Mid County Rental Service, Inc. v. Miner-Dederick Construction Corp.

583 S.W.2d 428, 1979 Tex. App. LEXIS 3449
CourtCourt of Appeals of Texas
DecidedFebruary 8, 1979
Docket8174
StatusPublished
Cited by10 cases

This text of 583 S.W.2d 428 (Mid County Rental Service, Inc. v. Miner-Dederick Construction Corp.) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Mid County Rental Service, Inc. v. Miner-Dederick Construction Corp., 583 S.W.2d 428, 1979 Tex. App. LEXIS 3449 (Tex. Ct. App. 1979).

Opinion

CLAYTON, Justice.

Appellee, Miner-Dederick Construction Corporation (defendant and cross-plaintiff below) was the general or prime contractor to construct a library building and certain related works for the Lamar University in Beaumont, Texas. Appellee entered into three separate subcontracts with appellants, Mid-County Rental Service, Inc. and Alton M. Stewart (plaintiffs and cross-defendants below) relating to certain portions of the work. Appellants filed suit against appel-lee to recover for “extras,” attorney fees and the balance due under the three subcontracts. Appellee answered and filed a cross-action and also sued United States Fidelity & Guaranty Company (USF&G) upon the performance bond and payment bond executed by it as surety. The cross-action filed by appellee against appellants was based upon a breach of the three subcontracts and sought damages for the amount appellee was required to expend to complete the work called for by the subcontracts.

A jury trial resulted in findings to special issues that appellants did not substantially perform subcontracts one and three; that appellants performed “extras” the value of which was $2,090.64; that $700 was reasonable attorney fees; that appellants breached the subcontracts in question; that appellants willfully, intentionally, “or” in bad faith failed to substantially perform the contracts in question; that appellee “was damaged” because of such breach of contract; that the amount of damages for such breach was “none” as to each contract; and that the appellee was obligated to pay to persons who furnished labor or materials for use by appellants on the contracts the amount of $10,000.

The appellants’ “Motion for Judgment” and to disregard answers to certain special issues was overruled by the trial court, and judgment was entered for appellee and against appellants and USF&G, jointly and severally, for $7,203.36. The amount of the judgment was apparently determined by deducting the amount of extras and attorney fees found by the jury in favor of *430 appellants from the amount found in favor of appellee. From this judgment appellants and USF&G have appealed.

Appellants and USF&G urge “no evidence” points as to the trial court’s action in overruling its motion to disregard the jury’s answer to Special Issue No. 10 and in rendering judgment for appellee based thereon.

In deciding a “no evidence” question, we must consider only the evidence and the inferences tending to support the findings and disregard all evidence and inferences to the contrary. Lucas v. Hartford Accident & Indemnity Co., 552 S.W.2d 796, 797 (Tex.1977); Garza v. Alviar, 395 S.W.2d 821, 823 (Tex.1965).

Special Issue No. 10 inquired of the jury the reasonable sum of money appellee “paid or became obligated to pay” to persons and firms who furnished labor and materials for use by appellants on the contracts in question, and in response thereto the jury answered $10,000. We construe the words “became obligated to pay” to be equivalent to “legally obligated to pay.” To make a determination of the money which appellee became legally obligated to pay we must review the transactions conducted between all the parties.

Appellee was the general contractor for the construction of a library building for Lamar University, which was a “public works” contract within the meaning of Tex. Rev.Civ.Stat.Ann. art. 5160 (Vernon 1971 and Supp.1978). Appellee entered into three separate subcontracts with appellants to perform certain work. Under each subcontract appellants furnished a performance bond and a payment bond, with USF&G as sureties thereon. Each performance bond and payment bond, in addition to the general terms, expressly provides:

“PROVIDED, HOWEVER, that this bond is executed pursuant to the provisions of Article 5160 of the Revised Civil Statutes of Texas . . . and all liabilities on this bond shall be determined in accordance with the provisions of said article to the same extent as if it were copied at length herein.”

Unquestionably, the provisions of Article 5160 were incorporated into and made a part of the bonds, and the bonds expressly, state that all liabilities on each bond “shall be determined in accordance with the provisions of art. 5160.”

The question before us is whether or not the $10,000 as found by the jury constituted a legal obligation or liability on the part of appellee. It is undisputed that appellants owed the aggregate sum of $10,000 to three suppliers for materials furnished and labor performed in connection with the work to be done by appellants pursuant to their contract with appellee. It is further undisputed that the claims of the suppliers were not paid by appellants. Appellee urges that it was legally obligated to pay the suppliers for the amount due them by appellants, and therefore appellee was entitled to recover from appellants such sums. It is undisputed that the suppliers did not timely give appellee notice of their claims pursuant to the provision of art. 5160. Appellee argues the notice requirements of art. 5160 are not necessary, but, if such notices are required, then there was a substantial compliance with the notice requirements of art. 5160.

The provisions of art. 5160 are applicable to the establishment of liability on the part of the general contractor as well as to liability on the part of the surety on its payment bond and performance bond. The statute provides the procedure and remedy for presenting a claim. It has been held that the statute is mandatory as well as exclusive; that it must be complied with in all respects or a cause of action under it is not maintainable. Therefore, a claimant must follow the procedures provided therein. Employers’ Liability Assurance Corp. v. Young County Lumber Co., 122 Tex. 647, 64 S.W.2d 339 (1933); Fidelity & Deposit Co. v. Big Three Welding Equipment Co., 151 Tex. 278, 249 S.W.2d 183 (1952); Bunch Electric Co. v. Tex-Craft Builders, Inc., 480 S.W.2d 42 (Tex.Civ.App.—Tyler 1972, no writ). As stated by the court in Bunch Electric Co. v. Tex-Craft Builders, Inc., supra: “The requirement of notice ... is not a *431 mere statute of limitation, but is a substantive condition precedent to the existence of the cause of action,” citing General Casualty Co. of America v. United States, 205 F.2d 753, 755 (5th Cir. 1953). It is undisputed that the suppliers in the case at bar did not have a direct contractual relationship with a prime contractor. It is clearly held in Keetch Metal Works of Dallas, Inc. v. Yates,

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Anderson, Greenwood & Co. v. Martin
44 S.W.3d 200 (Court of Appeals of Texas, 2001)
Edwards v. Holleman
842 S.W.2d 704 (Court of Appeals of Texas, 1992)
City of Houston v. Blackbird
658 S.W.2d 269 (Court of Appeals of Texas, 1983)
Houston Lighting & Power Co. v. Dickinson Independent School District
641 S.W.2d 302 (Court of Appeals of Texas, 1982)
Paulus v. Lawyers Surety Corp.
625 S.W.2d 843 (Court of Appeals of Texas, 1981)

Cite This Page — Counsel Stack

Bluebook (online)
583 S.W.2d 428, 1979 Tex. App. LEXIS 3449, Counsel Stack Legal Research, https://law.counselstack.com/opinion/mid-county-rental-service-inc-v-miner-dederick-construction-corp-texapp-1979.