Moon v. Wilson

130 So. 25, 100 Fla. 791
CourtSupreme Court of Florida
DecidedSeptember 11, 1930
StatusPublished
Cited by9 cases

This text of 130 So. 25 (Moon v. Wilson) is published on Counsel Stack Legal Research, covering Supreme Court of Florida primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Moon v. Wilson, 130 So. 25, 100 Fla. 791 (Fla. 1930).

Opinions

The appellant, A. B. Moon, as complainant below, filed his bill in chancery against appellee, Graham L. Wilson, as defendant below, for the purpose of foreclosing a statutory lien for labor and material furnished in the construction of a house upon defendant's property in Lee County, Florida. Attached to the bill of complaint is the written contract of construction in which, among other things, complainant agreed to furnish all material and labor for the remodeling of the old house and complete new building to correspond with the submitted drawings and specifications; all for the sum of $12,800.00. All materials and workmanship used in the construction were guaranteed by complainant to be first quality and he agreed "to complete" the buildings to defendant's "entire satisfaction within a period of nine weeks."

The terms of payment for the construction were as follows: "It is hereby understood when frame construction is built and roof raised, I am to receive one-third of the contract price, and when the building is entirely inclosed another one-third and the final third is to be paid upon final completion and satisfactory inspection by the owner."

The bill of complaint alleges that complainant performed the labor and furnished the material and "had almost complied with said contract by building said house and supplying said extras" when on or about the 18th day of September, 1926, there came a great storm and the "said house that he had constructed was almost wrecked and almost destroyed," that nevertheless he started in earnest to reconstruct the said house according to the original plans and extras, "having in mind that the work of placing the house in the condition it was before the storm would be charged to the defendant;" that the work under the contract "that had not been done was to be done by orator in compliance *Page 794 with an under the terms of said contract, but defendant told orator that has services were dispensed with and that he could not go on with the said work."

The bill further alleges that defendant paid complainant "until there now remains due to him the sum of $4,805.50, and he is entitled to a lien" upon the said property for the said sum.

It is further alleged that complainant "is claiming the amount that is actually due him for the work and labor furnished and bestowed upon said building and premises prior to the time he was ordered to cease," and not damages for breach of contract.

A demurrer was interposed by the defendant stating that the allegations of the bill of complaint are so vague, indefinite and uncertain that they do not apprise the defendant of the relief sought. The chancellor sustained the demurrer and the complainant having declined to amend the bill was dismissed. The said rulings of the chancellor are here for review upon appeal of complainant.

Under the statutes of this State, liens prior in dignity to all others accruing thereafter exist in favor of persons performing labor or furnishing material on the construction of any building or additions thereto and the land upon which it stands. Section 5349, 5350, 5353, Comp. Gen. Laws of Florida, 1927.

The contract for the construction provides that complainant was to furnish all material and labor for remodeling and completing the building for the sum of $12,800.00, to be paid one-third "when frame construction is built and roofing raised," and one-third "when building is entirely enclosed," and the "final third is to be paid upon final completion and satisfactory inspection by owner."

The above sets forth the conditions upon which each third of the construction was to be paid for. The bill of *Page 795 complaint sets forth that there were some extras, but does not state what they were or the cost. The bill further alleges that there remains due to complainant $4,805.50, which appears to be the last payment or one-third of the contract price plus any extras. The bill of complaint shows that the building was not completed within the "period of nine weeks" as specified by the contract entered into April 15, 1926, which would require the building to have been completed about June 22, 1926. It is further shown that the building was not completed on September 18, 1926, three months thereafter, when the storm almost destroyed it. If the construction had been completed before or at the time of the storm, the defendant would be liable for the last one-third payment of the contract, whether the damage or destruction was caused by an act of Providence or not. Until the improvements were "completed" to "defendant's entire satisfaction" the last payment was not due and payable.

The contract for the construction was, in the language of the complainant, in the form of a letter or bid addressed to and accepted by defendant.

There is a distinction between cases in which a contractcan be performed, notwithstanding the destruction of the subject-matter of the contract by an inevitable accident, and cases in which the performance of the contract becomesimpossible by the intervention of causes which human agencies cannot prevent. An inevitable accident will not excuse the performance of a contract where its essential purposes are still capable of substantial performance though literal performance is impossible. 6 R. C. L. 1002, Section 367; 52 R. A. 826 and notes.

"The loss caused by the destruction by storm of a building partly finished falls upon the one who has undertaken to complete and deliver it to the owner *Page 796 for a stipulated price." Milske v. Steiner, Mantel Co., 103 Md. 235, 63 Atl. R. 471, 5 L.R.A. (N.S.) 1105.

It has been held that even though the contract is an entire one, if payment therefor is to be made in installments, as the work progresses, the owner's obligation to pay such sums becomes fixed absolute when the structure reaches the required stage, and that, therefore, the builder is entitled to recover such payments as are due at the time the structure is destroyed. 9 C. J. 806-7, Secs. 144-145; 3 Elliott on Contracts, Secs. 1908-1909; Addison's Law of Contracts, 11th Edition, 884.

The last above authority states the general rule as follows:

"If the contract price of the building is to be paid by installments on the completion of certain specified portions of the work, each installment becomes a debt due to the builder, as the particular portion specified is completed; and, if the house is destroyed by accident, the employer would be bound to pay the installments then due, but would not be responsible for the intermediate work and labor and materials." See also, 3 Elliott on Contracts, Sec. 1909; Cutcliff v. McAnally, 88 Ala. 507, 7 So. R. 331; 22 L.R.A. (N.S.) 364.

With reference to extras under such agreement Addison's Law of Contracts, page 886, says:

"If work has been agreed to be done, and materials supplied under a building contract for certain estimated prices, and there has subsequently been a deviation from the original plan by consent of the parties, the contract is not on that account excluded, but is to *Page 797 be the rule of payment, as far as the contract can be traced to have been followed, and the excess only is to be paid for according to the usual rates of charging." See also Clark v. Collier, 100 Calif. 256, 34 Pac. R. 677.

The case of Richardson v. Shaw, 1 Mo. App. 234, is exactly in point: One installment was to be paid when the frame work was up, a second when the building was enclosed and a third when ready for plaster.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

MORRIS v. CAMDEN COUNTY
D. New Jersey, 2025
Bloom v. K & K Pipe & Supply Co.
390 So. 2d 770 (District Court of Appeal of Florida, 1980)
Butler Plaza, Inc. v. ALLEN TROVILLION
389 So. 2d 682 (District Court of Appeal of Florida, 1980)
Frankel v. Bernstein
334 So. 2d 37 (District Court of Appeal of Florida, 1976)
La Gasse Pool Const. Co. v. City of Fort Lauderdale
288 So. 2d 273 (District Court of Appeal of Florida, 1974)
Enid Corporation v. Mills
101 So. 2d 906 (District Court of Appeal of Florida, 1958)
Florida Power Corp. v. City of Tallahassee
18 So. 2d 671 (Supreme Court of Florida, 1944)
Nelson v. Watson
155 So. 101 (Supreme Court of Florida, 1933)

Cite This Page — Counsel Stack

Bluebook (online)
130 So. 25, 100 Fla. 791, Counsel Stack Legal Research, https://law.counselstack.com/opinion/moon-v-wilson-fla-1930.