Partners in Building, L.P. v. Bryan Joseph Jamail

CourtCourt of Appeals of Texas
DecidedDecember 16, 2004
Docket03-03-00709-CV
StatusPublished

This text of Partners in Building, L.P. v. Bryan Joseph Jamail (Partners in Building, L.P. v. Bryan Joseph Jamail) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Partners in Building, L.P. v. Bryan Joseph Jamail, (Tex. Ct. App. 2004).

Opinion

TEXAS COURT OF APPEALS, THIRD DISTRICT, AT AUSTIN



NO. 03-03-00709-CV



Partners in Building, L.P., Appellant



v.



Bryan Joseph Jamail, Appellee



FROM THE DISTRICT COURT OF TRAVIS COUNTY, 200TH JUDICIAL DISTRICT

NO. GN201598, HONORABLE PAUL DAVIS, JUDGE PRESIDING



M E M O R A N D U M O P I N I O N



This is a dispute between Bryan Jamail, a property developer, and Partners in Building ("PIB"), a homebuilder, concerning the enforceability of a settlement agreement they entered into after PIB attempted to terminate a previous sales contract. The district court ordered PIB to perform under the terms of that settlement agreement. PIB claims in six issues on appeal that the trial court erred (1) because Jamail failed to plead that he was able to perform under the terms of the agreement; (2) in finding that the settlement agreement superceded their previous sales contract; (3) in concluding that Jamail substantially completed his duties under the original contract; (4) in determining that PIB did not plead an affirmative defense; (5) because the evidence establishes the existence of a unilateral mistake; and (6) because it was impossible for Jamail to perform under the terms of the agreement on the date of trial. For the reasons stated below, we affirm the judgment of the district court.



BACKGROUND

In late 1998, Jamail purchased thirty acres off Highway 290 in southwestern Travis County. In June 2001, he entered into a contract to sell a section of the property ("Section 4"), subdivided into twenty-seven lots, to PIB. According to the terms of the sales contract, Jamail was to improve the property and obtain the necessary permits for subdividing the property so that PIB, upon purchase, could construct houses on the lots. Upon Jamail's "substantial completion" of contract terms, PIB was to first buy eight of the subdivided lots and then buy four lots every three months until PIB had purchased all the lots constituting Section 4. The price for each lot was set at $70,000. "Substantial completion" was defined to require Jamail to have installed operational water lines with actual water service, asphalt streets with curbs, stormwater drainage facilities, streetlights and signs in accordance with local government requirements, and underground electric and telephone lines. In addition, Jamail was to have ensured that each lot was surveyed and physically pinned and staked; that each lot was free of construction debris, excavated rock, boulders, and cut trees; and that any restrictive covenants were previously approved by PIB and recorded. If Jamail failed to "substantially complete" the subdivision improvements by September 1, 2001, PIB was allowed to unilaterally terminate the contract. If not "substantially complete" by March 15, 2002, Jamail could unilaterally terminate the contract.

On June 19, 2001, the parties amended the contract by adding several conditions to the definition of "substantial completion." These additional conditions included requirements that Jamail construct sidewalks, obtain approval for a stormwater management facility, obtain approval for a landscaping maintenance and irrigation system in street right-of-ways from PIB and the City of Austin, receive a contributing zone permit for the Edwards Aquifer from the Texas Commission on Environmental Quality, and sign a release of obligations with PIB.

Jamail admits that he did not substantially complete the improvements by September 1, 2001. However, PIB did not immediately exercise its right to terminate the contract. Instead, between September 1, 2001, and February 13, 2002, PIB submitted house plans to the subdivision architectural control board, moved its sales trailer onto a lot in Section 4, and began marketing lots. However, on February 13, 2002, PIB faxed Jamail a letter in an attempt to terminate the contract. In that letter, PIB listed the items it believed were still incomplete and stated that it no longer had time to begin construction of homes to market during the upcoming summer marketing season. On May 14, Jamail filed suit in district court, alleging (i) that he had substantially performed under the terms of the contract by February 11, 2002; (ii) that PIB had represented after September 1, 2001, the date its right to terminate had vested, that it intended to close on the properties covered by the contract; (iii) that he relied on that representation in developing the property; and (iv) that PIB's actions since February 13 constituted a default under the contract. Jamail sought specific performance.

After discovery began, the parties entered into the settlement negotiations that are now at the center of the dispute. On January 24, 2003, Jamail's attorney, Brian Bishop, faxed a letter setting forth Jamail's understanding of the proposed settlement terms to Henry Novak, PIB's attorney. In that letter, Bishop stated that part of the settlement would include a commitment by PIB to purchase three lots out of the "currently available" lots in Section 4 at the "current market price list for said lots." In handwriting on that same letter, Bishop indicated that the price for each lot would be $70,000. On January 27, Novak responded by letter, confirming that PIB agreed to the settlement terms. In that letter, however, he did not mention any purchase price for the lots. Bishop responded to that letter and reiterated the $70,000 per lot purchase price. In the final written communications between Bishop and Novak, all explicit references to prices were $70,000.

Novak then drafted a written agreement, entitled "Rule 11 agreement." According to the Rule 11 agreement, PIB would purchase three lots from Jamail "at Jamail's current marketing prices." PIB would select the three lots "from Jamail's current price list for Section 4 lots, a copy of which is attached hereto as Exhibit A." Closing would occur on February 27. The agreement further provided that PIB would begin constructing houses on at least two of those properties by March 28, and Jamail warranted that he had completed all subdivision improvements to those lots and had obtained all government approvals.

Novak faxed the final version of the Rule 11 agreement to Bishop for his signature without the purchase price list that was to have been attached. Bishop signed and returned the agreement, also without a price list attached. At that point, Novak noticed that he no longer had a copy of Jamail's "current price list." He asked Bishop to fax a copy to him for attachment to the agreement. Bishop sent a price list, which Novak received on January 28. Novak attached it to the Rule 11 agreement. Novak filed the agreement with the district court on January 30, 2003. See Tex. R. Civ. P. 11. However, neither Novak nor any officer of PIB specifically read the price list sent by Bishop before Novak attached it and filed it with the Rule 11 agreement.

The filed "current price list" included a small map of the property with the lot divisions indicated.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Wal-Mart Stores, Inc. v. Canchola
121 S.W.3d 735 (Texas Supreme Court, 2003)
Ortega-Carter v. American International Adjustment Co.
834 S.W.2d 439 (Court of Appeals of Texas, 1992)
Torchia v. Aetna Casualty & Surety Co.
804 S.W.2d 219 (Court of Appeals of Texas, 1991)
Joe T. Garcia's Enterprises, Inc. v. Snadon
751 S.W.2d 914 (Court of Appeals of Texas, 1988)
Merrell Dow Pharmaceuticals, Inc. v. Havner
953 S.W.2d 706 (Texas Supreme Court, 1997)
Stewart v. Mathes
528 S.W.2d 116 (Court of Appeals of Texas, 1975)
Chessher v. McNabb
619 S.W.2d 420 (Court of Appeals of Texas, 1981)
Plas-Tex, Inc. v. U.S. Steel Corp.
772 S.W.2d 442 (Texas Supreme Court, 1989)
Janak v. Federal Deposit Insurance Corp.
586 S.W.2d 902 (Court of Appeals of Texas, 1979)
Catalina v. Blasdel
881 S.W.2d 295 (Texas Supreme Court, 1994)
Westech Engineering, Inc. v. Clearwater Constructors, Inc.
835 S.W.2d 190 (Court of Appeals of Texas, 1992)
Montanaro v. Montanaro
946 S.W.2d 428 (Court of Appeals of Texas, 1997)
Priem v. Shires
697 S.W.2d 860 (Court of Appeals of Texas, 1985)
Volpe v. Schlobohm
614 S.W.2d 615 (Court of Appeals of Texas, 1981)
Wilson v. Dearing, Inc.
415 S.W.2d 475 (Court of Appeals of Texas, 1967)
Padilla v. LaFrance
907 S.W.2d 454 (Texas Supreme Court, 1995)
Burroughs Wellcome Co. v. Crye
907 S.W.2d 497 (Texas Supreme Court, 1995)
Thigpen v. Locke
363 S.W.2d 247 (Texas Supreme Court, 1962)
Transportation Insurance Co. v. Moriel
879 S.W.2d 10 (Texas Supreme Court, 1994)
Mantas v. Fifth Court of Appeals
925 S.W.2d 656 (Texas Supreme Court, 1996)

Cite This Page — Counsel Stack

Bluebook (online)
Partners in Building, L.P. v. Bryan Joseph Jamail, Counsel Stack Legal Research, https://law.counselstack.com/opinion/partners-in-building-lp-v-bryan-joseph-jamail-texapp-2004.