Middle West Roads Co. v. Peoples National Bank & Trust Co.

4 N.E.2d 187, 210 Ind. 437, 1936 Ind. LEXIS 261
CourtIndiana Supreme Court
DecidedOctober 19, 1936
DocketNo. 26,720.
StatusPublished
Cited by3 cases

This text of 4 N.E.2d 187 (Middle West Roads Co. v. Peoples National Bank & Trust Co.) is published on Counsel Stack Legal Research, covering Indiana Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Middle West Roads Co. v. Peoples National Bank & Trust Co., 4 N.E.2d 187, 210 Ind. 437, 1936 Ind. LEXIS 261 (Ind. 1936).

Opinion

Tremain, J.

This was an action by the appellee against the appellant to recover damages on account of appellant’s failure to pay to appellee certain sums received by appellant on estimates made in the construction of a highway.

The facts disclose that on the 24th day of December, 1931, the appellant, a corporation engaged in constructing highways, entered into a contract with the State Highway Commission of Indiana to construct a cement road between the cities of Washington and Petersburg, Indiana. The contract which the parties executed was in the form, and contained the conditions and stipulations required by statute, among which the appellant agreed to pay for all labor and material used in the construction. Appellant executed to the state its bond guaranteeing the faithful performance and fulfillment of the contract.

On February 29, 1932, the appellant sublet the grading of the roadway to one Lehmer upon a yardage and lineal foot basis, evidenced by a written contract between appellant and Lehmer. Lehmer executed and delivered a surety company bond to appellant, guaranteeing the faithful performance of the subcontract and providing for the payment of all labor and material accounts. The contract of the appellant with the state, as well as the subcontract of appellant with Lehmer, provided for payments to be made upon estimates made by the engineer and the retention of ten per cent of all estimates until the. work was completed.

At the time the ofiicers of appellant were negotiating with Lehmer to subcontract the grading, Lehmer stated to them that he was unable to finance the work; that it would be impossible for him to undertake it without some understanding upon that subject. Lehmer stated *439 that he had theretofore talked with the cashier of thd appellee bank, and that it was possible to finance the project through appellee. Lehmer and agents of the appellant discussed the matter. The vice president of appellant, a Mr. Johnson, told Mr. Beall, appellant’s superintendent, to go to the appellee bank with Lehmer and see what could be done in the way of securing funds to finance the subcontract. Accordingly Beall and Lehmer presented the matter to the cashier of appellee on April 12,1932.

By the terms of the said subcontract, the appellant was to receive pay from the state for the grading and pay it over to Lehmer as the estimates were made. The state did not know Lehmer in the transaction. It was proposed by these parties to the appellee that it should make loans to Lehmer, and as monthly estimates for the grading were made by the engineer in charge of the construction, the appellant would pay the full amount less ten per cent, to the appellee bank. From said sums the appellee should satisfy all indebtedness of Lehmer and place any remainder to Lehmer’s account in the bank. As evidence of the agreement between appellant and Lehmer to pay to the appellee the sums due to Lehmer on his subcontract, Mr. Beall prepared in triplicate the following instrument, to-wit:

“Washington, Indiana, April 12, 1932.
Middle West Roads Company,
Box 302,
Washington, Indiana.
Gentlemen:
This will be your authority to pay to the Peoples National Bank and Trust Company of Washington, Indiana, from the date hereof all moneys due me under the terms of my sub-contract with you dated February 29, 1932, for work on Federal Aid Pro *440 ject No. 62, Section A, Washington to Petersburg Road.
It is my understanding that payments will be made direct to the Peoples National Bank and Trust Company as monthly estimates are due me under the terms of our agreement.
Yours truly,
H. K. Lehmer.
Accepted: April 12, 1932
Middle West Roads Company
By I. G. Beall
Superintendent.”

The instrument was executed by the parties. A copy was delivered to appellee, and appellant and Lehmer each retained a copy.

Pursuant to the oral agreement among the parties, and the foregoing instrument, the appellee advanced sums to Lehmer in the months of April and May, 1932. At the end of each month appellant paid to appellee, all estimates made for the grading of said highway. Appellee satisfied all advancements and loans made to Lehmer out of such sums and placed the remainder to Lehmer’s credit. In the month of June appellee made two loans to Lehmer: One for the sum of $2,000 on June 14 and another for the sum of $1,000 on June 16. Before the thousand dollar loan was made the superintendent of appellant called upon the appellee bank and told the cashier that the bank could safely loan an additional thousand dollars in the month of June; that Lehmer’s estimate for the month would amount to more than $10,000. An estimate for work done by him was actually made on June 30 for the sum of $10,127, which sum was received by appellant from the state.

On June 29, Lehmer notified appellant that he was unable to perform his contract, although the record shows that he performed it until July 7. Appellant refused to pay to appellee the $10,127 received from the *441 state or any part thereof for the reason, that Lehmer owed other indebtedness incurred in said construction, which appellant, was compelled to pav. Also, by reason of the default, appellant claimed that Lehmer had caused it to suffer losses and damages. All sums advanced by the appellee to Lehmer were used to pay for labor and material in the construction and grading of said highway.

Upon these facts the cause was submitted to the court for trial. By request the court made special findings of fact, and stated its conclusion of law thereon, and rendered judgment against the appellant in favor of the appellee in the sum of $2,999 and costs. Appellant excepted to the findings and conclusion of law and filed a motion for a new trial. From an adverse ruling the appellant has perfected this appeal.

The appellant contends that said written assignment contains all the terms of the contract between the parties and merges all prior conversations and negotiations; that it could not be varied by parol evidence; that “the written instrument was an authorization to appellant to pay directly to appelle all moneys due Lehmer under the terms of his subcontract with appellant as monthly estimates should become due”; that the appellee was entitled to no more money from the appellant than Lehmer himself was entitled at the time of his default; that the assignment of April 12 transferred to appellee the net sum due to Lehmer under his subcontract, and appellee cannot recover unless Lehmer could have recovered if he had not executed the assignment. It is clear from the special findings of fact and the record that by the endorsement “Accepted: April 12, 1932”, appellant intended to and did promise and agree to pay appellee at the end of each month thereafter all moneys due Lehmer on his subcontract, and thereby intended to induce appellee to make loans to Lehmer;

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Turner v. Clary
606 N.E.2d 878 (Indiana Court of Appeals, 1993)
First National Bank v. Pomona Tile Manufacturing Co.
82 Cal. App. 2d 592 (California Court of Appeal, 1917)

Cite This Page — Counsel Stack

Bluebook (online)
4 N.E.2d 187, 210 Ind. 437, 1936 Ind. LEXIS 261, Counsel Stack Legal Research, https://law.counselstack.com/opinion/middle-west-roads-co-v-peoples-national-bank-trust-co-ind-1936.