Millennium Pipeline Company v. Basil Seggos

860 F.3d 696, 2017 WL 2697987, 84 ERC (BNA) 1833, 2017 U.S. App. LEXIS 11157
CourtCourt of Appeals for the D.C. Circuit
DecidedJune 23, 2017
Docket16-1415
StatusPublished
Cited by9 cases

This text of 860 F.3d 696 (Millennium Pipeline Company v. Basil Seggos) is published on Counsel Stack Legal Research, covering Court of Appeals for the D.C. Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Millennium Pipeline Company v. Basil Seggos, 860 F.3d 696, 2017 WL 2697987, 84 ERC (BNA) 1833, 2017 U.S. App. LEXIS 11157 (D.C. Cir. 2017).

Opinion

SRINIVASAN, Circuit Judge:

Millennium Pipeline Company, L.L.C., would like to extend its existing, natural gas pipeline in Orange County, New York. Before it can break ground, however, it must gain the approval of the Federal Energy Regulatory Commission (FERC). Millennium must also comply with environmental regulations like the Clean Water Act, which requires it to show that its pipeline will meet all applicable water-quality requirements. 33 U.S.C. § 1341(a)(1).

As part of that permitting process, Millennium submitted an application for a water-quality certificate to the New York State Department of Environmental Conservation. More than a year has passed, but the Department has taken no formal action on Millennium’s application. Millennium now asks us to compel the Department to act on the application.

We dismiss Millennium’s petition for review. Even if the Department has unlawfully delayed acting on Millennium’s application, its inaction would operate as a waiver, enabling Millennium to bypass the Department and proceed to obtain approval from FERC. The Department’s delay, then, causes Millennium no cognizable injury. Millennium therefore lacks standing to proceed with its petition.

I.

A.

For any company desiring to construct a natural gas pipeline, all roads lead to FERC. The Natural Gas Act of 1938 vests the agency with “exclusive jurisdiction” over the interstate transportation of natural gas. Schneidewind v. ANR Pipeline Co., 485 U.S. 293, 300-01, 108 S.Ct. 1145, 99 L.Ed.2d 316 (1988). No company or person may construct a natural gas pipeline without first obtaining “a certificate of public convenience and necessity” from the agency. 15 U.S.C. § 717f(c).

Before FERC can issue a certificate of public convenience, the agency must ensure that the proposed pipeline complies with all applicable federal, state, and local regulations. See 15 U.S.C. § 717b(d); 18 C.F.R. § 4.38. The Clean Water Act, the statute at issue in this case, is one such regulatory regime. See 33 U.S.C. § 1341(a)(1); 15 U.S.C. § 717b(d)(3). Because Millennium’s proposed pipeline would traverse several streams in southern New York, the Clean Water Act requires the State to certify that any discharge from the pipeline will comply with the Act’s water-quality requirements. 33 U.S.C. § 1341(a)(1). FERC cannot sign off on the construction until New York either grants a water-quality certificate or waives the Act’s requirements. See id.

To prevent state agencies from indefinitely delaying issuance of a federal permit, Congress gave States only one year to act on a “request for certification” under the Clean Water Act. Alcoa Power Generating Inc. v. FERC, 643 F.3d 963, 972 (D.C. Cir. 2011) (quoting 33 U.S.C. § 1341(a)(1)). That deadline is established by section 401 of the Act, which requires a State to grant or deny the certificate “within a reasonable period of time (which shall not exceed one year) after receipt of [a] request.” Id. If the State fails to act within that period, the Act’s “certification requirements” are deemed “waived,” such that the pipeline no longer needs a water- *699 quality certificate to begin construction. Id.

B.

On November 9, 2016, FERC issued a provisional certificate of public convenience for Millennium’s proposed project, a 7.8-mile extension of its existing natural gas pipeline. The Commission, however, conditioned its approval on proof of Millennium’s receipt of “all authorizations required under federal law,” including the Clean Water Act. Millennium Pipeline Co., 157 FERC ¶ 61,096, 2016 WL 6662548, at *35 (2016). To that end, Millennium must present FERC with documentation of the applicable permits or evidence of waiver thereof. Id.

Millennium had previously applied for a water-quality certificate from the New York State Department of Environmental Conservation. The Department received Millennium’s request on November 23, 2015, and responded by sending Millennium a notice of incomplete application. Over the next year, the Department sent Millennium several requests for supplemental information. Millennium has complied with the Department’s requests each time. In November 2016, the Department wrote a letter indicating that Millennium had “fully responded” to its requests, but it would “continue its review of the Application, as supplemented, to determine if a valid request for a [water-quality certificate] has been submitted.” N.Y. State Dep’t of Envtl. Conservation, Letter on Application for Section 401 Water Quality Certification, Freshwater Wetlands and Protection of Waters Permit (Nov. 18, 2016). The Department stated that it had “at a minimum, until August 30, 2017 to either approve or deny the Application.” Id.

Frustrated by the agency’s delay, Millennium brought a petition for review in this Court under section 19(d)(2) of the Natural Gas Act. That provision gives us “original and exclusive jurisdiction” to review “an alleged failure to act by a ... State administrative agency acting pursuant to Federal law to issue, condition, or deny any permit required under Federal law.” 15 U.S.C. § 717r(d)(2). If we find that an agency has delayed unlawfully, the Act requires us to remand the proceeding to the agency and “set a reasonable schedule and deadline for the agency to act on remand.” Id. § 717r(d)(3).

Millennium argues that the Department failed to act within the Clean Water Act’s one-year statutory window, and therefore asks us to compel the Department either to grant its application or to take action within a specified schedule. The Department counters that it need only act within one year of receiving a complete or valid application, and it alleges Millennium has repeatedly failed to meet that requirement.

II.

Before reaching the merits of Millennium’s claim, we first examine Millennium’s standing to sue. Article III of the Constitution limits our jurisdiction to “Cases” and “Controversies.” U.S. Const, art. Ill, § 2, cl. 1.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
860 F.3d 696, 2017 WL 2697987, 84 ERC (BNA) 1833, 2017 U.S. App. LEXIS 11157, Counsel Stack Legal Research, https://law.counselstack.com/opinion/millennium-pipeline-company-v-basil-seggos-cadc-2017.