Midwest ISO Transm v. FERC

CourtCourt of Appeals for the D.C. Circuit
DecidedJuly 16, 2004
Docket02-1121
StatusPublished

This text of Midwest ISO Transm v. FERC (Midwest ISO Transm v. FERC) is published on Counsel Stack Legal Research, covering Court of Appeals for the D.C. Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Midwest ISO Transm v. FERC, (D.C. Cir. 2004).

Opinion

Notice: This opinion is subject to formal revision before publication in the Federal Reporter or U.S.App.D.C. Reports. Users are requested to notify the Clerk of any formal errors in order that corrections may be made before the bound volumes go to press.

United States Court of Appeals FOR THE DISTRICT OF COLUMBIA CIRCUIT

Argued April 23, 2004 Decided July 16, 2004

No. 02-1121

MIDWEST ISO TRANSMISSION OWNERS, ET AL., PETITIONERS

v.

FEDERAL ENERGY REGULATORY COMMISSION, RESPONDENT

PUBLIC SERVICE COMMISSION OF THE COMMONWEALTH OF KENTUCKY, ET AL., INTERVENORS

Consolidated with 02-1122, 03-1236, 03-1256

On Petitions for Review of Orders of the Federal Energy Regulatory Commission

Paul M. Flynn argued the cause for petitioners Midwest ISO Transmission Owners, et al. John E. McCaffrey argued Bills of costs must be filed within 14 days after entry of judgment. The court looks with disfavor upon motions to file bills of costs out of time. 2

the cause for Public Service Commission of the Common- wealth of Kentucky, et al. With them on the briefs were David W. D’Alessandro, Michael E. Small, and Robert H. Benna. Jeffrey G. DiSciullo and Linda S. Portasik entered appearances. Robert H. Solomon, Deputy Solicitor, Federal Energy Reg- ulatory Commission, argued the cause for respondent. With him on the brief were Cynthia A. Marlette, General Counsel, and Dennis Lane, Solicitor. Larry D. Gasteiger, Attorney, entered an appearance. Stephen L. Teichler argued the cause for intervenors Mid- west Independent Transmission System Operator, Inc., et al. With him on the brief were Stephen G. Kozey, David Martin Connelly, Jeffrey L. Landsman, Christine C. Ryan, A. Hewitt Rose, III, Gary D. Bachman, Evan Charles Reese, III, William F. Fields, Sandra L. Hall, Susan Stevens Miller, David W. D’Alessandro, John E. McCaffrey, Robert Campbell McDiarmid, Larissa A. Shamraj, Denise C. Goulet, and David J. Lynch. Richard G. Raff entered an appearance.

Before: GINSBURG, Chief Judge, and SENTELLE and ROBERTS, Circuit Judges. Opinion for the Court filed by Circuit Judge ROBERTS. ROBERTS, Circuit Judge: I. 1. In the bad old days, utilities were vertically integrated monopolies; electricity generation, transmission, and distribu- tion for a particular geographic area were generally provided by and under the control of a single regulated utility. Sales of those services were ‘‘bundled,’’ meaning consumers paid a single price for generation, transmission, and distribution. As the Supreme Court observed, with blithe understatement, ‘‘[c]ompetition among utilities was not prevalent.’’ New York v. FERC, 535 U.S. 1, 5 (2002). 3

In its pathmarking Order No. 888, FERC required utilities that owned transmission facilities to guarantee all market participants non-discriminatory access to those facilities. See Promoting Wholesale Competition Through Open Access Non-Discriminatory Transmission Services by Public Utili- ties, FERC Stats. & Regs. ¶ 31,036, 31,635–36 (1996) (Order No. 888). That is, FERC required all transmission-owning utilities to provide transmission service for electricity gener- ated by others on the same basis that they provided transmis- sion service for the electricity they themselves generated. To effectuate this introduction of competition, FERC required public utilities to ‘‘functionally unbundle’’ their wholesale gen- eration and transmission services by stating separate rates for each service in a single tariff and offering transmission service under that tariff on an open-access, non- discriminatory basis. See New York, 535 U.S. at 11; see generally California Indep. Sys. Operator Corp. v. FERC, No. 02-1287, slip op. at 2-4 (D.C. Cir. June 22, 2004). As the next step toward the goal of a more competitive electricity marketplace, Order No. 888 encouraged — but did not require — the development of multi-utility regional trans- mission organizations (RTOs). The concern was that the segmentation of the transmission grid among different utili- ties, even if each had functionally unbundled transmission, contributed to inefficiencies that impeded free competition in the market for electric power. Combining the different seg- ments and placing control of the grid in one entity — an RTO — was expected to overcome these inefficiencies and promote competition. Order No. 888 at 31,730–32; see also Public Util. Dist. No. 1 of Snohomish County v. FERC, 272 F.3d 607, 610–11 (D.C. Cir. 2001). Better still if the RTO were run by an independent system operator — an ISO. As envisioned by FERC, an ISO would assume operational con- trol — but not ownership — of the transmission facilities owned by its member utilities, thereby ‘‘separat[ing] opera- tion of the transmission grid and access to it from economic interests in generation.’’ Order No. 888 at 31,654; see also 4

id. at 31,730–32. The ISO would then provide open access to the regional transmission system to all electricity generators at rates established in ‘‘a single, unbundled, grid-wide tariff that applies to all eligible users in a non-discriminatory manner.’’ Id. at 31,731; see also California Indep. Sys. Operator Corp., slip op. at 3–4. FERC called this type of separation of generation and transmission ‘‘operational un- bundling,’’ a step beyond ‘‘functional unbundling.’’ Order No. 888 at 31,654. Although several parties to the 1996 rulemak- ing had requested that FERC require ‘‘operational unbun- dling’’ or even divestiture of transmission assets, it was FERC’s considered judgment that ‘‘the less intrusive func- tional unbundling approach TTT is all that we must require at this time.’’ Id. at 31,655. By 1999, FERC had come to a less sanguine view of the curative powers of functional unbundling. In FERC’s view, inefficiencies in the transmission grid and lingering opportu- nities for transmission owners to discriminate in their own favor remained obstacles to robust competition in the whole- sale electricity market. FERC concluded that these prob- lems could be remedied through the establishment of RTOs, explaining that ‘‘better regional coordination in areas such as maintenance of transmission and generation systems and transmission planning and operation’’ was necessary to ad- dress regional reliability concerns and to foster regional competition. See Regional Transmission Organizations, Or- der No. 2000, FERC Stats. & Regs. ¶ 31,089, 30,999 (1999) (Order No. 2000) (codified at 18 C.F.R. § 35.34) (citing Staff Report to FERC on the Causes of Wholesale Electric Pricing Abnormalities in the Midwest During June 1998, at 5–8 (Sept. 22, 1998)). FERC concluded that RTOs would: ‘‘(1) improve efficiencies in transmission grid management; (2) impose grid reliability; (3) remove remaining opportunities for discrimina- tory transmission practices; (4) improve market performance; and (5) facilitate lighter handed regulation.’’ Order No. 2000 at 30,993; Public Util. Dist. No. 1, 272 F.3d at 611. To further encourage RTO development, FERC directed trans- mission-owning utilities either to participate in an RTO or to explain their refusal to do so. Public Util. Dist. No. 1, 272 5

F.3d at 612. Importantly, though, Order No. 2000 still did not require utilities to join RTOs; participation remained voluntary. See id. at 616. For those utilities opting to join an RTO, Order No. 2000 retained a flexible approach, allowing the RTOs to employ a variety of ownership and operational structures, so long as the RTO established that it had certain required characteris- tics and functional capabilities. Id. at 611. FERC required, inter alia, that an RTO be regional in scope, 18 C.F.R.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Nantahala Power & Light Co. v. Thornburg
476 U.S. 953 (Supreme Court, 1986)
New York v. Federal Energy Regulatory Commission
535 U.S. 1 (Supreme Court, 2002)
LA Pub Svc Cmsn v. FERC
184 F.3d 892 (D.C. Circuit, 1999)

Cite This Page — Counsel Stack

Bluebook (online)
Midwest ISO Transm v. FERC, Counsel Stack Legal Research, https://law.counselstack.com/opinion/midwest-iso-transm-v-ferc-cadc-2004.