MFA, INC. v. HLW Builders, Inc.

303 S.W.3d 620, 2010 Mo. App. LEXIS 178, 2010 WL 605368
CourtMissouri Court of Appeals
DecidedFebruary 23, 2010
DocketWD 70475
StatusPublished
Cited by6 cases

This text of 303 S.W.3d 620 (MFA, INC. v. HLW Builders, Inc.) is published on Counsel Stack Legal Research, covering Missouri Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
MFA, INC. v. HLW Builders, Inc., 303 S.W.3d 620, 2010 Mo. App. LEXIS 178, 2010 WL 605368 (Mo. Ct. App. 2010).

Opinion

JOSEPH M. ELLIS, Judge.

MFA, Inc. appeals from a summary judgment entered in the Circuit Court of Callaway County in favor of HLW Builders, Inc. in an action filed by MFA to compel arbitration or, in the alternative, for breach of contract. For the following reasons, the judgment is affirmed.

On December 9, 1998, MFA entered into a contact with HLW for the construction of an agriculture chemical/fertilizer facility in Callaway County. HLW was chosen as the contractor by MFA’s project coordinator, John Seiler. In order to solicit bids for the project, Seiler had created and provided contractors with drawings of the proposed facility along with certain specifications. Those drawings and specifications were incorporated by reference in the construction contract. HLW completed the construction in March 2000.

On October 25, 2002, Bradley Hamilton went to the facility to repair an elevated conveyor system on behalf of a repair contractor hired by MFA. The repairs required Hamilton to utilize the catwalk located next to the conveyor. While working on the conveyor, Hamilton had a seizure, fell to the ground, and died as a result of the injuries he sustained. OSHA investigated the incident and cited MFA with exposing employees to a twenty-four foot fall hazard because the catwalk did not have a guardrail or other fall protection system on the side closest to the conveyor belt.

On May 10, 2004, Hamilton’s widow filed a wrongful death action against MFA in *623 the Circuit Court of Jackson County. On November 10, 2004, MFA filed a third-party petition against HLW. In its answer to MFA’s third-party petition, HLW asserted that the dispute should be resolved through arbitration as provided by the arbitration clause contained in the construction contract. On January 7, 2005, HLW wrote MFA and requested that the claims be submitted to binding arbitration as provided in the construction contract.

On August 24, 2005, Hamilton’s widow filed her First Amended Petition, adding HLW as a defendant. On May 10, 2006, the circuit court granted HLW’s motion for summary judgment on the claims brought by Hamilton’s widow based upon the acceptance doctrine. On June 6, 2006, MFA dismissed its third-party petition and demanded for the first time that the dispute between the two companies be arbitrated. HLW refused to arbitrate at that point, contending that the findings and conclusions of the summary judgment resolved the dispute between the two companies. On January 23, 2007, following mediation, MFA entered into a settlement agreement with Hamilton’s widow for $1.2 million.

On February 28, 2007, MFA filed the current action in the Circuit Court of Cal-laway County asserting that HLW had breached the construction contract by refusing to arbitrate its claim that HLW should indemnify it for the $1.2 million paid to Hamilton’s widow. In the alternative, MFA brought a breach of contract claim against HLW for failing to construct the facility in compliance with OSHA standards and claimed that breach resulted in Hamilton’s death and the subsequent settlement of the wrongful death action.

HLW filed a motion for summary judgment on July 26, 2007. On September 4, 2007, MFA filed a motion for partial summary judgment and motion to compel arbitration.

Following a hearing, the trial court denied the motion to compel arbitration, finding that the arbitration clause in the contract was not mandatory. In addition, the court found that MFA had waived any right it had to arbitrate. The trial court also granted HLW’s motion for summary judgment and denied MFA’s motion for partial summary judgment. MFA brings three points on appeal.

In its first point, MFA claims the trial court erred in denying its motion to compel arbitration because the arbitration clause was mandatory rather than permissive. MFA also argues that the trial court erred in finding that it waived its right to arbitration.

“In determining whether parties are bound by an agreement to arbitrate, the court must determine whether a valid arbitration agreement exists and, if so, whether the specific dispute falls within the scope of the arbitration agreement.” Kritzer v. Curators of Univ. of Mo., 289 S.W.3d 727, 730 (Mo.App. W.D.2009) (internal quotation omitted). “In making these determinations, the court should apply the usual rules of state contract law and canons of contract interpretation.” Id. (internal quotation omitted). “[A]n appellate court’s review of the arbitrability of a dispute is de novo.” Woods v. QC Fin. Servs., Inc., 280 S.W.3d 90, 94 (Mo.App. E.D.2008).

Article 15 of the General Conditions of the contract, adopted by reference in the Construction Agreement, provides:

To prevent suits and litigations, it is agreed by the parties hereto that should any disputes arise under this Contract that cannot be otherwise peacefully agreed upon, the same may be submitted to arbitration upon the written request of either party hereto. If arbitration is chosen, the Owner and the Contractor shall each choose one *624 arbitrator, and they in turn shall choose a third member. Their decision shall be final, and either the Owner or Contractor shall comply.

The trial court concluded that the “may be submitted to arbitration” language rendered Article 15 permissive rather than mandatory.

Contrary to the trial court’s conclusion, “[t]he overwhelming authority from state and federal courts throughout the nation supports the conclusion that the use of operative language such as “may elect” does give rise to mandatory arbitration.” Discover RE Managers, Inc. v. Preferred Employers Group, Inc., No. 3:05CV809, 2006 U.S. Dist. LEXIS 97836, at *22-23 (D.Conn. March 8, 2006). 1 “[PJarties can always voluntarily submit a claim to arbitration; therefore, making an agreement to arbitrate only if the parties later agree to do so is a meaningless promise.” Maloney-Refaie v. Bridge at Sch., Inc., 958 A.2d 871, 884 (Del.Ch.2008). The use of the word “may” grants one side a right to pursue arbitration if it wished and mandatory arbitration is required when one side so requests. Id.

Under the arbitration language contained in the construction contract at issue here, while not all disputes must be resolved through arbitration, once any of the parties to the contract invokes the right to arbitration by written request, arbitration is mandatory unless subsequently waived by that party. Thus, we must ascertain whether, as MFA claims, the trial court improperly found that MFA had waived its right to arbitration.

“A party may waive a valid arbitration agreement.” Major Cadillac, Inc. v. General Motors Corp., 280 S.W.3d 717, 721 (Mo.App. W.D.2009).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

GFS, II, LLC v. Janelle Carson
Missouri Court of Appeals, 2023
L. Dotson v. Dillard's, Inc.
472 S.W.3d 599 (Missouri Court of Appeals, 2015)
Lovelace Farms, Inc. v. Marvin Marshall
442 S.W.3d 202 (Missouri Court of Appeals, 2014)
Frye v. Speedway Chevrolet Cadillac
321 S.W.3d 429 (Missouri Court of Appeals, 2010)

Cite This Page — Counsel Stack

Bluebook (online)
303 S.W.3d 620, 2010 Mo. App. LEXIS 178, 2010 WL 605368, Counsel Stack Legal Research, https://law.counselstack.com/opinion/mfa-inc-v-hlw-builders-inc-moctapp-2010.