City National Bank v. Board of Commissioners

172 N.E. 201, 91 Ind. App. 564, 1930 Ind. App. LEXIS 87
CourtIndiana Court of Appeals
DecidedJuly 2, 1930
DocketNo. 13,425.
StatusPublished
Cited by1 cases

This text of 172 N.E. 201 (City National Bank v. Board of Commissioners) is published on Counsel Stack Legal Research, covering Indiana Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
City National Bank v. Board of Commissioners, 172 N.E. 201, 91 Ind. App. 564, 1930 Ind. App. LEXIS 87 (Ind. Ct. App. 1930).

Opinion

Nichols, J.

Action by appellant against appellees to recover a sum of money due from the county to one Huffman for constructing a highway under contract with appellee board of commissioners in favor .of Huffman, but the payment of which was withheld because appellant claimed the money under an assignment of Huffman to it, while certain laborers and materialmen had filed liens with the auditor of the county wherein they claimed priority over the assignment to appellant.

The various labor and material claimants, being appellees herein, respectively filed cross-complaints against appellant and against DeKalb County, in which they claimed priority of liens.

*566 There being special findings in which the facts here involved are fully found, and based on evidence admitted without objection, and conclusions of law, we do not need to consider alleged error of the court in its rulings on demurrers to the pleadings. It appears by these findings, so far as we need to set them out, that appellee Huffman, on October. 6, 1925, entered into a contract with appellee board of commissioners of DeKalb County, by which he agreed to furnish all the work, labor and materials for the construction of the Duncan improved gravel ruad, under the “Three-mile Road Law.” The total contract price was $12,393.20. The funds were raised by sale of bonds.

The Southern Surety Company was the surety on the contractor’s bond; thé contract with the board provided specifically that, if the contractor failed to pay for the work, labor and materials used by him iri said work, then the board of commissioners should have the right to pay such bills out of the fund provided for the building of such road; and the specifications provided that the Board should retain 20 per cent of the contract price until the final completion of the work; the fund now in controversy is this retained percentage.

When this action was begun, estimates had been allowed and paid until but $2,478.64 remained in the hands of the officials, which is the money in dispute. The road was completed and accepted by the board in due course. The contractor failed to pay for all the work, labor and materials used by him, and, on the acceptance of said work by the Board, and at the time of the beginning of this action, a large number of claimants had filed claims against the fund with the auditor of DeKalb County.

On May 7, 1926, appellant took from the contractor an assignment in writing of $4*000 of the funds then and thereafter to become due the contractor, as collateral *567 security for such sums as it should loan the contractor, a copy of which assignment was filed with the auditor of said county; after taking such assignment, appellant loaned money to the contractor, evidenced by prorifissory notes, as follows: On May 7, 1926, $1,000; on May 29,1926, $1,000; on June 28,1926, $2,000; the proceeds of these loans were credited to the account of Huffman, at appellant bank. The court found that these notes were unpaid, but did not find the total amount due appellant bank from the contractor.

Appellant filed its complaint in the DeKalb Circuit Court to recover said sum of $2,478.64, then in the hands of the county-on its assignment. All persons who had filed claims were made parties defendant, as was also the board of commissioners. Appellee, the Southern Surety Company, on its application, was, without objection, admitted as a party defendant.. The claimants to the fund filed cross-complaints against appellant and all codefendants, including the surety company on the contractor’s bond, and to have their several claims paid out of such retained fund.

The surety company filed its answer and cross-complaint asking that the court determine the rights of all the parties in and to the fund, and that all valid claims against the fund be ordered paid therefrom to protect itself as surety on the contractor’s bond. The board filed an answer of general denial to the complaint.

Appellant claimed the entire remaining fund, and asked that all claims of claimants be declared void, but it did not ask any judgment on the contractor’s bond, nor against Huffman personally, and asked that the remaining fund be awarded to it on its assignment.

Among other things, the findings show that the following estimates and warrants were issued by order of the board: June 10, 1926, $1,584; July 7, 1926, $2,640; August 3, 1926, $240; September 8, 1926, $4,080; *568 October. 5, 1926, $1,370.56. The total of said sums so paid was $9,914.56. All these warrants were delivered to appellant bank, and were by it credited to the account of Huffman, contractor, on his checking account in appellant bank. Each warrant showed on its face that it was issued on the Duncan Road fund, and those for the sums of $240, $4,080 and $1,370.56 were drawn to the contractor and appellant jointly.

No part of these sums of money, all of which were received by appellant bank, was applied to the payment of its debt against the contractor, Huffman, but all of these sums were by appellant passed to the credit of Huffman on his checking account and by him checked out.

There is nothing whatever in the special findings to show that any of the moneys loaned by appellant to the contractor, being the proceeds of the above-mentioned notes, nor any part of the proceeds of such estimates, was ever used by the contractor in payment for any. work, labor, or materials, nor in payment of any debt contracted by the contractor in the construction of the Duncan Road.

So far as appellant bank is concerned, as shown by the special findings of fact, it was a mere volunteer so far as the funds in question are concerned, and was nothing more than a general creditor of the contractor. The application of Huffman to the surety company for the bond executed by it as surety contains an assignment of these funds to the Southern Surety Company, antedating the assignment to appellant bank.

The court, on its finding, stated certain conclusions in favor of the claimants to the fund, who had furnished labor, work and materials for the construction of the road, and rendered judgment on such conclusions that their claims be paid out of the fund; it further stated conclusions that certain claimants were not entitled to any part of the fund, but rendered judgment for these *569 claimants against Huffman, the contractor; it also stated conclusions of law that what remained of such fund after payment of claims as aforesaid, to wit, $345.10, should be paid to appellant on its assignment, and rendered judgment accordingly.- No judgment except for costs was awarded to appellee surety company, nor against it on its bond. No appeal except that of appellant was taken from the judgment.

The question presented for our decision by exceptions to the conclusions of law is whether or not appellant is entitled to all of the fund in question, amounting to $2,478.64, or to a greater part thereof than was awarded to it, as against appellee surety company and the several claimants thereto for work, labor and materials furnished by them respectively in the construction of the road.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Middle West Roads Co. v. Peoples National Bank & Trust Co.
4 N.E.2d 187 (Indiana Supreme Court, 1936)

Cite This Page — Counsel Stack

Bluebook (online)
172 N.E. 201, 91 Ind. App. 564, 1930 Ind. App. LEXIS 87, Counsel Stack Legal Research, https://law.counselstack.com/opinion/city-national-bank-v-board-of-commissioners-indctapp-1930.