Merrillville Conservancy District v. Atlas Excavating, Inc.

764 N.E.2d 718, 2002 Ind. App. LEXIS 332, 2002 WL 363656
CourtIndiana Court of Appeals
DecidedMarch 8, 2002
Docket45A05-0010-CV-417
StatusPublished
Cited by15 cases

This text of 764 N.E.2d 718 (Merrillville Conservancy District v. Atlas Excavating, Inc.) is published on Counsel Stack Legal Research, covering Indiana Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Merrillville Conservancy District v. Atlas Excavating, Inc., 764 N.E.2d 718, 2002 Ind. App. LEXIS 332, 2002 WL 363656 (Ind. Ct. App. 2002).

Opinion

OPINION

RATLIFEF, Senior Judge.

STATEMENT OF THE CASE

Plaintiff-Appellant Merrillville Conser-vancey District, by the District's Board of Directors ("MCD") appeals the trial court's determination in its action against Defendants-Appellees Atlas Excavating, Inc. ("Atlas"), Employer's Insurance of Wausau, Wausau Insurance Companies, and Wausau Nationwide Insurance Group. 1 Atlas cross-appeals.

We affirm in part and reverse in part.

ISSUES

MCD raises three issues for our review, which we restate as:

I. Whether the trial court erred in awarding prejudgment interest to Atlas.
II. Whether the trial court erred in ' determining that a contract clause provided for actual damages.
Whether the trial court erred in not adopting the findings made in an earlier determination. IIL.

Atlas raises two issues on cross-appeal, which we restate as:

*721 IV. Whether the trial court erred in determining that Atlas breached the contract by performing defective work.
V. Whether the trial court erred in determining that Atlas was not entitled to additional compensation.

FACTS AND PROCEDURAL HISTORY

Atlas entered into a construction contract with MCD for improvements to MCD’s sewage and wastewater disposal works (the “Project”). 2 MCD subsequently determined that Atlas had breached the contract, and it filed a complaint for declaratory judgment in which it sought the following declarations: (1) that a damages clause in the contract was a liquidated damages clause and not an actual damages clause; (2) that MCD was entitled to a specified amount in liquidated damages; (3) that MCD was entitled to terminate the contract because Atlas had breached it; and (4) that MCD was entitled to withhold the final contract payment. Atlas filed a counterclaim in which it sought to recover the balance of the contract sum and additional compensation for extra work. MCD then filed a second complaint in which it sought to recover liquidated and actual damages for Atlas’s alleged breach of contract.

MCD’s complaints were consolidated with a complaint filed against Atlas by a subcontractor. The trial court subsequently entered partial summary judgment in Atlas’s favor on the issue of whether the damages provision of the contract was an actual damages and not a liquidated damages provision. A bench trial was held on the remaining issues, and

the court eventually entered judgment awarding Atlas the contract balance and prejudgment interest along with additional compensation of $3,883.66 (damages and interest) for replacement of field tiles, loss due to a stop work order, installation and repair of a lateral sewer, and grading of a private drive. The court rejected Atlas’s counterclaim for additional compensation for labor associated with pipe bedding changes. The court found that Atlas had installed defective manhole covers, but MCD had not proven any damages. As noted above, both parties raise issues pertaining to the judgment.

DISCUSSION AND DECISION

I. PROPRIETY OF PREJUDGMENT INTEREST AWARD MCD withheld final payment to Atlas in the amount of $106,682.00. The trial court determined that MCD was not entitled to withhold payment, and it ordered MCD to remit the final payment along with $47,645.47 in prejudgment interest. MCD alleges that it was authorized by both statute (Ind.Code § 36-1-12-1 et seq.) and the contract to withhold payment. MCD further alleges that the award of prejudgment interest was improper.

The trial court, on its own motion, made findings of fact and conclusions of law on limited issues. It did not make such findings and conclusions on this issue. Accordingly, we review this issue under a general judgment standard. Keybank National Association v. NBD Bank, 699 N.E.2d 322, 325 (Ind.Ct.App.1998). A general judgment will be affirmed if it can *722 be sustained upon any legal theory consistent with the evidence introduced at trial. Bedford Recycling, Inc. v. U.S. Granules Corp., 634 N.E.2d 1361, 1363 (Ind.Ct.App.1994), trams. denied. On appeal, we will neither reweigh the evidence nor rejudge the credibility of witnesses. Id.

We first determine whether MCD had statutory authority to withhold the entire final payment. Ind.Code § 86-1-12-1 et seq. is a statutory scheme which provides for the payment of contractors, laborers, material suppliers, and those who perform services for public work projects. Wallem v. CLS Industries, Inc., 725 N.E.2d 880, 887 (Ind.Ct.App.2000). This relief is mandated by statute because mechanic's liens are not available to a claimant who works on public works projects. Id. The statute expands the rights of claimants who would be left without the ability to recover for the materials, labors, or services when general contractors and public entities are unable to make payment. Id. Generally, the public works board is required to withhold sufficient monies to pay subcontractors, laborers, material suppliers, and those performing services. Id.

The apposite provisions are Ind.Code § 36-1-12-12 and Ind.Code § 36-1-12-13. When a public work project is to be performed, "the board shall withhold final payment to the contractor until the contractor has paid the subcontractors, material suppliers, laborers, or those furnishing services." Ind.Code § 36-1-12-12(@). In order to receive payment, "the subcontractor or subcontractors, material suppliers, laborers, or those furnishing services shall file their claims with the board within sixty (60) days after the last labor performed, last material furnished, or last service rendered. ..." Ind.Code § 86-1-12-12(b). If there is no dispute between the parties claiming to be entitled to the money withheld, "the board shall pay the claim from the money due the contractor and deduct it from the contract price." Ind.Code § 86-1-12-12(c).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

David Roberts v. Estate of Bertha Roberts
Indiana Court of Appeals, 2014
Paris v. FAITH PROPERTIES, INC.
766 F. Supp. 2d 877 (N.D. Indiana, 2011)
Mead Johnson & Co., Inc. v. Kenco Group, Inc.
899 N.E.2d 1 (Indiana Court of Appeals, 2009)
Kempf v. ST. PAUL REINSURANCE CO. LIMITED
872 N.E.2d 162 (Indiana Court of Appeals, 2007)
Trinity Baptist Church v. Howard
869 N.E.2d 1225 (Indiana Court of Appeals, 2007)
Time Warner Entertainment Co. v. Whiteman
802 N.E.2d 886 (Indiana Supreme Court, 2004)
Dick Corp. v. Geiger
783 N.E.2d 368 (Indiana Court of Appeals, 2003)
Citicorp Vendor Finance, Inc. v. WIS Sheetmetal, Inc.
206 F. Supp. 2d 962 (S.D. Indiana, 2002)
Stewart v. Kingsley Terrace Church of Christ, Inc.
767 N.E.2d 542 (Indiana Court of Appeals, 2002)
Rogers v. Lockard
767 N.E.2d 982 (Indiana Court of Appeals, 2002)

Cite This Page — Counsel Stack

Bluebook (online)
764 N.E.2d 718, 2002 Ind. App. LEXIS 332, 2002 WL 363656, Counsel Stack Legal Research, https://law.counselstack.com/opinion/merrillville-conservancy-district-v-atlas-excavating-inc-indctapp-2002.