Miller v. Merritt

60 A. 508, 211 Pa. 127, 1905 Pa. LEXIS 421
CourtSupreme Court of Pennsylvania
DecidedMarch 6, 1905
DocketAppeal, No. 154
StatusPublished
Cited by15 cases

This text of 60 A. 508 (Miller v. Merritt) is published on Counsel Stack Legal Research, covering Supreme Court of Pennsylvania primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Miller v. Merritt, 60 A. 508, 211 Pa. 127, 1905 Pa. LEXIS 421 (Pa. 1905).

Opinion

Opinion by

Mr. Justice Mestrbzat,

There was ample evidence submitted to the jury to justify [129]*129them in finding that the concrete used in the construction of the floors and roof of the building was defective by reason of improper or negligent mixing, and that the roof fell by reason of the defective concrete or premature removal of the “ centres ” which are temporary wooden structures used to support the plastic concrete work of the roof before it had become hard. The learned judge charged as to the concrete as follows: “I say there is evidence tending to show that the concrete was not properly mixed in the process, and that it was not properly made when it was done; that is, that the result showed that the process was wrong. You will remember the evidence of those witnesses who tended to show that. On the other hand, there is evidence on the other side to show that the process was excellent and that the result was excellent. There is a square issue of fact. One or the other, or perhaps in a degree both, may be incorrect; but it is for you to decide whether upon the whole there was any negligence on the part of the defendants, Merritt & Company, in mixing the concrete, so that from the defective nature of its mixing it produced the fall and the consequent injury to the decedent.” It was also alleged by the plaintiff that the roof collapsed by reason of the defendants having prematurely removed the “ centres ” before the concrete had hardened sufficiently to support the additional weight and tamping of the material placed upon the roof by the defendants to make the drainage slopes. The trial judge properly submitted the question to the jury in the following language of his charge: “ It appears that when they had got that base line done, they took this flooring off and they put this other stuff on and tamped it without a bottom to it. It is alleged here that that is not good work and that that really produced the mischief. That is a question of fact for you. It is averred on the one side and contradicted on the other. You will have to consider the weight of the evidence, and if you find that that did not produce the effect, of course the defendants cannot be charged in respect to it. If you, after examining all the reasons, cannot find what did produce the effect, then the defendants are not to be charged, because negligence must be affirmatively proved. But if you find that the tamping with the bottom off did produce the result, then the defendants are liable and must answer in damages.”

[130]*130Under these instructions, the verdict of the jury sustains the contention of the plaintiff that the death of Wilbur F. Miller, an employee of the owner of the building, resulting from the fall of the roof, was caused by the negligence of the defendants in using defective material in constructing the roof and in failing to properly support the roof until the concrete had hardened sufficiently to sustain the additional weight placed upon it by the defendants.

The learned counsel for the defendants, however, insist in their argument that there was no evidence to support the contention that the accident was caused by the improper mixing of the concrete or premature removal of the centres. The concrete used in this building was composed of certain proportions of cement, cinders and sand. Improper mixing results in “voids” which are open spaces in the body of the concrete and weaken the material. The more numerous the voids the weaker the concrete necessarily is. Essick, the city building inspector, examined the concrete immediately after the roof and wall fell. He testified that it had not been properly mixed, was full of voids, and that none of it had the proper set. It also appeared by the testimony that the concrete was not inspected by any person after it was made by the laborers ; and as to the care with which they prepared it, one of the laborers testified that “ the quicker they mixed it up the more time we would have to ourselves.”

There was likewise sufficient testimony to go to the jury on the question of the negligent removal of the “ centres.” They were placed under the entire roof. The work of laying the concrete and tamping was begun Wednesday afternoon and finished Thursday morning. On the following day, Friday, according to the testimony of Branson, the defendants’ employee, the “ centres ” were removed from the north end of the building where the roof fell on the following Monday afternoon causing the death of the plaintiff’s husband. The roof at the south end of the building, from which the “ centres ” had not been removed, remained intact. The testimony of the defendants’ own witnesses shows that the “ centres ” should not have been removed • in less than three or four days after the cement had been laid, while the testimony of the plaintiff’s witness leads to ‘the belief that a longer time should have elapsed, one [131]*131witness, the building inspector, saying : I would not remove them under two weeks, not a day less than two weeks.”

Under this and other testimony in the case, it was clearly a question for the jury to determine whether the defective concrete and premature withdrawal of the “ centres ” caused the roof to fall, which resulted in the death of the plaintiff’s husband. If the testimony alluded to is credible, the “ centres” should have remained in position for at least three days to support the weight of the floor. The tamping and additional weight of the heavy material placed on the roof for constructing the drainage grade required that the “ centres ” should continue in place much longer. There is also the significant fact, in support of the verdict, that only that part of the roof fell from which the “ centres ” had been removed. It is true that one of the plaintiff’s witnesses testified on cross-examination that the absence of tie-rods between the I beams permitted the arches to flatten and push the wall out and that caused thfe accident. This, like the other testimony introduced to establish the cause of the accident, was submitted to the jury who were distinctly told by the court in affirming a point that “ if '.you find that the accident resulted from the absence of tie-rods, .... your verdict inust be for the defendants.” They were also instructed that “ if you, after examining all the reasons, cannot find what did produce the effect, then the defendants are not to be charged, because negligence must be affirmatively proved.” The jury, therefore, found that the accident was not caused by the absence of tie-rods, but by the improperly prepared concrete and premature removal of the “ centres ” from the part of the floor which fell.

It is further contended by the defendants that Miller was guilty of contributory negligence, that he knew the conditions at the place of the accident and assumed the risks; and further, that defendants’ employees acted under his supervision and according to his instructions in performing the work. The learned court, however, left these questions, with proper instructions, to be determined by the jury. He told the jury there could be no recovery if Miller participated in or supervised the preparation of the concrete, or the “ centres ” were removed at the request or by direction of Miller, or he had knowledge of their removal, and that “ if Wilbur Miller really acted so that these [132]*132people (defendants’ employees) obeyed him, and that he directed this thing, or knew of it, then they (defendants) cannot be held liable.”

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cary v. Gooding
34 Pa. D. & C.4th 417 (Chester County Court of Common Pleas, 1996)
Sharkey v. Airco, Inc.
522 F. Supp. 646 (E.D. Pennsylvania, 1981)
Spinozzi v. Lavino Company
243 F.2d 80 (Third Circuit, 1957)
Harry W. Boettger v. The Babcock & Wilcox Company
242 F.2d 455 (Third Circuit, 1957)
Spinozzi v. E. J. Lavino & Co.
243 F.2d 80 (Third Circuit, 1957)
Murrin v. Rifugiato
96 A.2d 865 (Supreme Court of Pennsylvania, 1953)
Bentley v. Jones
173 S.E. 737 (Court of Appeals of Georgia, 1934)
Weaver v. Foundation Co.
165 A. 381 (Supreme Court of Pennsylvania, 1933)
Tyler v. MacFadden Newspapers Corp.
163 A. 79 (Superior Court of Pennsylvania, 1932)
Flaharty v. Trout
138 A. 863 (Supreme Court of Pennsylvania, 1927)
Brooks v. Buckley & Banks
139 A. 379 (Supreme Court of Pennsylvania, 1927)
Brooks v. City of Philadelphia
9 Pa. D. & C. 72 (Philadelphia County Court of Common Pleas, 1927)
Jackman v. Rosenbaum Co.
106 A. 238 (Supreme Court of Pennsylvania, 1919)
Larsen v. United Gas Improvement Co.
180 F. 268 (U.S. Circuit Court for the District of Eastern Pennsylvania, 1910)
Bain v. Petroleum Iron Works Co.
72 A. 279 (Supreme Court of Pennsylvania, 1909)

Cite This Page — Counsel Stack

Bluebook (online)
60 A. 508, 211 Pa. 127, 1905 Pa. LEXIS 421, Counsel Stack Legal Research, https://law.counselstack.com/opinion/miller-v-merritt-pa-1905.