Dick Corp. v. Geiger

783 N.E.2d 368, 2003 Ind. App. LEXIS 212, 2003 WL 344193
CourtIndiana Court of Appeals
DecidedFebruary 17, 2003
Docket29A03-0206-CV-212
StatusPublished
Cited by14 cases

This text of 783 N.E.2d 368 (Dick Corp. v. Geiger) is published on Counsel Stack Legal Research, covering Indiana Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Dick Corp. v. Geiger, 783 N.E.2d 368, 2003 Ind. App. LEXIS 212, 2003 WL 344193 (Ind. Ct. App. 2003).

Opinion

OPINION

KIRSCH, Judge.

This case arises from a complaint filed by Dick Corporation ("DC") alleging inter alia civil and criminal conversion and constructive fraud against Gordon Geiger, Eduardo Calanog, and Albert Lucas ("Defendants"), who served as former officers and directors of Qualitech Steel Corporation ("Qualitech"), based upon their use of loan proceeds to pay Qualitech creditors other than DC. Following the trial court's grant of summary judgment in favor of Defendants on the conversion claims, DC appealed. Defendants subsequently filed an interlocutory appeal challenging the trial court's denial of their summary judgment motion on the issue of constructive fraud. Both cases have been consolidated for purposes of appeal, and we find the following issue dispositive: whether the parties' mutual release was conditioned upon the performance of certain obligations excluded from the release.

Because we conclude that the excluded obligations were not conditions precedent to the release, we affirm in part, reverse in part, and remand.

FACTS AND PROCEDURAL HISTORY 1

On June 20, 1996, Qualitech and DC entered into a contract for the construction of a state of the art special bar quality steel mill in Pittsboro, Indiana. Qualitech was a start-up company with virtually no other assets other than the mill it was building. Gordon Geiger served as Quali-tech's CEO and Chairman of the Board, Eduardo Calanog functioned as Qualitech's President and was a board member, and Albert Lucas served as Treasurer, Director of Finance and Accounting, and Assistant Secretary. 2 DC served as the general contractor of the construction project with the responsibility to build the facility, including providing foundations, buildings, and roads and installing the steelmaking equipment.

Pursuant to a March 1998 contract amendment, the contract price for the inte *370 grated design and construction of the mill was in excess of $118 million with payments to be made according to a fixed payment schedule. The final payment of $4,899,504.75 was due to be paid following completion of the project and subject to certain performance criteria, namely "hot and cold test guarantees" being satisfied. Qualitech obtained financing for the construction project from various lenders, which included a $40 million revolving credit line to be used as working capital. The terms of the construction loan required a Qualitech officer to certify that a draw on the revolving eredit line would be used to pay project costs, which included "capital expenditures, working capital or other operating costs [that] are necessary for the construction and operation of the Project." Appellant's Appendix at 342a.

By the beginning of 1998, although the mill was still several months from completion, it was becoming apparent to Quali-tech that it was in deteriorating financial condition. An operating budget completed in March 1998 and presented to Defendants forecast that Qualitech would continue to suffer a cash-flow problem and be unable to pay its debts by November 1998. This projected shortfall was not specifically discussed with DC prior to its execution of the contract amendment in March 1998.

DC completed the mill on schedule. In May 1998, DC turned over the mill building to Qualitech and in July 1998 turned over the melt shop and equipment. DC sent its final invoice to Qualitech on September 25, 1998 seeking payment of $4,399,504.75. On October 20, 1998, Quali-tech sent a letter to DC stating that it had reviewed the project and identified certain items that needed to be "cleared up" before payment of the final invoice. Appellant's Appendix at 812a. Qualitech's letter also declared that once agreement was reached on the items that it was "prepared to provide payment." Appellant's Appendix at 8122. A solution was reached and sometime later in October or November 1998, Geiger sent a memorandum to all those who worked on the mill construction, which in pertinent part stated:

On behalf of myself and the Qualitech family I want to express my sincere thanks to you for your hard work and efforts in building our steel mill, You will have built the mill in just 17 months from the first concrete pour, which is close to, if not in fact, a record. Most importantly, you have done so very safely, with an excellent safety record of which you can be very proud. Your productivity has been outstanding, allowing us to keep within our budget parameters.

Appellant's Appendix at 3152.

In November 1998, Qualitech submitted notice in accordance with its credit agreement with its lenders that it was request, ing a term loan in the amount of $41,815,790 from which it would prepay the outstanding revolving credit loan of $13,500,000 thereby leaving it with net proceeds of $28,815,790 to pay project costs. In further compliance with the credit agreement, Qualitech prepared a "Use of Advance Certificate" for its lenders in which it certified that the loan would be used only to pay project costs that had been incurred or were scheduled to be incurred along with supporting documentation. Appellant's Appendix at 342a,. The lenders refused to fund the November 4 draw request until receiving further information concerning Qualitech's open invoices. On November 13, 1998, a revised draw request was sent to the lenders, which included project costs that had not been paid, including DC's final invoice for $4.399 million. The draw request was still not funded because the lenders again requested more detailed information. A see- *371 ond revised draw request was submitted on November 16, 1998, and on or about November 17, 1998, the lenders wired $28,815,790 to Qualitech's operating account at Mellon Bank.

Despite the designation of the $4.399 million for payment to DC, Qualitech did not make final payment. Aware that Qual-itech had received funding, DC wrote in a December 18, 1998 letter to Qualitech that it had been awaiting final payment (exelud-ing pending change orders) for almost three months and that if payment was not received by December 28, 1998, DC would "have no choice but to declare Qualitech in default and [to] exercise all available legal remedies to secure and recover the funds due us." Appellees' Appendix at 165B. On December 28, 1998, Geiger and Peter Matt of Credit Suisse First Boston met at the Pittsburgh airport with Ken Martin, Roger Peters, Esq., and Ken Burk, all with DC, to discuss Qualitech's financial situation, the outstanding final payment, and efforts Qualitech was taking to arrange payment. The next day, DC sent Qualitech a letter in which it thanked Qual-itech for the meeting and its candor concerning its financial situation, declared Qualitech in default, and expressed the desire to resolve the outstanding final contract payment of $4.399 million and open change orders. OC

Negotiations between the parties occurred in January, and on February 4, 1999, DC sent a letter to Qualitech confirming. their agreement with respect to the final contract payment of $4.399 million and payment for the outstanding change orders in the amount of $3 million. Ne requested a Qualitech signature on the "letter agreement," which Geiger executed and returned to DC. Appellees' Appendix at 181-182B. By letter dated February 5, 1999, DC sent its Change Order No.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Scott v. Zimmer, Inc.
889 F. Supp. 2d 657 (D. Delaware, 2012)
Moore v. Wells Fargo Construction
903 N.E.2d 525 (Indiana Court of Appeals, 2009)
Four Seasons Manufacturing, Inc. v. 1001 Coliseum, LLC
870 N.E.2d 494 (Indiana Court of Appeals, 2007)
Harbours Condominium Ass'n, Inc. v. Hudson
852 N.E.2d 985 (Indiana Court of Appeals, 2006)
Liggett v. Young
851 N.E.2d 968 (Indiana Court of Appeals, 2006)
Northstar Partners v. Marsh Supermarkets, Inc.
157 F. App'x 932 (Seventh Circuit, 2005)
Morfin v. Estate of Martinez
831 N.E.2d 791 (Indiana Court of Appeals, 2005)
Thomas Hinc v. Lime-O-Sol Company
382 F.3d 716 (Seventh Circuit, 2004)
Haltom v. State
808 N.E.2d 761 (Indiana Court of Appeals, 2004)

Cite This Page — Counsel Stack

Bluebook (online)
783 N.E.2d 368, 2003 Ind. App. LEXIS 212, 2003 WL 344193, Counsel Stack Legal Research, https://law.counselstack.com/opinion/dick-corp-v-geiger-indctapp-2003.