OPINION
MOORE, Justice.
This case involves a dispute between a construction lender and a material supplier under Alaska’s stop-payment notice statute, AS 34.35.062, as it read in 1985.
Donnybrook Building Supply, Inc., (Donnybrook) provided $46,000 worth of building supplies on credit to a contractor for two houses financed by Alaska National Bank of the North (ANB). Donnybrook, asserting that it had not been paid by the recently-bankrupt contractor, sued ANB to recover the $46,000 under the stop-payment notice statute and other theories.
The trial court granted partial summary judgment on liability in favor of ANB. The court held that ANB could not be liable under the stop-payment notice statute because it had made no disbursals from the construction funds after receiving the stop-payment notices.
Without considering Donnybrook’s other theories of recovery, the court entered final judgment against Donnybrook.
Donnybrook appeals. It claims that the stop-payment statute guarantees its interest in undisbursed construction funds and that the statute is not its exclusive remedy.
We affirm. A stop-payment notice does not give a supplier an interest in undis-bursed construction funds.
A construction lender becomes directly liable to a supplier only if it has disbursed construction funds after receipt of a stop-payment notice. Additionally, the statutory mechan
ics’ lien scheme, of which the stop-payment statute is a part, constitutes a complete remedy that preempts common law and equitable remedies.
FACTS AND PROCEEDINGS
Donnybrook sold building supplies on open account to Eugene Cain and Violet Mullen, doing business as Executive Builders (Cain/Mullen), for houses they built in Fairbanks in 1981 and 1982. Cain/Mullen’s first projects were financed by Interior City Branch, First National Bank (ICB); their last three projects were financed by ANB. Donnybrook established a separate charge account for each house project.
In mid-October 1982, Donnybrook was advised that ANB was the construction lender for the last three houses. At that time, several of Cain/Mullen’s other accounts with Donnybrook were in arrears. ANB issued two checks for $25,000 each payable to Mullen, Cain and Donnybrook on October 27, intending that they be applied to the accounts for two of the ANB-financed houses. Instead, Donnybrook applied the money to Cain/Mullen’s accounts with the oldest balances. These were for houses financed by ICB.
Donnybrook filed Notices of Right to Lien pursuant to AS 34.35.064 for the two house projects at issue here on October 29. In December, Cain left Fairbanks, leaving the two houses incomplete. The market value of the houses plus the remaining construction funds held by ANB totalled less than the construction debt Cain/Mullen owed on them to ANB.
Donnybrook filed stop-payment notices totalling $47,181.39 with ANB against the two projects pursuant to AS 34.35.062 on January 6, 1983. It recorded lien claims for $46,181.08 against the properties on January 20.
Donnybrook filed suit to enforce its stop-payment notices pursuant to AS 34.35.062(c) on February 7, 1983. On February 25, Cain/Mullen filed for bankruptcy.
ANB did not disburse funds from the construction accounts after receiving Donnybrook’s stop-payment notices. ANB declared the Cain/Mullen notes in default and foreclosed on its deeds of trust in the properties. The value of the properties was less than the outstanding loan balance.
DISCUSSION
The first issue raised by the trial court’s decision is whether AS 34.35.062 gives a supplier a direct interest in construction funds on termination of the project when the lender does not disburse the funds but instead applies them against the builder’s loan balance.
The second issue is whether the mechanics’ lien laws create an exclusive remedy for unpaid suppliers. Our standard of review of issues of law is the substitution of judgment test.
Borkowski v. Snowden,
665 P.2d 22, 25 (Alaska 1983).
Alaska Statute 34.35.062 was part of a complex statutory scheme designed to protect subcontractors and material suppliers who provide labor and materials on construction projects. AS 34.35.050-.120. Typically, a private construction project is financed by a construction lender who commits a fixed sum to the project. This loan is secured by a first mortgage in the development. The loan is paid out in installments as work progresses. Suppliers also extend credit to the developer.
See generally Reitz, Construction Lenders’ Liability to Contractors, Subcontractors, and Materialmen,
130 U.Pa.L.Rev. 416, 417-18 (1981). Before 1978, subcontractors and suppliers were able to protect themselves by taking a priority lien in the real property under construction. Former AS 34.35.-060 (repealed by ch. 175, § 19, SLA 1978);
see Brand v. First Federal Sav. & Loan Ass’n. of Fairbanks,
478 P.2d 829, 832 (Alaska 1970). In 1978, the legislature repealed this lien priority, and substituted the statutory “stop payment notice” procedure. Under this procedure, a supplier can re
solve claims against a developer by “intercepting” construction loan disbursements made by the lender.
We have not previously construed a stop-payment notice statute.
A. A Stop-payment Claim Does Not Reach Undisbursed Construction Funds
Our starting point for interpreting a statute is the language of the statute construed in light of the purpose for its enactment.
Commercial Fisheries Entry Comm’n v. Apokedak,
680 P.2d 486, 489-90 (Alaska 1984).
Alaska Statute 34.35.062
permits a supplier who has maintained his right to a mechanics’ lien by recording necessary notices and whose bills to a developer are 20 days overdue to serve a stop-payment notice on the construction lender. AS 34.35.-062(a)(2). Upon receipt of the stop-payment notice, the lender “shall withhold” from the contractor’s subsequent draws the sum claimed by the supplier. AS 34.-35.062(a)(4). The lender can only disburse the claimed amount upon court order or written agreement of the' claimant and developer. AS 34.35.062(a)(5). If the lender does disburse funds in violation of a stop-
payment notice, the lender becomes directly liable to the supplier for the lesser of the sum disbursed or the amount of the valid claim. AS 34.35.062(b).
Free access — add to your briefcase to read the full text and ask questions with AI
OPINION
MOORE, Justice.
This case involves a dispute between a construction lender and a material supplier under Alaska’s stop-payment notice statute, AS 34.35.062, as it read in 1985.
Donnybrook Building Supply, Inc., (Donnybrook) provided $46,000 worth of building supplies on credit to a contractor for two houses financed by Alaska National Bank of the North (ANB). Donnybrook, asserting that it had not been paid by the recently-bankrupt contractor, sued ANB to recover the $46,000 under the stop-payment notice statute and other theories.
The trial court granted partial summary judgment on liability in favor of ANB. The court held that ANB could not be liable under the stop-payment notice statute because it had made no disbursals from the construction funds after receiving the stop-payment notices.
Without considering Donnybrook’s other theories of recovery, the court entered final judgment against Donnybrook.
Donnybrook appeals. It claims that the stop-payment statute guarantees its interest in undisbursed construction funds and that the statute is not its exclusive remedy.
We affirm. A stop-payment notice does not give a supplier an interest in undis-bursed construction funds.
A construction lender becomes directly liable to a supplier only if it has disbursed construction funds after receipt of a stop-payment notice. Additionally, the statutory mechan
ics’ lien scheme, of which the stop-payment statute is a part, constitutes a complete remedy that preempts common law and equitable remedies.
FACTS AND PROCEEDINGS
Donnybrook sold building supplies on open account to Eugene Cain and Violet Mullen, doing business as Executive Builders (Cain/Mullen), for houses they built in Fairbanks in 1981 and 1982. Cain/Mullen’s first projects were financed by Interior City Branch, First National Bank (ICB); their last three projects were financed by ANB. Donnybrook established a separate charge account for each house project.
In mid-October 1982, Donnybrook was advised that ANB was the construction lender for the last three houses. At that time, several of Cain/Mullen’s other accounts with Donnybrook were in arrears. ANB issued two checks for $25,000 each payable to Mullen, Cain and Donnybrook on October 27, intending that they be applied to the accounts for two of the ANB-financed houses. Instead, Donnybrook applied the money to Cain/Mullen’s accounts with the oldest balances. These were for houses financed by ICB.
Donnybrook filed Notices of Right to Lien pursuant to AS 34.35.064 for the two house projects at issue here on October 29. In December, Cain left Fairbanks, leaving the two houses incomplete. The market value of the houses plus the remaining construction funds held by ANB totalled less than the construction debt Cain/Mullen owed on them to ANB.
Donnybrook filed stop-payment notices totalling $47,181.39 with ANB against the two projects pursuant to AS 34.35.062 on January 6, 1983. It recorded lien claims for $46,181.08 against the properties on January 20.
Donnybrook filed suit to enforce its stop-payment notices pursuant to AS 34.35.062(c) on February 7, 1983. On February 25, Cain/Mullen filed for bankruptcy.
ANB did not disburse funds from the construction accounts after receiving Donnybrook’s stop-payment notices. ANB declared the Cain/Mullen notes in default and foreclosed on its deeds of trust in the properties. The value of the properties was less than the outstanding loan balance.
DISCUSSION
The first issue raised by the trial court’s decision is whether AS 34.35.062 gives a supplier a direct interest in construction funds on termination of the project when the lender does not disburse the funds but instead applies them against the builder’s loan balance.
The second issue is whether the mechanics’ lien laws create an exclusive remedy for unpaid suppliers. Our standard of review of issues of law is the substitution of judgment test.
Borkowski v. Snowden,
665 P.2d 22, 25 (Alaska 1983).
Alaska Statute 34.35.062 was part of a complex statutory scheme designed to protect subcontractors and material suppliers who provide labor and materials on construction projects. AS 34.35.050-.120. Typically, a private construction project is financed by a construction lender who commits a fixed sum to the project. This loan is secured by a first mortgage in the development. The loan is paid out in installments as work progresses. Suppliers also extend credit to the developer.
See generally Reitz, Construction Lenders’ Liability to Contractors, Subcontractors, and Materialmen,
130 U.Pa.L.Rev. 416, 417-18 (1981). Before 1978, subcontractors and suppliers were able to protect themselves by taking a priority lien in the real property under construction. Former AS 34.35.-060 (repealed by ch. 175, § 19, SLA 1978);
see Brand v. First Federal Sav. & Loan Ass’n. of Fairbanks,
478 P.2d 829, 832 (Alaska 1970). In 1978, the legislature repealed this lien priority, and substituted the statutory “stop payment notice” procedure. Under this procedure, a supplier can re
solve claims against a developer by “intercepting” construction loan disbursements made by the lender.
We have not previously construed a stop-payment notice statute.
A. A Stop-payment Claim Does Not Reach Undisbursed Construction Funds
Our starting point for interpreting a statute is the language of the statute construed in light of the purpose for its enactment.
Commercial Fisheries Entry Comm’n v. Apokedak,
680 P.2d 486, 489-90 (Alaska 1984).
Alaska Statute 34.35.062
permits a supplier who has maintained his right to a mechanics’ lien by recording necessary notices and whose bills to a developer are 20 days overdue to serve a stop-payment notice on the construction lender. AS 34.35.-062(a)(2). Upon receipt of the stop-payment notice, the lender “shall withhold” from the contractor’s subsequent draws the sum claimed by the supplier. AS 34.-35.062(a)(4). The lender can only disburse the claimed amount upon court order or written agreement of the' claimant and developer. AS 34.35.062(a)(5). If the lender does disburse funds in violation of a stop-
payment notice, the lender becomes directly liable to the supplier for the lesser of the sum disbursed or the amount of the valid claim. AS 34.35.062(b). The stop-payment notice expires automatically after 30 days unless the supplier files a bonded suit to enforce his claim. AS 34.35.062(c).
The stop-payment notice thus puts direct financial pressure on the contractor to pay his suppliers. If he does not, the amount claimed will normally be withheld from his next draw. The lender can pay the claimant directly if the claimant and developer agree, or if a court orders it. The lender will be directly liable to the claimant if it disburses funds without withholding funds to pay the claim.
In this case, however, after ANB received the stop-payment notice, it apparently neither prevailed upon the developer to pay the claim
nor disbursed funds in violation of the statute. Instead, ANB ceased making disbursals and declared Cain/Mullen’s loan in default. Cain/Mullen became insolvent. ANB foreclosed on the construction property but recovered less than the debt owed to it by Cain/Mullen. Now ANB apparently seeks to apply the remaining construction funds to the outstanding debt pursuant to its loan agreement with Cain/Mullen. Donnybrook contends that its stop-payment claim must be paid from the undisbursed construction funds.
ANB argues that it is not liable under AS 34.35.062 because the stop-notice remedies against the lender are explicitly limited to the lesser of the amount claimed or the amount “disbursed in violation of those subsections.” AS 34.35.062(b). Because it did not disburse the funds remaining in the accounts, ANB argues, those funds are not subject to Donnybrook’s claims and thus can be applied toward the deficiency remaining on Cain/Mullen’s construction loan debt.
Donnybrook argues that a stop-payment notice requires the lender to ensure that a supplier’s claim is settled before the lender releases construction funds for any us.e, including repayment of the construction loan. Donnybrook observes that the statute is remedial in purpose and argues that it should be construed liberally to achieve the remedies intended.
We agree that this statute is remedial and that its purpose is to protect subcontractors and material suppliers. We will construe a remedial statute liberally to fulfill its purposes.
See Moores v. Alaska Metal Buildings, Inc.,
448 P.2d 581, 584 (Alaska 1968) (adopting liberal construction of the former mechanics’ lien statute). However, the language of this statute compels the determination that a stop-payment claim does not take a priority interest in undisbursed construction funds.
Alaska Statute 34.35.062(a)(4) states: “After receipt of a stop-payment notice under this section, the lender
shall
withhold
from the next and subsequent draws
sufficient money to pay the amount claimed ...” (emphasis added). Subsection (b) provides for direct lender liability for the lesser of the valid claim amount as determined by a court or the amount disbursed. When no funds are disbursed, the lender incurs no liability.
The lender’s duty to withhold funds does not attach to the entire construction fund, but only to “the next and subsequent draws.” AS 34.35.062(a)(4). “Draws” are “periodic disbursements of construction financing by a lender.” AS 34.35.120(6). The draw procedure is mandated by statute on unbonded projects. AS 34.35.062(a). The lender issues draws based on construction progress; if no further progress is made, as determined by the lender’s certification, then no draws become payable to the contractor. In effect, the statute assigns to the claimant the developer’s right to collect a draw due from the lender. Where no draw becomes due based on the lender’s agreement with the developer and the statute, there is nothing to assign to the claimant.
The State of Washington has a similar stop-payment notice statute.
A comment evaluating this statute observed that the lender had three options upon receipt of the stop-payment notice: (1) to withhold the claimed sum from later draws; (2) to permit later draws and risk loss of its senior lienor status (the Washington statute provides this remedy where Alaska’s provides for direct lender liability); or (3) to “avoid the effect of the stop notice altogether by making no further loan advances and foreclosing his mortgage. In this last situation, the [claimant's] only recourse is to his mechanics’ lien which will have no enhanced priority by reason of the stop notice.” Comment,
supra
note 7, 695-96. In
In re Aspen Homes, Inc.,
54 B.R. 541, 545 (Bankr.E.D.Wash.1985), a bankruptcy court cited this comment with approval, and held that the Washington statute allowed a lender to foreclose the interest of a supplier by declaring the developer’s loan in default and using remaining construction funds to pay new suppliers to complete the project.
Id.
The California stop-notice statute
has been interpreted to impose on the lender the duty to pay stop-notice claimants out of undisbursed construction funds.
A-1 Door and Materials Co. v. Fresno Guarantee Sav. & Loan Ass’n,
61 Cal.2d 728, 40 Cal.Rptr. 85, 89, 394 P.2d 829, 833-34 (1964) (decided under earlier version of present statute). The
A-l Door
court held that a construction lender, having fully committed a given sum to a developer for a project, holds undisbursed funds as an assignee (for security) of the developer.
Id.
40 Cal.Rptr. at 89, 394 P.2d at 834. The statute expressly barred any assignment of the loan funds in derogation of a claimant’s right.
Id.
Furthermore, the court held that the stop notice attaches to the entire
fund, not just to funds subsequently disbursed.
Id.
40 Cal.Rptr. at 90, 394 P.2d at 833. A stop-notice claimant is thus guaranteed payment even though the developer has disappeared or gone bankrupt.
Ilyin,
supra
note 7, 187.
Unlike the California statute, AS 34.35.-062 expressly applies only to funds disbursed after the lender receives the stop-payment notice. Furthermore, AS 34.35.-062 does not bar an assignment by the developer of his right to receive loan funds. Indeed, the draw procedure of AS 34.35.-062(a)(1) suggests that the legislature did not view the lender’s interest in the loan funds as an assignee of the developer, but instead established that the developer’s interest in the loan funds did not vest until the lender certified each draw.
We do not see that the equities sharply favor either party. While a supplier may be less able to assess the credit-worthiness of a developer than a lending institution, and may implicitly rely on the loan in extending credit to the developer, the lender is also in the business of providing an essential “material” for construction and does not intend to insure the payment of other suppliers nor to bear the unavoidable risk of the project. Placing upon lenders the obligation to ensure that suppliers are paid may well have the effect of increasing interest rates and limiting loan availability, especially to smaller developers.
See
Gutierrez,
supra
note 7, 520-21. Particularly where the project is incomplete, courts have been reluctant to make lenders liable to suppliers under equitable theories.
E.g., JG Plumbing Service Inc. v. Coastal Mortgage Co.,
329 So.2d 393, 395 (Fla.App.1976);
see generally
Reitz,
supra
p.6, 442-50.
We conclude that the legislature intended to empower lenders to cut off suppliers’ claims if the lenders are willing to risk the loss of the developer’s efforts before the project is complete. Therefore, we affirm the trial court’s decision that Donnybrook has no remedy under AS 34.35.062.
B. Alternative Remedies
Donnybrook asserts that, even if its stop-payment claim is unsuccessful, ANB is nonetheless liable for Cain/Mullen’s debt under several other theories.
First, Donnybrook seeks an equitable lien against the construction funds. Second, Donnybrook claims that the draw procedure of AS 34.-35.062(a)(1) imposes a duty of care upon a lender toward suppliers, for the breach of which a supplier may recover damages.
Alaska’s mechanics’ lien law, AS 34.35.-050-.120, establishes a complex and detailed scheme for the protection of suppliers on construction projects. The legislature clearly sought to balance the conflicting interests of developers, lenders and suppliers under this statutory umbrella. The statutes provide two separate remedies for suppliers: the stop-payment remedy of AS 34.35.062, and the mechanics’ lien under AS 34.35.050. All suppliers have an equal right to the stop-payment notice remedy, but an “individual actually performing labor” (or his trust fund) is entitled to a priority lien. AS 34.35.060(c). While no party to this action asserts a claim under AS 34.35.060(c), we believe that that ex
press priority is an indication of legislative intent to provide a complete and prioritized system of remedies. To impose judicially additional remedies on behalf of suppliers here would disturb this balance.
Furthermore, the legislature expressly retained the right of a lienor “under a contract” to utilize his contract remedies regardless of his lien. AS 34.35.045. Because only this exception to the exclusivity of the mechanics’ lien law remedies is expressed, the statutory maxim
expressio un-ius est exclusio alterius
suggests that other remedies are excluded.
Burrell v. Burrell,
696 P.2d 157, 165 (Alaska 1984). We conclude that the mechanics’ lien law preempts the remedies sought by Donnybrook. Cf
. Aleut Corp. v. Arctic Slope Regional Corp.,
424 F.Supp. 897, 399-400 (D. Alaska 1976) (Alaska’s legislative scheme of attachment-type remedies preempts common law sequestration).
C. Conclusion
We conclude that the plain language of AS 34.35.062 precludes Donnybrook’s stop-payment notice action because ANB did not disburse construction funds following receipt of the notice. Furthermore, the mechanics’ lien law is an exclusive remedy which preempts Donnybrook’s equitable lien and statutory duty theories of recovery. Therefore, we AFFIRM the trial court’s judgment.