Montanaro v. Montanaro

946 S.W.2d 428, 1997 WL 175249
CourtCourt of Appeals of Texas
DecidedMay 22, 1997
Docket13-95-188-CV
StatusPublished
Cited by21 cases

This text of 946 S.W.2d 428 (Montanaro v. Montanaro) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Montanaro v. Montanaro, 946 S.W.2d 428, 1997 WL 175249 (Tex. Ct. App. 1997).

Opinion

OPINION

SEERDEN, Chief Justice.

Reynaldo Montanaro and Xiomara Majew-ski, appellants, sued to enforce a settlement agreement entered on July 15, 1992 as a result of forced mediation ordered by the trial court. At a bench trial, appellees filed a motion to dismiss. The trial court granted the motion and awarded judgment to appel-lees on their counterclaims. Appellants bring three points of error claiming that the trial court erred in not enforcing the settlement agreement. We reverse and remand.

Factual Background

Appellants sued appellees for an accounting and dissolution of their business partnership, Montanaro Investments, as well as for fraud and breach of their fiduciary duties. In addition to being business partners, all the parties to this litigation are related to each other.

In May 1992, the trial court ordered the parties to mediation. On July 15, 1992, the case was settled and a written settlement agreement was signed by all parties and their counsel. The agreement provided for the conveyance by appellants of their interests in the partnership to appellees in exchange for a promise, secured by a promissory note, to pay monthly payments until appellants were effectively bought out. Specifically, it was agreed that appellees would (1) pay Majewski a lump sum payment of $6,000.00 by July 24, 1992; (2) make monthly payments to Majewski of $750.00 for a period of ten years beginning August 15, 1992; (3) make monthly payments to Reynaldo of $800.00 for a period of six and one-half years beginning August 15, 1992; and (4) secure the periodic payments with a promissory note. Additionally, the agreement provided for universal mutual releases among the parties.

Soon thereafter, problems arose regarding the settlement agreement. Specifically, the parties could not agree on the terms to be included in the promissory note. 1 Accordingly, appellants amended their petitions, asserting only a cause of action for breach of the purported settlement agreement. Appel-lees counterclaimed, seeking to recover monies appellant Reynaldo improperly took from the partnership. The trial court entered a judgment enforcing the settlement agreement in May 1993. On July 26, 1993, the court signed and entered a corrected judgment once again enforcing the settlement agreement.

In August 1993, appellees moved for a new trial on the sole ground that the parties never completed a settlement because the form of the promissory note was never agreed upon. On October 7, 1993, the trial court summarily granted the motion for new trial. Uncertain of the consequences of the order granting new trial, appellees filed a motion to clarify the order granting the new trial. 2 On March 16,1994, after a hearing on *430 appellees motion, the court entered an order setting aside the settlement agreement and ordering a trial on “all issues.”

The parties went to trial and waived a jury. Despite the trial court’s order setting aside the settlement agreement, appellants pleaded only for damages resulting from a breach of that agreement. On the first day of trial, appellees filed a motion to dismiss arguing that the settlement agreement had been set aside and was no longer before the Court. The court agreed and refused to hear any evidence concerning the settlement agreement. Although appellants made a bill of exception, they did not request the right to amend their pleadings, nor did they offer any evidence regarding the underlying factual dispute. The trial court then heard evidence concerning the appellees’ counterclaims and awarded judgments to appellees.

Disoussion

In their first point of error, appellants claim that the trial court erred in failing to enforce the written settlement agreement reached as a result of court-ordered mediation. In their third point, appellants claim that the trial court erred in entering judgment in favor of Sara because she released all claims against appellants in the settlement agreement. Essentially, appellants argue that the settlement agreement is enforceable as a matter of law.

Appellees argue that there never was a completed contract because the parties never agreed on all of the specific items to be included in the promissory note. Thus, ap-pellees argue, in the absence of those essential terms, the settlement agreement is unenforceable as a matter of law.

A settlement agreement is a contract, and its construction is governed by legal principles applicable to contracts generally. Old Republic Ins. Co. v. Fuller, 919 S.W.2d 726, 728 (Tex.App.—Texarkana 1996, writ denied); Stevens v. Snyder, 874 S.W.2d 241, 243 (Tex.App.—Dallas 1994, writ denied). While it is true that a contract must define its essential terms with sufficient detail to allow a court to determine the obligations of the parties, T.O. Stanley Boot Co. v. Bank of El Paso, 847 S.W.2d 218, 221 (Tex.1992); see also Gannon v. Baker, 830 S.W.2d 706, 709 (Tex.App.—Houston [1st Dist.] 1992, writ denied); University Nat’l Bank v. Ernst & Whinney, 773 S.W.2d 707, 710 (Tex.App.—San Antonio 1989, no writ), it is equally true that Texas law also confers upon those same parties the ability to agree upon certain contractual terms and to leave other matters for later negotiation. Scott v. Ingle Bros. Pacific, 489 S.W.2d 564, 555 (Tex.1972); McCulley Fine Arts Gallery v. “X” Partners, 860 S.W.2d 473, 477 (Tex.App.—El Paso 1993, no writ); Magcobar North American, Inc. v. Grasso Oilfield Services, Inc., 736 S.W.2d 787, 795 (Tex.App.—Corpus Christi 1987, writ dism’d w.o.j.); Frank B. Hall & Co. Inc. v. Buck, 678 S.W.2d 612, 629 (Tex.App.—Houston [14th Dist.] 1984, writ refd n.r.e.), cert. denied, 472 U.S. 1009, 105 S.Ct. 2704, 86 L.Ed.2d 720. It is only when an essential term of a contract is left open for future negotiations that there is no binding contract. T.O. Stanley Boot Co., 847 S.W.2d at 221; Cap Rock Elec. Coop., Inc. v. Texas Utilities Elec. Co., 874 S.W.2d 92, 99 (Tex.App.—El Paso 1994, no writ); McCulley, 860 S.W.2d at 477.

Whether an agreement is legally enforceable or binding is a question of law. Texaco, Inc. v. Pennzoil Co., 729 S.W.2d 768, 814 (Tex.App.—Houston [1st Dist.] 1987, writ ref'd n.r.e.), cert. dism’d, 485 U.S. 994, 108 S.Ct.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Durk DeBoer v. Attebury Grain, LLC
Court of Appeals of Texas, 2024
State v. Gambling Paraphernalia, Devices, Equipment & Proceeds
356 S.W.3d 594 (Court of Appeals of Texas, 2011)
Gutierrez v. Laredo Independent School District
139 S.W.3d 363 (Court of Appeals of Texas, 2004)
Alan F. Lucke v. Janice E. Kimball
Court of Appeals of Texas, 2004
Mercedes Monroy Fidalgo v. Jaime Mansur Galan
Court of Appeals of Texas, 2003
In Re United States Brass Corp.
277 B.R. 326 (E.D. Texas, 2002)
McCreary v. Bay Area Bank & Trust
68 S.W.3d 727 (Court of Appeals of Texas, 2001)
In Re the Marriage of Nolder
48 S.W.3d 432 (Court of Appeals of Texas, 2001)
Pegasus Energy Group, Inc. v. Cheyenne Petroleum Co.
3 S.W.3d 112 (Court of Appeals of Texas, 1999)
Barnes v. Forest Hills Investment, Inc.
11 F. Supp. 2d 699 (E.D. Texas, 1998)

Cite This Page — Counsel Stack

Bluebook (online)
946 S.W.2d 428, 1997 WL 175249, Counsel Stack Legal Research, https://law.counselstack.com/opinion/montanaro-v-montanaro-texapp-1997.