Millis Construction Co. v. Fairfield Sapphire Valley, Inc.

358 S.E.2d 566, 86 N.C. App. 506, 1987 N.C. App. LEXIS 2742
CourtCourt of Appeals of North Carolina
DecidedAugust 4, 1987
Docket8630SC1209
StatusPublished
Cited by40 cases

This text of 358 S.E.2d 566 (Millis Construction Co. v. Fairfield Sapphire Valley, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals of North Carolina primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Millis Construction Co. v. Fairfield Sapphire Valley, Inc., 358 S.E.2d 566, 86 N.C. App. 506, 1987 N.C. App. LEXIS 2742 (N.C. Ct. App. 1987).

Opinion

EAGLES, Judge.

Defendant assigns error to the trial judge’s refusal to charge the jury on the issue of anticipatory breach as requested by the defendant pursuant to G.S. 1A-1, Rule 51(b).

It is the duty of the trial judge without any special requests to instruct the jury on the law as it applies to the substantive features of the case arising on the evidence. Faeber v. E.C.T. Corp., 16 N.C. App. 429, 192 S.E. 2d 1 (1972). When a party ap *510 propriately tenders a written request for a special instruction which is correct in itself and supported by the evidence, the failure of the trial judge to give the instruction, at least in substance, constitutes reversible error. Bass v. Hocutt, 221 N.C. 218, 19 S.E. 2d 871 (1942); Faeber v. E.C.T. Corp., supra. Here, we believe the trial court improperly refused to give the requested instruction on anticipatory breach.

The trial court submitted two issues to the jury on breach of contract: Did the defendant breach its contract with the plaintiff and did the plaintiff breach its contract with the defendant? Breach of contract occurs when a party fails to perform a contractual duty which has become absolute. J. Calamari and J. Perillo, The Law of Contracts section 12-1, at 513 (3d ed. 1987). As explained by the Restatement when performance of a duty under contract is presently due any nonperformance constitutes a breach. Restatement (Second) of Contracts section 235(2) (1981). Breach may also occur by repudiation. Id. at section 236 comment a. Repudiation is a positive statement by one party to the other party indicating that he will not or cannot substantially perform his contractual duties. Calamari and Perillo, section 12-4, at 524; Restatement (Second) of Contracts at section 250 comment a. When a party repudiates his obligations under the contract before the time for performance under the terms of the contract, the issue of anticipatory breach or breach by anticipatory repudiation arises. Calamari and Perillo, section 12-3, at 521. One effect of the anticipatory breach is to discharge the non-repudiating party from his remaining duties to render performance under the contract. Restatement (Second) of Contracts at section 253(2).

[W]hen a party to a contract gives notice that he will not honor the contract, the other party to the contract is no longer required to make a tender or otherwise to perform under the contract because of the anticipatory breach of the first party.

Dixon v. Kinser and Kinser v. Dixon, 54 N.C. App. 94, 101, 282 S.E. 2d 529, 534 (1981), disc. rev. denied, 304 N.C. 725, 288 S.E. 2d 805 (1982).

Here there was sufficient evidence to support an instruction that the plaintiff’s statements during the November 16 meeting constituted a repudiation. In order to constitute a repudiation, a *511 party’s statement “must be sufficiently positive to be reasonably interpreted that a party will not or cannot substantially perform.” Calamari and Perillo, section 12-4, at 525 (quoting Restatement (Second) of Contracts at section 250 comment b). For example, if a party to a contract states “I doubt I will perform,” his statement, alone, is not sufficiently positive to be reasonably interpreted by the other party to mean that he will not perform. Id. at 524. However, if a party to the contract states that he cannot perform except on some condition which goes outside the terms of his contract then the statement will constitute a repudiation. Id. at 525. Applying these rules to the facts here, we hold that plaintiffs statements on November 16 could have constituted a repudiation. According to defendant’s evidence, at the meeting between Coker and Millis, Millis stated that he was “busted,” “belly-up” and would be unable to complete the contract unless he received re-tainage on building number 7. However, according to the terms of the contract, plaintiff was not entitled to retainage until 30 days after building number 7 was completed. At the time of the November 16 meeting building number 7 was not yet completed. Clearly at the time of the November 16 meeting, plaintiff was not yet entitled to any retainage under the terms of the contract. In essence, his statement was that he could not perform the remaining contracts except on some condition outside the terms of the contracts, i.e. that he be paid the retainage before he was entitled to it under the contract.

If the repudiation occurs before the time of performance arises under the contract, the repudiation is anticipatory and the issue of anticipatory breach arises. Here plaintiffs statements were made on November 16, at least one month before completion of buildings 8, 9 and 10 was required under the terms of plaintiffs contracts. The effect of breach by anticipatory repudiation is to relieve the non-repudiating party from further performance under the contract. Dixon v. Kinser, supra. We agree with defendant’s argument that had the jury been given the opportunity to consider the issue of anticipatory breach, it could have found that the defendant did not breach its contract with plaintiff but was no longer required to perform under the contract due to plaintiffs anticipatory breach or breach by anticipatory repudiation. Dixon v. Kinser, supra. Accordingly, the trial court erred in refusing to *512 instruct the jury on the issue of anticipatory breach as requested by defendant.

The issue of anticipatory breach does not affect defendant’s obligation under its contracts to pay for work performed, invoiced and approved as of the date of the November 16 meeting, where defendant alleges plaintiff anticipatorily breached its contracts with defendant. Up until that date plaintiff had fully performed. The evidence suggests that plaintiff was owed money for work performed, invoiced and approved by defendant as of 16 November 1984 and that defendant without justification refused to pay for that work. Plaintiffs exhibit number four sets out the following amounts as being owed for invoices not paid: $3,064.50 for building number 8; $5,172.75 for building number 9; and $2,034.00 for building number 10. In addition, plaintiffs exhibit number four indicates that plaintiff was overpaid in the amount of $1,675.95 for work completed, invoiced and approved on building number 7. Plaintiff also claims retainage on buildings 8, 9 and 10 in the amounts of $1,276.89, $2,548.98 and $1,588.00 respectively. However, plaintiff never satisfactorily completed buildings 8, 9 and 10 and consequently would only be entitled to retainage on these buildings if it is found by the trier of the fact that defendant materially breached its contract with plaintiff. The general rule governing bilateral contracts requires that if either party commits a material breach of the contract, the other party should be excused from the obligation to further perform. Coleman v. Shirlen, 53 N.C. App. 573, 281 S.E. 2d 431 (1981). The question of whether a breach is material or immaterial is ordinarily a question of fact. Id. If the breach is material, the aggrieved party may cancel the contract and sue for total breach if he can show that he was ready, willing and able to perform but for the breach. See Calamari and Perillo, section 11-18, at 458.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Untitled Case
M.D. North Carolina, 2026
Maldon v. Scott
Court of Appeals of North Carolina, 2026
Auto Provisions, LLC v. G1.34 Holdings, LLC
North Carolina Business Court, 2026
Howard v. Iomaxis, LLC
2022 NCBC 76 (North Carolina Business Court, 2022)
Crescent Univ. City Venture, LLC v. Ap Atl., Inc.
2019 NCBC 46 (North Carolina Business Court, 2019)
Chisum v. Campagna
2019 NCBC 27 (North Carolina Business Court, 2019)
N.C. Farm Bureau Mut. Ins. Co. v. Hull
795 S.E.2d 420 (Court of Appeals of North Carolina, 2016)
Sitelink Software, LLC v. Red Nova Labs, Inc.
2016 NCBC 43 (North Carolina Business Court, 2016)
Brock v. Johnson Breeders, Inc.
775 S.E.2d 925 (Court of Appeals of North Carolina, 2015)
Christenbury Eye Ctr., P.A. v. Medflow, Inc.
2015 NCBC 61 (North Carolina Business Court, 2015)
Tai Sports, Inc. v. Hall
2012 NCBC 62 (North Carolina Business Court, 2012)
Williams v. Habul
724 S.E.2d 104 (Court of Appeals of North Carolina, 2012)
Sirsi Corp. v. Craven-Pamlico-Carteret Regional Library System
815 F. Supp. 2d 931 (E.D. North Carolina, 2011)
D.G. II, LLC v. Nix
712 S.E.2d 335 (Court of Appeals of North Carolina, 2011)
Profile Investments No. 25, LLC v. Ammons East Corp.
700 S.E.2d 232 (Court of Appeals of North Carolina, 2010)
Broadbent v. Allison
626 S.E.2d 758 (Court of Appeals of North Carolina, 2006)
Oakes v. Wooten
620 S.E.2d 39 (Court of Appeals of North Carolina, 2005)
VF Jeanswear Ltd. Partnership v. Molina
320 F. Supp. 2d 412 (M.D. North Carolina, 2004)

Cite This Page — Counsel Stack

Bluebook (online)
358 S.E.2d 566, 86 N.C. App. 506, 1987 N.C. App. LEXIS 2742, Counsel Stack Legal Research, https://law.counselstack.com/opinion/millis-construction-co-v-fairfield-sapphire-valley-inc-ncctapp-1987.