Adrian Smith + Gordon Gill Architecture LLP v. Chicago Shakespeare Theater

2024 IL App (1st) 230133
CourtAppellate Court of Illinois
DecidedSeptember 27, 2024
Docket1-23-0133
StatusPublished

This text of 2024 IL App (1st) 230133 (Adrian Smith + Gordon Gill Architecture LLP v. Chicago Shakespeare Theater) is published on Counsel Stack Legal Research, covering Appellate Court of Illinois primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Adrian Smith + Gordon Gill Architecture LLP v. Chicago Shakespeare Theater, 2024 IL App (1st) 230133 (Ill. Ct. App. 2024).

Opinion

2024 IL App (1st) 230133

No. 1-23-0133

Opinion filed September 27, 2024

FIFTH DIVISION

IN THE APPELLATE COURT OF ILLINOIS FIRST JUDICIAL DISTRICT

ADRIAN SMITH + GORDON GILL ) Appeal from the ARCHITECTURE LLP, ) Circuit Court of ) Cook County. Plaintiff-Appellee, ) ) No. 18 L 006287 v. ) ) Honorable CHICAGO SHAKESPEARE THEATER, ) James E. Snyder, ) Judge, presiding. Defendant-Appellant. )

JUSTICE MITCHELL delivered the judgment of the court, with opinion. Presiding Justice Mikva and Justice Navarro concurred in the judgment and opinion.

OPINION

¶1 Defendant Chicago Shakespeare Theater appeals the circuit court’s order granting plaintiff

Adrian Smith + Gordon Gill Architecture LLP’s motion for summary judgment on defendant’s

counterclaim. The counterclaim alleged that plaintiff breached an owner-architect agreement by

failing to provide architectural services with “professional care” in connection with the installation

of limited use elevators. At issue is whether the circuit court erred in entering judgment as a matter

of law in favor of plaintiff on defendant’s counterclaim because the alleged breach of contract

claim did not require expert testimony and, even if it did, defendant’s expert was competent to

testify on the applicable standard of care. For the following reasons, we affirm. No. 1-23-0133

¶2 I. BACKGROUND

¶3 The following uncontested facts are taken from the pleadings, depositions, admissions, and

supporting affidavits of record. Defendant Chicago Shakespeare Theater is a theater company

located in Chicago, Illinois. In 2013, defendant initiated plans to re-purpose its outdoor Chicago

Skyline Stage at Chicago’s Navy Pier into a flexible indoor theater called The Yard. The Yard

would include nine mobile towers, each containing three levels of seating, that could be rearranged

to meet the needs of each production. To design The Yard, defendant hired CharcoalBlue LLP, a

London-based theater design consultancy company. However, because CharcoalBlue did not have

a license to practice architecture in the United States, defendant also hired plaintiff Adrian Smith

+ Gordon Gill Architecture LLP.

¶4 In April 2014, plaintiff and defendant entered into a sub-consultant agreement under which

plaintiff agreed to provide certain design services for the lobby pavilion and exterior enclosure and

serve as the architect of record for The Yard project. Given the project’s limited budget, in late

2014 the parties explored using limited use / limited application elevators for The Yard. The

limited use elevators would be “Orion” models provided by Savaria Corporation. In December

2014, plaintiff informed CharcoalBlue that plaintiff had met with Savaria’s local representative,

Access Elevator Inc., and had been informed that the maximum capacity of a limited use elevator

is “approximately (5)-(6) persons” and that “[limited use] elevators are not fast,” so “[i]t was

estimated that a round trip for one floor in the lobby would be approximately one (1) minute” or,

if both elevators are running, “approximately fifty (50) persons in about five (5) minutes.”

¶5 In March 2015, the general contractor for The Yard project at that time, James McHugh

Construction Co., expressed concern over the use of the limited use elevators:

-2- No. 1-23-0133

“Our elevator contractors have expressed concern that the [limited use elevators]

as shown on the project may not meet code and may not pass review by the Elevator

Bureau. They are also concerned that the elevators as shown may not be ADA compliant.

The bidders noted that the [limited use] elevators specified are not designed to be in

continuous use as a conventional elevator. *** Given the location and layout of these

elevators, the elevator manufacturer has expressed concern that these elevators would be

used improperly, therefore leading to malfunction and damage to the elevators.”

¶6 In response, plaintiff stated that “[w]e were able to catch up to the [limited use elevator]

representative that we all met with back in December” and that “[h]e was confident that the systems

will perform as they are intended in their current configuration for the theater and lobby.” Savaria

stated that while “50 trips a day” was “heavy use” and “100 trips a day” was “excessive use,”

“[w]e have Orion’s in service with excessive use and running fine because the dealer and owners

understands they need monthly maintenance and will require frequent consumable parts such as

slide guides, ropes etc.”

¶7 On November 1, 2015, plaintiff and defendant entered into a written owner-architect

agreement for plaintiff to provide certain architectural services for The Yard project. The

agreement acknowledged that plaintiff had already provided design services for the project, and

that all services performed before February 25, 2015 were to have been performed with

“professional care”:

“Architect and Architect’s consultants listed in this Agreement provided services

under letters of intent, preliminary agreements and oral agreements for the Conceptual

Design, Schematic Design, Design Development Documents and all other services prior to

-3- No. 1-23-0133

the February 25, 2015 Owner approval of the Design Development Documents. All such

services were to have been performed with professional care and are represented to Owner

as completed and paid for by Owner. All services thereafter are deemed provided under

this Agreement.”

The agreement also stated plaintiff’s standard of care for all services provided after February 25,

2015:

“The Architect shall perform its services consistent with the professional skill and

care ordinarily provided by architects practicing in the same or similar locality under the

same or similar circumstances. The Architect shall perform its services as expeditiously as

is consistent with such professional skill and care and the orderly progress of the Project.”

¶8 Plaintiff ultimately specified two limited use elevators to serve as lobby elevators and two

limited use elevators to operate in the mezzanine. Access Elevator was retained as a subcontractor

for the limited use elevators’ installation. On The Yard’s opening night in 2017, all four limited

use elevators failed to operate correctly, trapping patrons inside the elevators. While some of the

problems were caused by the improper installation of two of the limited use elevators, even after

the installation issues were fixed, all the limited use elevators continued to malfunction. Defendant

hired an elevator consultant and, following the consultant’s recommendations, replaced the limited

use elevators with a hydraulic elevator system.

¶9 In 2018, plaintiff sued defendant for breach of contract, account stated, quantum meruit,

conversion, and fraud, seeking payment on allegedly unpaid invoices related to replacing the

limited use elevators and a 2015 reimbursable expense. Defendant filed a counterclaim for breach

of contract, alleging that plaintiff owed defendant a duty of professional care in its architectural

-4- No. 1-23-0133

services and that plaintiff breached its duty by specifying limited use elevators that could not meet

defendant’s performance requirements.

¶ 10 In discovery, defendant disclosed two expert witnesses: Dennis Olson and Adam

Tymowski. Ill. S. Ct. R. 213(f)(3) (eff. Jan. 1, 2018). Olson would provide testimony on plaintiff’s

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Mississippi Meadows, Inc. v. Hodson
299 N.E.2d 359 (Appellate Court of Illinois, 1973)
Compton v. Ubilluz
819 N.E.2d 767 (Appellate Court of Illinois, 2004)
Jones v. Chicago HMO Ltd. of Illinois
730 N.E.2d 1119 (Illinois Supreme Court, 2000)
Walski v. Tiesenga
381 N.E.2d 279 (Illinois Supreme Court, 1978)
People v. Clifton
795 N.E.2d 887 (Appellate Court of Illinois, 2003)
Mielke v. Condell Memorial Hospital
463 N.E.2d 216 (Appellate Court of Illinois, 1984)
Rosos Litho Supply Corp. v. Hansen
462 N.E.2d 566 (Appellate Court of Illinois, 1984)
Advincula v. United Blood Services
678 N.E.2d 1009 (Illinois Supreme Court, 1996)
People v. Nelson
922 N.E.2d 1056 (Illinois Supreme Court, 2009)
Thompson v. Gordon
851 N.E.2d 1231 (Illinois Supreme Court, 2006)
Lee v. Chicago Transit Authority
605 N.E.2d 493 (Illinois Supreme Court, 1992)
Ferentchak v. Village of Frankfort
475 N.E.2d 822 (Illinois Supreme Court, 1985)
Fence Rail Development Corp. v. Nelson & Associates, Ltd.
528 N.E.2d 344 (Appellate Court of Illinois, 1988)
JPMorgan Chase Bank, N.A. v. Earth Foods, Inc.
939 N.E.2d 487 (Illinois Supreme Court, 2010)
Thompson v. Gordon
948 N.E.2d 39 (Illinois Supreme Court, 2011)
Studt v. Sherman Health Systems
2011 IL 108182 (Illinois Supreme Court, 2011)
Wilson v. University of Chicago Medical Center
2023 IL App (1st) 230078 (Appellate Court of Illinois, 2023)

Cite This Page — Counsel Stack

Bluebook (online)
2024 IL App (1st) 230133, Counsel Stack Legal Research, https://law.counselstack.com/opinion/adrian-smith-gordon-gill-architecture-llp-v-chicago-shakespeare-theater-illappct-2024.