the houses plus the remaining construction funds held by ANB totalled less than the construction debt Cain/Mullen owed on them to ANB.

Donnybrook filed stop-payment notices totalling $47,181.39 with ANB against the two projects pursuant to AS 34.35.062 on January 6, 1983. It recorded lien claims for $46,181.08 against the properties on January 20. 5 Donnybrook filed suit to enforce its stop-payment notices pursuant to AS 34.35.062(c) on February 7, 1983. On February 25, Cain/Mullen filed for bankruptcy.

ANB did not disburse funds from the construction accounts after receiving Donnybrook’s stop-payment notices. ANB declared the Cain/Mullen notes in default and foreclosed on its deeds of trust in the properties. The value of the properties was less than the outstanding loan balance.

DISCUSSION

The first issue raised by the trial court’s decision is whether AS 34.35.062 gives a supplier a direct interest in construction funds on termination of the project when the lender does not disburse the funds but instead applies them against the builder’s loan balance. 6 The second issue is whether the mechanics’ lien laws create an exclusive remedy for unpaid suppliers. Our standard of review of issues of law is the substitution of judgment test. Borkowski v. Snowden, 665 P.2d 22, 25 (Alaska 1983).

Alaska Statute 34.35.062 was part of a complex statutory scheme designed to protect subcontractors and material suppliers who provide labor and materials on construction projects. AS 34.35.050-.120. Typically, a private construction project is financed by a construction lender who commits a fixed sum to the project. This loan is secured by a first mortgage in the development. The loan is paid out in installments as work progresses. Suppliers also extend credit to the developer. See generally Reitz, Construction Lenders’ Liability to Contractors, Subcontractors, and Materialmen, 130 U.Pa.L.Rev. 416, 417-18 (1981). Before 1978, subcontractors and suppliers were able to protect themselves by taking a priority lien in the real property under construction. Former AS 34.35.-060 (repealed by ch. 175, § 19, SLA 1978); see Brand v. First Federal Sav. & Loan Ass’n. of Fairbanks, 478 P.2d 829, 832 (Alaska 1970). In 1978, the legislature repealed this lien priority, and substituted the statutory “stop payment notice” procedure. Under this procedure, a supplier can re *1150 solve claims against a developer by “intercepting” construction loan disbursements made by the lender. 7

We have not previously construed a stop-payment notice statute.

A. A Stop-payment Claim Does Not Reach Undisbursed Construction Funds

Our starting point for interpreting a statute is the language of the statute construed in light of the purpose for its enactment. Commercial Fisheries Entry Comm’n v. Apokedak, 680 P.2d 486, 489-90 (Alaska 1984).

Alaska Statute 34.35.062 8 permits a supplier who has maintained his right to a mechanics’ lien by recording necessary notices and whose bills to a developer are 20 days overdue to serve a stop-payment notice on the construction lender. AS 34.35.-062(a)(2). Upon receipt of the stop-payment notice, the lender “shall withhold” from the contractor’s subsequent draws the sum claimed by the supplier. AS 34.-35.062(a)(4). The lender can only disburse the claimed amount upon court order or written agreement of the' claimant and developer. AS 34.35.062(a)(5). If the lender does disburse funds in violation of a stop- *1151 payment notice, the lender becomes directly liable to the supplier for the lesser of the sum disbursed or the amount of the valid claim. AS 34.35.062(b).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Hope P. v. Flynn G.
355 P.3d 559 (Alaska Supreme Court, 2015)
McDonald v. Trihub
173 P.3d 416 (Alaska Supreme Court, 2007)
Young v. Embley
143 P.3d 936 (Alaska Supreme Court, 2006)
D.H. Blattner & Sons, Inc. v. N.M. Rothschild & Sons, Ltd.
55 P.3d 37 (Alaska Supreme Court, 2002)
Falconer v. Adams
20 P.3d 583 (Alaska Supreme Court, 2001)
Commerce v. Equity
695 So. 2d 383 (District Court of Appeal of Florida, 1997)
Roe v. Miles Laboratories, Inc.
740 F. Supp. 740 (D. Alaska, 1989)
Great Western Savings Bank v. George W. Easley Co.
778 P.2d 569 (Alaska Supreme Court, 1989)

Cite This Page — Counsel Stack

Bluebook (online)
736 P.2d 1147, 4 A.L.R. 5th 1139, 1987 Alas. LEXIS 258, Counsel Stack Legal Research, https://law.counselstack.com/opinion/donnybrook-building-supply-co-v-alaska-national-bank-of-the-north-alaska-1987.