Cutcliff v. McAnally

88 Ala. 507
CourtSupreme Court of Alabama
DecidedNovember 15, 1889
StatusPublished
Cited by23 cases

This text of 88 Ala. 507 (Cutcliff v. McAnally) is published on Counsel Stack Legal Research, covering Supreme Court of Alabama primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Cutcliff v. McAnally, 88 Ala. 507 (Ala. 1889).

Opinion

SOMERVILLE, J.

1. The first question raised on the record in this case is, whether a married woman can create a mechanic’s or material-man’s lien on her separate estate, by her verbal contract, and without the written assent of her husband; or, whether, on the contrary, her legal capacity to contract for such a lien is limited by section 2346 of the present Code, which restricts her general powers to contract as a feme sole to an instrument in writing, with the super-added assent of her husband, also expressed in writing. The case of Wadsworth v. Hodge, decided at the present term (iante, p. 500), settles this question against the contention of the appellee. We there held, that a married woman could charge her separate estate under the provisions of the mechanic’s lien law, as embraced in sections 3018-3048 of the Code (1886), by her oral contract for labor or improvements, and without her husband’s consent, written or otherwise. [509]*509Our ruling was placed upon the broad basis of the statute itself, which provides for the creation of liens of this nature by an oral contract, and expressly authorizes such a contract to be made by a married woman. — Code, 1886, § 3046.

2. A second point of inquiry is, whether the requisite written statement of the plaintiff’s demand was filed in the office of the judge of probate within the time prescribed by statute. If not, the lien is admitted to be barred and lost. The contract in this case was made under the Code of 1876, and must, therefore, be governed by its provisions. The statute then required every original contractor to file his demand within six months after the indebtedness had “accrued,” and actions to enforce the lien were required to be commenced within ninety days after filing such demand. — Code, §§ 3444, 3454. The present Code contains the same provisions as to filing, limiting the time to six months after accrual of the indebtedness; and declares further that, with certain exceptions, all liens arising under this law “shall be deemed lost, unless suit for the enforcement thereof is commenced within six months after the maturity of the entire indebtedness secured thereby.” — Code, 1886, §§ 3022, 3041. We are concerned here, however, only with the question of filing. Was the statement of the demand filed with the judge of probate within six months after the indebtedness accrued, within the meaning of the statute?

In this connection the word “accrued” is evidently used in the sense of having come to maturity, so as to be due and payable. Or, in other words, it indicates the time when the work contracted for is completed, or the materials furnished, one or both, as the case may be, and the account for the same is past due. This is implied in the further description of such indebtedness, thus required to be filed, as “a just and true account of the demand dile him.” — Code, 1876, § 3444. Requiring suit to be instituted on such claim within ninety days after filing, moreover, implies that the demand must have been due and payable when filed.

It has accordingly been held, both under our own statute, and the similar one in Missouri, that where work is done and materials furnished under one continuous, or running contract, the indebtedness created is said to accrue from the last item of the account, and the time of filing must be computed from this date. But, if there be several distinct and independent contracts, separately made for the different parts of a building — as, for example, one for the brick work, another [510]*510for the wood work, and a third for the painting — each must be filed within the time of its own separate accrual.—Lane & Bodley Co. v. Jones, 79 Ala. 156; Livermore v. Wright, 33 Mo. 31; Misso. Code, 1879, § 3192; Pages v. Bettes, 17 Mo. 366; 2 Jones on Liens, §§ 1432-1437; Peck v. Bridwell, 10 Mo. Ap. 524; Henry v. Hinds, 18 Ib. 497.

It is an uncontroverted fact in this case, that the building in process of erection was never completed, but was destroyed by fire, when approaching completion, without the fault of the plaintiff, on September 12th, 1887, — having been willfully burned by the husband of the defendant, who was superintending the work as her agent. The sum sued for — something over $200 — was a percentage retained by the defendant, as usual in such contracts, as a security for the faithful completion of the work, and it was not due to plaintiff until the house was completed. On the 15th of October, 1887, the parties compromised the indebtedness, and, as a convenient mode of liquidating the same, the defendant executed her note to the plaintiff for $200, payable in sixty days after date. The required statement of' the demand was filed April 9th, 1888.

The defendant contends that the entire demand became due on September 12th, 1887 — when the progress of the work was interrupted by the destruction of the house. If this be true, the filing of the statement on the 9th of April following was too late, the lapse of time which had intervened being more than the statutory limit of six months. The plaintiff, on the contrary, contends that the filing was in time, because the sum sued for would not have become due until the house was completed, and the house would not have been completed until about two months after the burning. The case, in this aspect, thus turns on the inquiry, when did this demand accrue, or become due and payable.

The plaintiff’s contract, made in writing on June 6th, 1887, was to build for the defendant a house, and furnish the materials for a stipulated compensation of $2,150, payable in several specified installments according to the progress of the work, the last, including the sum sued for, not being payable until the completion of the building. If the destruction of the house before completion excused the performance of the contract by plaintiff to build it, and gave him any right of action on a quantum meruit, or quantum valebat, and such claim included the retained percentage here sued for, we are of the opinion such demand accrued [511]*511at the time of the fire, and not afterwards. Whatever right of action the plaintiff had, he acquired then, not afterwards. The note given by the defendant was void as a contract by reason of her coverture, and, 'being made without her husband’s written consent, it imposed on her no liability additional to that already existing. — Code, 1886, § 2346. It was no payment of the debt, and the offer is made in the complaint to deliver the paper up for cancellation, which is all that could be required.—Lane & Bodley Co. v. Jones, 79 Ala. 156. The filing was, therefore, too late, and the claim, if it ever had any validity, was extinguished.

3. But there is another view of the case which would justify the general affirmative charge given by the court, to find for the defendant. The contract of the plaintiff, to construct the house on the defendant’s premises, was not excused by the destruction of the house by fire while in process of completion. This is upon the settled principle, that when one, by his own voluntary contract, creates a lawful duty or charge upon himself, he is bound to make it good, if he may, despite obstructions interposed by accident, or inevitable necessity, because he might have provided against the difficulty by his contract. If the obligation is created by law, a different rule would prevail.

In School District v. Dauchy, 25 Conn. 530; 68 Amer. Dec.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Nelson Weaver Mortgage Co. v. Dover Elevator Co.
216 So. 2d 716 (Supreme Court of Alabama, 1968)
Johnson v. Godin
186 So. 2d 722 (Supreme Court of Alabama, 1966)
Home Federal Savings & Loan Association v. Williams
158 So. 2d 678 (Supreme Court of Alabama, 1963)
Sherrod v. Crane Co.
182 So. 48 (Supreme Court of Alabama, 1938)
Wood Coal Co. v. State Compensation Commissioner
195 S.E. 528 (West Virginia Supreme Court, 1938)
Snellings Lumber Co. v. Porter
142 So. 560 (Supreme Court of Alabama, 1932)
Gorr Lumber Co. v. McMillan
143 So. 173 (Supreme Court of Alabama, 1932)
Employers' Mutual Insurance v. Industrial Commission
3 P.2d 1079 (Supreme Court of Colorado, 1931)
Woodall v. Southern Mfg. Co.
135 So. 446 (Supreme Court of Alabama, 1931)
Moon v. Wilson
130 So. 25 (Supreme Court of Florida, 1930)
Dryden v. Baltimore Trust Co.
146 A. 752 (Court of Appeals of Maryland, 1929)
Graves v. Eubank
87 So. 587 (Supreme Court of Alabama, 1921)
Wilbourne v. Mann
81 So. 816 (Supreme Court of Alabama, 1919)
Security Trust Co. of Houston v. Roberts
208 S.W. 892 (Texas Commission of Appeals, 1919)
Ollinger & Bruce Dry Dock Co. v. James Gibbony & Co.
81 So. 18 (Supreme Court of Alabama, 1918)
College Court Realty Co. v. J. C. Letcher Lumber Co.
78 So. 217 (Supreme Court of Alabama, 1917)
Jefferson Plumbers & Mill Supply Co. v. Peebles
71 So. 413 (Supreme Court of Alabama, 1916)
In re Hellams
223 F. 460 (S.D. Alabama, 1915)
Cochise County v. Wilcox
127 P. 758 (Arizona Supreme Court, 1912)
Big Horn Lumber Co. v. Davis
84 P. 900 (Wyoming Supreme Court, 1906)

Cite This Page — Counsel Stack

Bluebook (online)
88 Ala. 507, Counsel Stack Legal Research, https://law.counselstack.com/opinion/cutcliff-v-mcanally-ala-1889.