Mitchell v. Owens

185 S.W.3d 837, 2005 Tenn. App. LEXIS 648, 2005 WL 2546915
CourtCourt of Appeals of Tennessee
DecidedOctober 12, 2005
DocketE2004-02342-COA-R3-CV
StatusPublished
Cited by3 cases

This text of 185 S.W.3d 837 (Mitchell v. Owens) is published on Counsel Stack Legal Research, covering Court of Appeals of Tennessee primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Mitchell v. Owens, 185 S.W.3d 837, 2005 Tenn. App. LEXIS 648, 2005 WL 2546915 (Tenn. Ct. App. 2005).

Opinion

*838 OPINION

HERSCHEL PICKENS FRANKS, P.J.,

delivered the opinion of the court,

in which CHARLES D. SUSANO, JR., J., and SHARON G. LEE, J., joined.

Plaintiff filed an action to compel arbitration. Defendant filed an action for damages. The Trial Court combined the actions and denied arbitration and the parties proceeded to trial and final judgment. The Trial Court inter alia held that plaintiffs waived issue of arbitration. On appeal, we affirm.

The Complaint in this action was initially filed on June 10, 2001 by appellant, Dan Mitchell (“Mitchell”), against appellees John Owens and Rose Marie Owens (“the Owens”). The Complaint averred that Mitchell had entered into a contract for construction improvements on the Owens’ property, and the contract contained the following provision:

Any dispute under this agreement shall be submitted to arbitration with a single arbiter under the rules of the American Arbitration Association. The arbiter need not be an attorney or professional adjudicator and not employeed [sic] or otherwise associated with either party, but must be a person with experience and training in construction engineering and construction contracting and architecture.

Further, that a hearing on the merits “be stayed to allow the parties to proceed with arbitration pursuant to the terms of their contract”. On June 22, 2001 the Owens filed a complaint against Mitchell seeking a stay of arbitration and damages.

On July 27, 2001 the Trial Judge entered an Order consolidating the actions which stated that Mitchell would be the plaintiff and the Owens would be considered the defendants and counter-plaintiffs. The Order also provided for a stay of arbitration pending a trial on the issues of promissory fraud and fraudulent inducement.

A series of Motions for Summary Judgment and amendments were subsequently filed, and all Motions for Summary Judgment were denied on October 16, 2002. On November 4, 2002 the Owens filed amendments to their Complaint and Answer, with the defense that the arbitration clause was invalid due to improper execution, along with a Motion to Dismiss the Request for Arbitration. Mitchell responded to the Motion, insisting the arbitration clause was valid.

The Trial Court entered an Order on December 5, 2002, that granted the Owens’ Motion to dismiss Mitchell’s request for arbitration. The Order further provided that discovery would be allowed, and a Special Master would be appointed “for the hearing of all issues of fact and mixed issues of law and fact,” and that the parties were to agree on a Special Master as soon as possible or the Court would appoint one.

On January 30, 2003 Mitchell filed a Motion for Enforcement of Arbitration, and if the Court overruled his Motion, he requested permission for an interlocutory appeal.

On September 2, 2003 the Trial Court entered an Agreed Order which appointed a Special Master.

On January 7, 2004, the Trial Court entered an Order denying Mitchell’s request for enforcement of the arbitration provision and refused to grant an interlocutory appeal. Subsequently, on January 12, 2004, Mitchell filed an Application for an Extraordinary Appeal to this Court, which was denied.

The Special Master heard the issues over the course of five days (January 15-16 & 27-29, 2004), and subsequently filed a *839 123 page report on March 5, 2004, which report was confirmed by the Trial Court on June 7, 2004.

Mitchell has appealed to this Court, and the determinative issue on appeal is whether Mitchell waived the arbitration issue.

Our standard of review is de novo, and there is no presumption of correctness as to the Trial Court’s legal conclusions. T.R. Mills Contractors, Inc. v. WRH Enters., 93 S.W.3d 861, 864 (Tenn.Ct.App.2002)

The Owens argue that through Mitchell’s actions during the lower Court’s proceedings, he waived the issue of whether he was entitled to arbitrate, which was the position taken by the Trial Court.

When the Trial Court entered its Order granting the Owens’ Motion to Dismiss Request for Arbitration on December 5, 2002, Mitchell had an immediate right to appeal. Generally, an appeal of right is permitted only from a final judgment. Tenn. R.App. P. 3(a). Tennessee’s Uniform Arbitration Act, however, creates exceptions to this rule. Tenn.Code Ann. § 29-5-319 provides that:

(a) An appeal may be taken from:
(1) An order denying an application to compel arbitration made under § 29-5-303;
(2) An order granting an application to stay arbitration made under § 29-5 — 303(b);
[[Image here]]
(b) The appeal shall be taken in the manner and to the same extent as from orders or judgments in a civil action.

For the purposes of this section, “application” is to be made by motion. Tenn. Code Ann. § 29-5-317.

Although the Owens’ Motion to Dismiss Request for Arbitration was not titled as a “Motion to Stay Arbitration,” it requested that the Trial Court dismiss Mitchell’s request for arbitration and take jurisdiction of the entire controversy. Thus, in substance the Owens’ motion was an application to stay arbitration. T.R. Mills Contractors, Inc. v. WRH Enters., 93 S.W.3d 861, 865 (Tenn.Ct.App.2002) (“When construing a motion, courts look to the substance rather than the form of the motion.”). In addition, the Owens’ Motion was made under § 29-5-303(b). This section provides that “On application, the court may stay an arbitration proceeding commenced or threatened on a showing that there is no agreement to arbitrate.” Tenn.Code Ann. § 29-5-303(b). The Owens’ Motion argued that there was no agreement to arbitrate because the arbitration provision in the contract was invalid under § 29-5-302(a). The Court’s Order granting that Motion was immediately appealable by Mitchell as an appeal as of right under § 29-5-319.

Mitchell failed to assert this right. The appeal granted by § 29-5-319 “shall be taken in the manner and to the same extent as from orders or judgments in a civil action.” Tenn Code Ann. § 29-5-319(b). Under Tenn. RApp. P 4(a), an appeal as of right to the Court of Appeals must be filed within 30 days after the date of entry of the judgment appealed from. Therefore, Mitchell had until January 6, 2003 to file his notice of appeal. Mitchell did not make any such filing by that date.

In fact, Mitchell did not file any motion attacking the December 5 Order until January 30, 2003 (56 days after the December Order).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Snider v. Production Chemical Manufacturing, Inc.
191 P.3d 691 (Court of Appeals of Oregon, 2008)

Cite This Page — Counsel Stack

Bluebook (online)
185 S.W.3d 837, 2005 Tenn. App. LEXIS 648, 2005 WL 2546915, Counsel Stack Legal Research, https://law.counselstack.com/opinion/mitchell-v-owens-tennctapp-2005.