City of Erie v. Caulkins

85 Pa. 247, 1878 Pa. LEXIS 242
CourtSupreme Court of Pennsylvania
DecidedOctober 15, 1877
DocketNo. 40
StatusPublished
Cited by6 cases

This text of 85 Pa. 247 (City of Erie v. Caulkins) is published on Counsel Stack Legal Research, covering Supreme Court of Pennsylvania primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
City of Erie v. Caulkins, 85 Pa. 247, 1878 Pa. LEXIS 242 (Pa. 1877).

Opinion

Mr. Justice Gordon

delivered the opinion of the court, January 7th 1878.

The accident, which is the foundation of the present case, resulted from the negligence of certain workmen who were engaged in the erection or construction of a sewer for the city of Erie. The excavation for this sewer, which was in one of the public streets, having been carelessly left unguarded, the plaintiff, on the night of the 26th of November 1872, without any fault of her own, fell into it, and received the injuries complained of. , The question now before us is, who is the responsible party ? The defendant asked the court to say to the jury that, as the city had contracted with Peter Grant [251]*251to construct this sewer, it was not responsible to the plaintiff for any injury she might have sustained in consequence of the negligence of Grant, or his agents or servants. The court refused so to charge, and this on the ground that, by the contract, the city reserved the power to use the street during the progress of the- work, and to control the manner in which the work should be carried on; that it retained a power over the men employed by the contractor, and that, by the contract, it had provided for indemnity for any damages that might he recovered from it, arising from the neglect or carelessness of the contractor in doing the work. The first part of this proposition is not found in the contract, except inferentially, from the stipulation therein contained for the protection of the public from the danger of falling into the trenches, and from the upsetting of vehicles on the earth thrown out of them. It is, however, a matter of course that, in all cases of this kind, use shall be had of such parts of the streets as are not occupied by the contractor; but it is also of course, that the contractor shall have the control over such parts thereof as are necessary for the proper execution of his work. Tlxo complaint, however, is not as to such portions of the streets as were in public occupancy, but as to those which, it is conceded, were necessarily occupied by the contractor under his contract. It must not be forgotten that the complaint is not that the street was used in an unlawful or unauthorized manner, but only that there was neglect in' not erecting such guards, or in not maintaining such lights at night, as were necessary to protect the public from injury. Whether, therefore, the city did, or did not, retain the use of the street unoccupied by the work, is of no kind of significance.

The latter part of the court’s proposition is faulty in that the converse thereof was ruled in Wray v. Evans, 30 P. F. Smith 102. In that case there was this provision in the contract: “That all losses, accidents and damages of whatever kind and from whatever cause, which shall at any time happen to the work, or any person or persons whomsoever, shall be wholly borne and made good by the party of the first part.” This provision was certainly as specific as that in the contract under consideration, but because the company in that ease provided against consequences in which it could not be involved, nothing was thereby added to its liability. Just so here, because the city supposed it might be liable for the negligence of its contractor, and so provided for indemnity, that surely did not make it so liable, if it were otherwise exempt from the consequences flowing from his want of care. If, however, the broad statement that the city reserved the power, not only to control and direct the manner in which the work should be done, but, also, the power over the men employed by the contractor, be true, then, indeed, is the city responsible for the negligence of all who were engaged in the construction of the sewer. In such case Grant must be considered but as an agent, over whose acts and conduct, in the prose-[252]*252ration of the work, the city would have unlimited control, and it must, in that event, be answerable for his negligence. Is this then a correct version of the contract? This question can only be answered by that instrument itself. By the terms of this contract Peter Grant was to furnish all the material and do all the work necessary to build and complete an eighteen-inch sewer, in State street, from the centre of Fifth street to within twenty feet of the north line of Ninth street, according to the plan and specifications then on file in the office of the city engineer, which were made part of the contract. The whole job was to be done in a workmanlike manner, and under the supervision and to the satisfaction of the city engineer. In case of alterations made by the engineer in the specifications he was to decide what change, if any, should be made in the pay of the contractor. An estimate was to be made, not oftener than once every two weeks, when payment was to be made, according to the price fixed per foot for the work, fifteen per cent, being retained until the final estimate and approval of the whole job. So far, then, the whole charge of this work was put into the hands of Grant, and the city had no power o.ver it except to see that it was well done, and, to this end, stipulation was made for supervision by the city engineer, just as was the case in Wray v. Evans and Reed v. Allegheny City, 29 P. F. Smith 300.

Do the specifications so modify and change the body of the contract as to alter the status of the parties, giving the city such general control over the work as to make it the superior who shall be answerable for Grant and his employees ? Let us see. By those specifications the contractor was required to dismiss, from Ms employment, all incompetent or unfaithful persons. In this we may observe, that the statement, that the city had a general power over the men employed by the contractor, is too broad, for the contract is, that he shall dismiss, from his employment, incompetent or unfaithful employees. Herein the fact of his superior and independent control over the workmen is recognised, for if the city retained this power, why contract with Grant for the doing of that which it could, at any time, do itself? Finally, we have this provision: “All work to be commenced and carried on at such times, and in such ¡daces, and in such manner as the engineer shall direct.” The court below laid especial stress upon that clause, in the above specification, which gives the engineer the power of directing the manner in which the work should be done, and, in this, it is supposed to be borne out by an expression made by Judge Strong, in Painter v. The Mayor of Pittsburgh, 10 Wright 213, as follows: “ It is further ruled, that a clause in the 'contract, by which the contractor engaged to conform the work to such further directions as might be given by the street commissioner, did not affect the case; that it only gave the corporation the power to direct the results of the [253]*253work, without any control over the manner of performing it, which control, alone, furnishes a ground for holding the master or principal for the act of a servant or agent.” But the word manner, in the above quotation, is evidently considered as having a meaning so general as to reduce the contractor to the grade of a mere servant or agent. Manner, must, in such case, mean the power to control the w'ork, not only as to its character, hut also as to the particular means used to accomplish it. This must needs be so, for as we have seen in the case of Reed v. Allegheny, 29 P. F.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Brooks v. Buckley & Banks
139 A. 379 (Supreme Court of Pennsylvania, 1927)
Commonwealth v. McKenty
52 Pa. Super. 332 (Superior Court of Pennsylvania, 1912)
Walters v. American Bridge Co.
82 A. 1103 (Supreme Court of Pennsylvania, 1912)
Miller v. Merritt
60 A. 508 (Supreme Court of Pennsylvania, 1905)
Hookey v. Borough of Oakdale
5 Pa. Super. 404 (Superior Court of Pennsylvania, 1897)
Ginther v. Borough of Yorkville
3 Pa. Super. 403 (Superior Court of Pennsylvania, 1897)

Cite This Page — Counsel Stack

Bluebook (online)
85 Pa. 247, 1878 Pa. LEXIS 242, Counsel Stack Legal Research, https://law.counselstack.com/opinion/city-of-erie-v-caulkins-pa-1877.