Michigan Steel Erectors, Inc. v. Crane (In Re Crane)

154 B.R. 60, 1993 Bankr. LEXIS 2271
CourtUnited States Bankruptcy Court, E.D. Michigan
DecidedMarch 16, 1993
Docket19-42336
StatusPublished
Cited by5 cases

This text of 154 B.R. 60 (Michigan Steel Erectors, Inc. v. Crane (In Re Crane)) is published on Counsel Stack Legal Research, covering United States Bankruptcy Court, E.D. Michigan primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Michigan Steel Erectors, Inc. v. Crane (In Re Crane), 154 B.R. 60, 1993 Bankr. LEXIS 2271 (Mich. 1993).

Opinion

OPINION DETERMINING NON-DISCHARGEABILITY UNDER § 523(a)(4) ONLY

WALTER SHAPERO, Bankruptcy Judge.

Facts and Background

This is a non-dischargeability action under 11 U.S.C. §§ 523(a)(2)(A), (a)(4) and (a)(6) brought by Michigan Steel Erectors, Inc. (“plaintiff”) against debtor Darrell Dean Crane (“debtor”) who was the principal owner and operating officer of Crane Welding and Fabricators, Inc. (“Crane Welding”). In connection with this case the Court makes the following findings of fact:

(1) During all periods relevant to this case the plaintiff was in the business of installing and erecting structural steel. Crane Welding’s business included fabricating and/or providing structural steel and making it ready for installation and erection by either itself or third parties such as the plaintiff.

(2) In 1990, Crane Welding became a sub-contractor to certain general or other contractors for structural steel erection on three (3) different jobs. In each of the three (3) jobs Crane Welding orally contracted with plaintiff as a sub-contractor to install that structural steel. Plaintiff’s work constituted only part of what Crane Welding’s obligations were under its other contracts on these jobs.

(3) Plaintiff and Crane Welding had some previous business dealings which appeared to have been mutually satisfactory and without untoward incident.

(4) The first of the three (3) relevant jobs was the so-called “Lantz Steel” job. On or about April 26, 1990, plaintiff and Crane Welding contracted for the former to furnish required labor and equipment to install the steel for a total of $4,200.00. Plaintiff commenced the work on April 28, 1990 and completed it on April 30, 1990. On April 30, 1990, plaintiff invoiced Crane Welding for the agreed upon $4,200.00. On or about that same date, Crane Welding invoiced J.C. Holly, the general contractor with whom it had its contract for sums *63 including amounts due under the contract with plaintiff. On or about May 18, 1990, J.C. Holly paid Crane Welding most of the sums due it under its contract. The remaining sums due Crane Welding were paid later in 1990. In addition to the $4,200.00, plaintiff also invoiced Crane Welding for certain extras by way of a number of invoices issued during the middle and latter part of May, 1990.

(5) The second of the three (3) relevant jobs was the so-called “Best Brand” job. Plaintiff and Crane Welding entered into an agreement on or about May 13, 1990, which required plaintiff to erect structural steel for the sum of $3,600.00. Plaintiff commenced work on May 15,1990 and completed it approximately May 17, 1990, on which date it invoiced Crane Welding for the agreed upon $3,600.00. Crane Welding invoiced the general contractor with whom it had its contract (Campbell Mannix, Inc.) on or about May 31, 1990. On or about July 5, 1990, Campbell Mannix, Inc. paid Crane Welding $32,840.00, the same being substantially all of the sums due Crane Welding in connection with the job. Balances due Crane Welding, if any, were paid later in 1990.

(6) The third of the three (3) relevant jobs was the so-called “Voss Steel” job. Plaintiff and Crane Welding entered into their contract for that job on or about June 12, 1990 for sum of $7,137.00. Plaintiff commenced the work on or about June 15, 1990 and completed it June 20, 1990. There is some discrepancy in the testimony as to the start and completion dates. That however, is irrelevant to the outcome of this case. Plaintiff completed its performance and rendered its invoice in connection with the job on June 29, 1990. Apparently, Crane Welding rendered its invoice in advance of completion for $24,500.00 to the general contractor with whom it had its contract (J.C. Holly) on or about June 4, 1990. On June 28, 1990 or soon thereafter, Crane Welding received $21,465.00 from the general contractor and received an additional amount of $4,395.00 in late August of 1990.

(7) At the time(s) each of the oral agreements between the plaintiff and debtor with regard to each of the three (3) jobs were made, there was a similar discussion about when plaintiff would be paid. The discussion and understanding, and the statement made by debtor on behalf of Crane Welding with respect thereto, was to the effect that plaintiff would be paid when Crane Welding received its money with respect to the job from its general contractor. This became part of, and was, the agreement of the parties.

(8) The only payments made by debtor to plaintiff with respect to any of these three (3) jobs were (a) $2,000.00 on or about May 25, 1990 (the payment being in fact made by a sister of the debtor) and (b) $1,000.00 on or about September 12, 1990. Both of those payments were apparently meant to apply on amounts due on the Lantz Steel job.

(9) Starting thirty (30) days or so after completion of its performance under each of the three (3) contracts, plaintiff regularly made inquiry of debtor as to when plaintiff would be paid. It was plaintiffs testimony (and the Court finds it credible) that debtor’s response was that he had not yet been paid by the general contractor. Debt- or’s responses were essentially false. Plaintiff testified that because of those statements by the debtor, plaintiff refrained from taking steps to enforce any construction lien rights it might have had under Michigan law.

(10) Because it had not been paid by October of 1990, plaintiff began a series of inquiries to the general contractors involved to determine whether or not what plaintiff had been told about non-payment of Crane Welding, was in fact true. As a result, plaintiff was apprised of the aforementioned actual dates and amounts of payments by the general contractors to Crane Welding. The Court further concludes from the evidence those monies were deposited in the bank account(s) and were thus commingled with other funds of Crane Welding and that Crane Welding used that money to pay various other subcontractors, and, in addition overhead ex *64 penses of Crane Welding including, compensation to the debtor, payments to other employees of the debtor (including secretarial) payments on a land contract covering the business premises occupied by Crane Welding and for heat, light and power and other expenses of Crane Welding relating to its normal business operations.

(11) Plaintiff introduced no evidence attempting to trace disbursements of any of the funds received by Crane Welding from its general contractors through the commingled funds bank account or accounts of Crane Welding.

(12) As stipulated to by the parties, plaintiff is owed the sum of $18,974.50 plus finance charges of 1.5% per month from thirty (30) days after the date of billing.

Discussion

As to the claim of non-disehargeability asserted under § 523(a)(2) the required elements are well known. See In re Ward, 857 F.2d 1082 (6th Cir.1988); In re Phillips, 804 F.2d 930 (6th Cir.1986). Initially there is a requirement that credit had been obtained through a material misrepresentation. What debtor said and the parties agreed to in this case,

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Conseco v. Howard (In Re Howard)
261 B.R. 513 (M.D. Florida, 2001)
In Re Baietti
189 B.R. 549 (D. Maine, 1995)
Houston v. Capps (In Re Capps)
193 B.R. 955 (N.D. Alabama, 1995)

Cite This Page — Counsel Stack

Bluebook (online)
154 B.R. 60, 1993 Bankr. LEXIS 2271, Counsel Stack Legal Research, https://law.counselstack.com/opinion/michigan-steel-erectors-inc-v-crane-in-re-crane-mieb-1993.