Metromont Corporation v. Allan Myers, L.P.

CourtDistrict Court, D. Maryland
DecidedJuly 19, 2019
Docket1:18-cv-03928
StatusUnknown

This text of Metromont Corporation v. Allan Myers, L.P. (Metromont Corporation v. Allan Myers, L.P.) is published on Counsel Stack Legal Research, covering District Court, D. Maryland primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Metromont Corporation v. Allan Myers, L.P., (D. Md. 2019).

Opinion

IN THE UNITED STATES DISTRICT COURT FOR THE DISTRICT OF MARYLAND

: METROMONT CORPORATION :

v. : Civil Action No. DKC 18-3928

: ALLAN MYERS, L.P. :

MEMORANDUM OPINION Defendant/Counter-Plaintiff Allan Myers, L.P. (“Myers”) filed a motion to stay, or in the alternative, motion to dismiss in this breach of contract case on February 15, 2019. (ECF No. 13). Myers filed a motion for more definite statement of the first affirmative defense in Plaintiff/Counter-Defendant Metromont Corporation’s (“Metromont”) answer on March 21, 2019. (ECF No. 22). The issues are briefed and the court now rules, no hearing being deemed necessary. Local Rule 105.6. For the following reasons, Myers’ motions will be denied. I. Background Metromont’s claim stems from a contract (“prime contract”) the City of Baltimore’s Department of Public Works (“the City”) awarded to Myers in 2009.1 (ECF No. 1 ¶¶ 2, 10). According to

1 Travelers Casualty & Surety Company of America (“Travelers”) is a third-party defendant in this action. (See ECF No. 16). However, facts pertaining to Travelers are omitted here because Travelers is not a pertinent party to either pending motion. the contract, Myers agreed to “build an enclosed concrete reservoir for Montebello Plant 2, a water filtration plant” (“the project”). (Id.). Myers formed a subcontract with Metromont on July 28, 2010 wherein Metromont agreed to supply “precast concrete double tee beams, inverted girders, and connections[,]” to construct the

reservoir roof. (ECF Nos. 1 ¶ 11 & 1-1, at 2). The standard purchase order for the materials indicated that they were to “strictly comply with the requirements of the [prime] [c]ontract[’s] . . . plans and specifications[][,]” (ECF No. 1-1, at 2), as put forward by the Project’s “registered design professional” (ECF No. 1 ¶ 15). Metromont supplied the requested materials and Myers used the materials to construct the reservoir roof.2 (See ECF No. 1 ¶¶ 13, 17-18). The parties agree that “[t]he reservoir’s large roof system experienced problems with cracking concrete at various connection points in July 2011[.]”3 (ECF Nos. 1 ¶ 17 & 9 ¶ 14). To resolve

2 The parties dispute whether Plaintiff designed the materials according to the prime contract’s plans and specifications. Metromont asserts that it designed the materials pursuant to the Prime Contract’s specifications (ECF No. 1 ¶ 14) and Myers contends that Plaintiff failed to do so (ECF No. 9 ¶¶ 15, 17). This question is one of the bases for the administrative proceedings and appeal. See infra, at 3-4.

3 Metromont contends that the concrete cracked because “the enormous rigid structure could not accommodate movement caused by 2 the issue, Myers and the City agreed to replace the “rigid welded connections” with “slip-joints[.]”4 (ECF Nos. 1 ¶ 18 & 9 ¶ 17). “On or about August 20, 2012, Myers submitted a change order request to the city, seeking an equitable adjustment of $1,993,382.56 for the additional work involved in implementing the

slip joint connection fix, which Myers later revised on or about March 13, 2015 to a total sum of $4,699,735.91.” (ECF No. 9 ¶ 19). The City questioned Myers’s change order request, “triggering the dispute resolution terms of the [p]rime [c]ontract.” (ECF No. 9 ¶ 20). From September 10, 2012 through November 19, 2018, Myers was involved in six years of administrative proceedings regarding its claim for a contractual equitable adjustment. (ECF No. 9 ¶¶ 20-23, 25-27). The City’s Deputy Director of Public Works issued a final administrative decision denying Myers’s change order on

thermal and seismic pressures.” (ECF No. 1 ¶ 17). Myers maintains that “Metromont failed to calculate thermal loads in its design of [the materials], in derogation of the” plans and specifications stated in the prime contract. (ECF No. 9 ¶ 15).

4 Metromont maintains that: (1) this constituted a “material and fundamental change in the original plans and specifications from the City[;]” (2) it did not design the new slip-joint connections; and (3) “these modifications . . . were not part of the original plans and specifications issued by the City [.]” (ECF No. 1 ¶¶ 18-19). Alternatively, Myers asserts that these new connections were designed to “correct Metromont’s design errors” by “account[ing] for the thermal loads that Metromont originally failed to take into consideration.” (ECF No. 9 ¶ 17). 3 November 19, 2018, concluding that Myers failed to meet its burden for adequately calculating the thermal loads in its design of the roof structure members.5 (ECF No. 9-5, at 13-17). Myers filed a still-pending appeal of the administrative decision in the Circuit Court for Baltimore City (“State Claim”) on November 27, 2018.6

(ECF No. 9 ¶ 28). Metromont did not join the appeal either voluntarily (ECF No. 9 ¶ 29) or via compulsory joinder (ECF No. 26-1, at 2). Metromont commenced this action on December 19, 2018, alleging one count of breach of contract based on Myers’s refusal to pay Metromont. (ECF No. 1). Metromont seeks damages in the amount of $1,015,000.00 plus pre- and post-judgment interest. (Id.). Myers filed an answer and counterclaim against Metromont on February 1, 2019, alleging four counts: (1) breach of contract;

5 Based on this decision, Myers asserts that “Metromont failed to comply with the requirements of the subcontract” (ECF No. 9 ¶ 27) and Metromont contends that “the administrative decision addresses only the contractual dispute between Myers and the City” (ECF No. 17, at 6).

6 The Maryland Judiciary Case Search website indicates that the Department of Public Works administrative decision was affirmed on June 5, 2019. However, the docket also reflects that Myers filed a motion for reconsideration of the appeal decision on July 8, 2019. See In the Matter of the Petition of Allan Myers, L.P., Case Number 24C18006397 (Circuit Court for Baltimore City), http://casesearch.courts.state.md.us/casesearch/inquiryByCaseNum .jis.

4 (2) breach of warranty; (3) negligent design; and (4) indemnification. (ECF No. 9). Myers’s counterclaim seeks damages in the amount of $4,699,735.91, attorneys’ fees, pre- and post- judgment interest, and “such additional direct, indirect, consequential, general and special damages as may be proven at

trial[.]” (Id., at 23). Myers also filed a motion to stay, or in the alternative, motion to dismiss on February 15, 2019. (ECF No. 13). Metromont filed a response in opposition to Myers’s motion to stay (ECF No. 17) and an answer to Myers’s counterclaim on March 1, 2019 (ECF No. 16). Myers filed a motion for a more definite statement on March 21, 2019 (ECF No. 22) and Metromont opposed the motion on April 4, 2019 (ECF No. 25). II. Motion to Stay or Dismiss A. Colorado River Myers argues that this action should be stayed or dismissed pursuant to the doctrine established by the Supreme Court of the United States in Colorado River Water Conservation District v.

United States, 424 U.S. 800 (1976),because “a determination as to liability in the [pending state court] [a]ppeal will prove

5 dispositive of Metromont’s claims in this case.”7 (ECF No. 13, at 2). In response, Metromont argues that the Colorado River abstention doctrine is not applicable here and abstention is not appropriate because “[f]ederal courts with jurisdiction over a

case can abstain from hearing it in deference to state-court proceedings only in truly ‘extraordinary circumstances’—not as a matter of convenience or efficiency.” (ECF No. 17, at 2). Generally, “our dual system of federal and state governments allows parallel actions to proceed to judgment until one becomes preclusive of the other.” Chase Brexton Health Servs., Inc. v. Maryland, 411 F.3d 457, 462 (4th Cir. 2005). Thus, the mere fact

Free access — add to your briefcase to read the full text and ask questions with AI

Related

McClellan v. Carland
217 U.S. 268 (Supreme Court, 1910)
Landis v. North American Co.
299 U.S. 248 (Supreme Court, 1936)
Quackenbush v. Allstate Insurance
517 U.S. 706 (Supreme Court, 1996)
Crawford-El v. Britton
523 U.S. 574 (Supreme Court, 1998)
Great American Insurance Company v. Gross
468 F.3d 199 (Fourth Circuit, 2006)
Charles v. nRosenberg v. Mark Lawrence
849 F.3d 163 (Fourth Circuit, 2017)
Ackerman v. Exxonmobil Corp.
734 F.3d 237 (Fourth Circuit, 2013)
Horlick v. Capital Women's Care, LLC
896 F. Supp. 2d 378 (D. Maryland, 2011)
Haley Paint Co. v. E.I. Du Pont De Nemours & Co.
279 F.R.D. 331 (D. Maryland, 2012)
Kohler v. Staples the Office Superstore, LLC
291 F.R.D. 464 (S.D. California, 2013)
Armstrong v. Snyder
103 F.R.D. 96 (E.D. Wisconsin, 1984)

Cite This Page — Counsel Stack

Bluebook (online)
Metromont Corporation v. Allan Myers, L.P., Counsel Stack Legal Research, https://law.counselstack.com/opinion/metromont-corporation-v-allan-myers-lp-mdd-2019.