Mississippi Meadows, Inc. v. Hodson

299 N.E.2d 359, 13 Ill. App. 3d 24, 1973 Ill. App. LEXIS 1974
CourtAppellate Court of Illinois
DecidedJuly 17, 1973
Docket72-174
StatusPublished
Cited by13 cases

This text of 299 N.E.2d 359 (Mississippi Meadows, Inc. v. Hodson) is published on Counsel Stack Legal Research, covering Appellate Court of Illinois primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Mississippi Meadows, Inc. v. Hodson, 299 N.E.2d 359, 13 Ill. App. 3d 24, 1973 Ill. App. LEXIS 1974 (Ill. Ct. App. 1973).

Opinion

Mr. JUSTICE STOUDER

delivered the opinion of the court:

Plaintiff-Appellee, Mississippi Meadows, Inc., brought this action against Gary Hodson, Defendant-Appellant, in the Circuit Court of Rock Island County to recover damages allegedly caused by the negligence of defendant. Plaintiff, a contractor who submitted the successful bid for construction of an eleven building apartment complex, entered into a contract with the owner of the real estate, Prince Hall Village, Inc., based on plans and specifications prepared by defendant. Under plaintiff’s theory of the case, defendant’s plans and specifications were followed; however, due to defendant’s errors and omissions therein, plaintiff was required to make changes in the construction requiring materials and labor in addition to those originally contemplated, the expense of which plaintiff was required to bear.

Plaintiff’s action was predicated on eleven claims of negligence; however, only three of these were submitted to the jury. The jury returned a verdict in favor of plaintiff for $30,000 upon which the trial court entered judgment. The three claims were based on a breach of defendant’s duty to prepare plans conforming to existing topography and complying with existing building regulations. More specifically, it is alleged that defendant’s “error in topography” required plaintiff to obtain extra fill and foundation extensions in order to comply with the city building codes and the defendant’s plans failed to provide for steel plates in all headers on exterior walls requiring plaintiff to install plates to comply with city building codes.

The principal assignments of error on this appeal relate to the sufficiency of the evidence. Defendant’s principal contention is the evidence is insufficient to raise a jury question or support the jury’s verdict in accord with the Pedrick rule. Consequently, according to defendant, the trial court erred in refusing to direct a verdict in his favor and in failing to grant his motion for judgment notwithstanding the verdict.

According to paragraph 8(a) of the complaint, “Defendant’s error in topography required plaintiff to obtain and place 2,132 cubic yards of fill dirt and 1,610 cubic yards of grandular sand mixture upon the constraction site in order to comply with City Building Regulations for frost lines.” Paragraph 8(e) of the complaint alleges: “Defendant’s error in topography required plaintiff to install foundation extensions on all buildings and change the exterior grades to comply with city building regulations for frost lines.” These allegations of negligence are each based on the same claimed misconduct namely, the negligence of defendant Hodson in the preparation of the topography plans submitted to plaintiff, which were the basis of the contract for the construction project.

An architect’s efficiency in preparing plans and specifications is tested by the rule of ordinary and reasonable skill usually exercised by one in that profession. (See Annot., 25 A.L.R.2d 1088.) The duty of an architect depends upon the particular agreement he has entered with the person who employs him and in the absence of a special agreement he does not imply or guarantee a perfect plan or satisfactory result; rather, he is only liable if he fails to exercise reasonable care and skill. 5 Am.Jur.2d, Architects, Sec. 8.

In reviewing the complaint it should be noted plaintiff fails to describe the alleged error or in any way specify ultimate facts which constitute any particular error by defendant. Also, the complaint fails to specify the code or the section of a code involved or any duty set forth by a code which was allegedly violated by defendant’s topographical plan. Not only do the allegations of negligencé in the pleadings appear to be inadequate, but also the instructions given to the jury, which are worded similarly to the complaint, must have been confusing. Indeed it is difficult to understand how the jury could measure the defendant’s conduct to determine the existence of negligence without being told what specific errors in topography allegedly were made by defendant or which building code or section thereof was allegedly violated.

Verbeke, a licensed surveyor testifying in behalf of defendant, described his activities in 1966 at which time he ascertained and laid out the boundaries and elevations of the area of the construction site. He prepared a survey of the area using as a reference point to determine elevations, the top of a fire hydrant located on the north line of the property. The top of the fire hydrant was the bench mark or reference point from which the relative elevations of various points on the property were ascertained. In the survey the bench mark was arbitrarily described as “100” and both contour lines and grid points were described in relation to the bench mark. On the survey grid points were designated at intervals of 100 feet. Contour lines were shown in one foot intervals designated with reference to the bench mark of “100”, all points along each line being of the same elevation. There were contour lines indicating elevations such as 100, 99, 98, 97 and 96. In describing the meaning of the contour Hnes, the witness indicated the area between Hnes gradually increased or decreased in elevation depending on whether the change in elevation was considered with reference to the smaHer numbered line proceeding to the higher numbered line or in the reverse. Verbelce testified that he rechecked his survey in 1968 and it was the same as in 1966. Grid points were designated in fractional feet such as 96.94, and consequently did not necessarily appear on' the contour lines which were described in terms of whole numbered feet. This witness had examined the plans prepared by the defendant which were submitted to the plaintiff and testified the topography plan was substantially the same as his survey except the grid points were not included on the defendant’s plan. He also referred briefly to a second pagó of the topography plans, referred to as a grading site improvement plan, which reflected the finished contour lines. Except for describing and interpreting the meaning of the points and lines on his own survey and indicating the defendant’s plans did not include the grid points, this witness offered no testimony either on direct examination or cross examination concerning the significance or effect of failure to include the grid points and offered no testimony whether it was or was not necessary to include such points on the plan.

According to the plaintiff, because defendant did not include grid points, it was required to provide substantial amounts of dirt and sand for fill which it could not determine were required from the plans. Because of the additional sand and dirt fill the depth of the foundation had to be increased requiring more concrete and labor. Grading and excavation by a subcontractor of the plaintiff had been in progress for several weeks before plaintiff voiced its complaint that more fill would be required than it had expected. Consequently, a significant portion of the testimony concerned the peripheral issues of whether the subcontractor had removed part of the dirt and whether he had removed too much of the dirt. Such evidence had no significant bearing on the issue of defendant’s misconduct and was more directly related to the question of damages on the assumption plaintiff might be entitled to a recovery.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Adrian Smith + Gordon Gill Architecture LLP v. Chicago Shakespeare Theater
2024 IL App (1st) 230133 (Appellate Court of Illinois, 2024)
Taake v. WHGK, INC.
592 N.E.2d 1159 (Appellate Court of Illinois, 1992)
Ferentchak v. Village of Frankfort
475 N.E.2d 822 (Illinois Supreme Court, 1985)
Greenhaven Corp. v. Hutchcraft & Associates, Inc.
463 N.E.2d 283 (Indiana Court of Appeals, 1984)
Rosos Litho Supply Corp. v. Hansen
462 N.E.2d 566 (Appellate Court of Illinois, 1984)
Klein v. Catalano
437 N.E.2d 514 (Massachusetts Supreme Judicial Court, 1982)
Bates & Rogers Construction Corp. v. North Shore Sanitary District
414 N.E.2d 1274 (Appellate Court of Illinois, 1981)
City of Mounds View v. Walijarvi
263 N.W.2d 420 (Supreme Court of Minnesota, 1978)

Cite This Page — Counsel Stack

Bluebook (online)
299 N.E.2d 359, 13 Ill. App. 3d 24, 1973 Ill. App. LEXIS 1974, Counsel Stack Legal Research, https://law.counselstack.com/opinion/mississippi-meadows-inc-v-hodson-illappct-1973.