Florida Power Corp. v. City of Tallahassee

18 So. 2d 671, 154 Fla. 638, 1944 Fla. LEXIS 778
CourtSupreme Court of Florida
DecidedJune 27, 1944
StatusPublished
Cited by32 cases

This text of 18 So. 2d 671 (Florida Power Corp. v. City of Tallahassee) is published on Counsel Stack Legal Research, covering Supreme Court of Florida primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Florida Power Corp. v. City of Tallahassee, 18 So. 2d 671, 154 Fla. 638, 1944 Fla. LEXIS 778 (Fla. 1944).

Opinion

CHAPMAN, J.:

The City of Tallahassee and the Florida Power Corporation, on August 25, 1936, entered into a contract for the purchase and sale of electric energy. This contract was to remain in force and effect and binding upon the parties for a period of twenty years, with optional extension privileges in behalf of the city. Article 1 of the contract made it the duty of the power company to maintain two separate and independent transmission lines and two independent sources of electrical energy. The parties will be referred to hereinafter as the city and the power company.

Article 2. The city grants to the power company easement over the streets and city property necessary to the transmission of the electric energy and the use of the city’s substation within the city. Article 3 provides for the removal, within four months after the termination of the contract, all property of the power company from the streets and property of the city. Article 4 binds the city not to generate energy or purchase it elsewhere except when the power company was unable to furnish it or refused, without *640 legal excuse, so to do. Article 5 provides for the price or amount to be paid for electric energy by the city to the power company so consumed by it or by the city sold to its customers.

Article 6 provides for the delivery to the city of the energy, its measurements, and other items not material to a disposition of the case at bar. Article 7 makes it the duty of the power company to render statements to the city each month for electric energy delivered. Article 8 provides that in emergencies the city may generate with its equipment electric energy. The ownership of generating units by the city in no manner affects the penalties imposed'by the city for its failure to supply the energy as required by the terms of the contract. Article 9 fixed the liability of the city and the power company for injuries to persons and property while operating under the several provisions of the contract. Articles 10 and 11 are not material or pertinent for a consideration and ruling on the facts in this controversy.

Pertinent provisions of the contract are found in Article 12, which is viz:

“Article 12. The service which the company agrees to furnish to the city shall be continuous and uninterrupted, and both of the company’s said sources of electric energy shall be kept available for such purpose, unless the company is prevented from delivering electric energy hereby agreed to be furnished by the Act of God, or cause or causes beyond its control, or by any emergency in which the company may be compelled to act to prevent injuries to life, person or property of another, but where flood or drought is claimed to be an act of God, it shall not be excused where the same could have been reasonably anticipated and provided against, but even where interruptions are excused by act of God or for causes beyond the control of the company, the company shall be diligent in restoring its service after any such interruption, and if such service can be continued from any of the sources of electric energy available to the company, the same shall be promptly resorted to and electric energy supplied therefrom, and the company agrees to keep such sources of electric energy immediately available to meet any *641 such emergency, and interrupted service shall be excused only until the company by the exercise of such diligence as the emergency demands can make available any of its sources of electric energy and deliver the same to the city.
“It is agreed by the company that when the voltage falls below twenty-one (2100) volts for a continuous period of more than fifteen (15) minutes, the service shall be considered and treated as interrupted service and shall come within the penalties herein provided for such service. The city shall install recording volt meters of a standard make at the point of delivery to determine voltage and show interrupted service, and the records made by these instruments shall be controlling, The company will have the privilege of testing these instruments at any time, provided the city manager or other authorized representative of 'the city is present.
“The company shall use due and reasonable diligence to provide a regular and uninterrupted supply of electric energy, but in case such supply shall be interrupted or be defective or fail for any cause, it shall be required to exercise all reasonable diligence in order to resume the normal supply of electric energy as quickly as practicable, but in any event it is mutually agreed that failures of energy or power shall be within the following limits, to wit: Interruptions not exceeding ten (10) consecutive minutes, or a total of thirty (30) minutes in any two (2) calendar days during any month, or total of two (2) hours during any month shall be disregarded. Should the said total exceed two (2) hours in any month, however, the company agrees to pay the city as liquidated damages, an amount equal to the amount which will be due the company by the city to be determined as follows: The quantity of energy to be estimated on the basis of the energy consumed during the same hour or hours of the previous day or days at the average cost rate for the month in which said interruption or interruptions occur multiplied by the following factors: (If interruptions occur during the same hour or hours on successive days, the quantity of energy to be estimated and determined on the basis of the energy consumed during the same hour or hours on the last day- or days previous in which no interruption or interruptions occurred.)
*642 Factor
Total of two hours in one month 0
Total of two to three hours in one month 2
Total of three to four hours in one month 5
Total of four to six hours in one month 10
Total of six to eight hours in one month 15
All over eight hours in one month 20
It is further agreed that should the said interruptions exceed a total of twelve (12) hours per month for any two consecutive months, and said interruptions, defects or failures result from the company’s negligence, the city may terminate this agreement by ninety (90) days’ written notice to the company, and at the expiration of the said ninety (90) days period, all rights of the company under this contract shall cease, and the company shall within thirty (30) days thereafter begin the removal of all its physical property situated in the City, as provided for in Article III hereof.”

A recital of the contents of Articles 13, 14, 15, 16, 17 and 18 of the contract is unnecessary for a ruling on or a disposition of this controversy.

The record reflects that on October 7, 1941, early in the morning, a hurricane blowing up from the Gulf of Mexico, struck Tallahassee and environs. The wind reached a high velocity, rain or sheets of water, accompanied the wind, and these natural elements continued, without serious interruption, for several hours and extended over a large and broad area about the City of Tallahassee and beyond.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Hussein-Scott v. Scott
298 P.3d 179 (Alaska Supreme Court, 2013)
Stein v. Paradigm Mirasol, LLC
586 F.3d 849 (Eleventh Circuit, 2009)
Jankus v. Edge Investors, L.P.
619 F. Supp. 2d 1328 (S.D. Florida, 2009)
Mailloux v. Briella Townhomes, LLC
3 So. 3d 394 (District Court of Appeal of Florida, 2009)
Silver v. Silver
992 So. 2d 886 (District Court of Appeal of Florida, 2008)
Stein v. Paradigm Mirsol, LLC
551 F. Supp. 2d 1323 (M.D. Florida, 2008)
City of Tampa v. Ezell
902 So. 2d 912 (District Court of Appeal of Florida, 2005)
Baggett v. Baggett
640 So. 2d 1167 (District Court of Appeal of Florida, 1994)
Bingemann v. Bingemann
551 So. 2d 1228 (District Court of Appeal of Florida, 1989)
South Florida Radiation Oncology Center v. Radiation Oncology Associates Toonkel, P.A.
541 So. 2d 1348 (District Court of Appeal of Florida, 1989)
Miami Dolphins, Ltd. v. GENDEN & BACH, PA
545 So. 2d 294 (District Court of Appeal of Florida, 1989)
Arthur Rutenberg Corp. v. Pasin
506 So. 2d 33 (District Court of Appeal of Florida, 1987)
Maines v. Davis
491 So. 2d 1233 (District Court of Appeal of Florida, 1986)
City of Miami v. Robbie
454 So. 2d 606 (District Court of Appeal of Florida, 1984)
Boden v. ATLANTIC FEDERAL SAV. & LOAN ASS'N
396 So. 2d 827 (District Court of Appeal of Florida, 1981)
Bay Management, Inc. v. Beau Monde, Inc.
366 So. 2d 788 (District Court of Appeal of Florida, 1978)
Aerojet-General Corporation v. Askew
511 F.2d 710 (Fifth Circuit, 1975)

Cite This Page — Counsel Stack

Bluebook (online)
18 So. 2d 671, 154 Fla. 638, 1944 Fla. LEXIS 778, Counsel Stack Legal Research, https://law.counselstack.com/opinion/florida-power-corp-v-city-of-tallahassee-fla-1944.