George B. Swift Co. v. Dolle

80 N.E. 678, 39 Ind. App. 653, 1907 Ind. App. LEXIS 187
CourtIndiana Court of Appeals
DecidedMarch 19, 1907
DocketNo. 5,897
StatusPublished
Cited by8 cases

This text of 80 N.E. 678 (George B. Swift Co. v. Dolle) is published on Counsel Stack Legal Research, covering Indiana Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
George B. Swift Co. v. Dolle, 80 N.E. 678, 39 Ind. App. 653, 1907 Ind. App. LEXIS 187 (Ind. Ct. App. 1907).

Opinion

Comstock, J.

The complaint alleges that Edward E. Claypool was the owner in fee simple, and the Indiana Hotel Company was lessee, in possession under a ninety-nine-year lease, of certain real estate in the city of Indianapolis, Indiana; that in July, 1901, the Indiana Hotel Company entered into a contract with the George B. Swift Company to erect on said real estate a building; that in the same month the Ransome Concrete Fireproofing Company, hereinafter called the Ransome Company, entered into a contract with the George B. Swift Company to furnish the fireproofing for said building; that said Ransome Company did furnish materials and labor for the construction of said building, to the value of $25,000; that in April, 1902, and within sixty days of the date of the furnishing of said materials, the Ransome Company filed in the recorder’s office of Marion county its written notice of its intention to hold a lien on said real estate in the amount of $25,000. It further alleges that a reasonable fee for plaintiff’s attorney is $1,000, and demands judgment for $28,000, and an enforcement of a lien against the real estate. Afterward, on its petition, the George B. Swift Company was made a party defendant over the objection of the appellee.

The George B. Swift Company, in addition to the general denial, filed a special answer alleging: That on July 8, 1901, it entered into a written contract with the Indiana Hotel Company to build for it an eight-story fire-proof [655]*655hotel and. business building; that on July 19, 1901, the George B. Swift Company entered into a contract with the Ransome Company, whereby it agreed to provide, deliver and place in position all materials and perform all work mentioned in the specifications and drawings referred to in said contract for the Ransome Company, a copy of which contract was made a part of the answer; that it was provided in said contract that the labor was to be performed and materials furnished by the Ransome Company, and the several portions of the work completed at certain times as the building would be ready for the work; that time was of the essence of the contract, and that as the various branches of the work had to proceed in unison, and each depended upon the other, it was necessary for the work of the Ransome Company to be completed at such times and in such portions as would enable the succeeding portions of work on said building to proceed according to time scheduled, without delay, and that the contract price should be lessened by the sum of $50 per day for each and every day of delay in the completion of the work beyond the specified date provided in said contract. It is further alleged that it was provided in said contract that upon failure of the Ran-some Company to supply a sufficient number of skilled workmen, or to furnish machinery, tools or other like necessaries, or in any respect to prosecute the work with promptness and diligence, the George B. Swift Company could take .charge of the work and complete the same;That within two weeks after this date the Ransome Company should execute to the George B. Swift Company a satisfactory surety bond in the sum of $50,000, to secure the faithful performance of its contract; that the Ransome Company failed to perform its contract according to its terms; that it failed to proceed with the work to such an extent that the construction of the building was retarded more than thirty days, and that the George B. Swift Company, the Ransome Company having abandoned the work, took charge of the same, after having [656]*656served notice upon the Ransome Company, and completed the contract at an expenditure of $70,000, which was more than $5,000 above contract, price; that the Ransome Company failed to furnish such bond for $50,000, and judgment was demanded against the appellee for the sum of $25,000.

Edward E. Claypool answered by general denial. The Indi'ana Hotel Company, in addition to a general denial and plea of payment, -filed a special answer, in which it set up the contract between the Ransome Company and the George B. Swift Company. It alleged that the Ransome Company did not comply with its contract, and delayed its work to such an extent that the George B. Swift Company took charge of the same; that the Ransome Company, in its contract, agreed to keep the real estate upon which the building was to be erected free of any mechanics’ liens, but that it violated said agreement, and allowed a large number of liens to be filed for material put into said'building by said Ransome Company; that in said contract the Ransome Company agreed to accept in payment of $5,000 of the contract price, fifty shares of preferred stock of the Indiana Hotel Company at the par value of $100 per share; that it never took said shares, and, by its failure to carry out said contract, was never entitled to receive said shares; that the Ransome Company violated the terms of its contract by failing to execute the bond for $50,000 which it agreed to execute ; that at the time plaintiff’s action was begun the Ran-some Company was indebted to the Geore B. Swift Company in the sum of $25,000, after allowing it credit for any labor performed or material furnished in the execution of said contract; that at the time the action was begun there was nothing due the Ransome Company, but, on the contrary, on settlement of accounts between the fireproofing company, represented by the appellee, and the George B. Swift Company, allowing credits for materials furnished and labor performed on said building, there would still be [657]*657an indebtedness of $25,00(7 due from said Bansome Company, represented by appellee, to said George B. Swift Company.

In tbe fourth paragraph of answer the Indiana Hotel Company set out that in the contract between the Bansome Company and the George B. Swift Company it was provided, among other things, that the Bansome Company agreed to keep the real estate described in said contract free from any mechanics’ liens, and in the contract between the George B. Swift Company and the Indiana Hotel Company it was provided that the George B. Swift Company would keep the real estate free from any mechanics’ liens, alleging that the appellee was not entitled to any relief against the defendant, and that there was no lien upon the real estate in favor of appellee.

The case was tried by the court without a jury, a special finding of facts made, and conclusions of law stated thereon. The assignment of error is that the court erred in its conclusions of law.

The court found that the defendant Olaypool is the owner of the real estate, and the Indiana Hotel Company holds the same under a ninety-nine-year lease; that the Indiana Hotel Company entered into a contract with the George B. Swift Company for the erection of the building on said real estate; that said contract was in writing, being the same set forth in the cross-complaint of the George B. Swift Company, and that one of the agreements and conditions of said contract was that the George B. Swift Company would “keep said real estate free from all mechanics’ liens;” that the George B. Swift Company made a subcontract with the Bansome Company, being the same contract .set forth in the answer and counterclaim of the defendant the George B. Swift Company; that after work had been begun, on the written contract between the George B. Swift Company and the Bansome Company, an oral contract was entered into between them whereby the Bansome Company agreed to [658]*658construct the common concrete work about the engine-room and other work, in the execution of the contract of the George.B.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Time Warner Entertainment Co. v. Whiteman
802 N.E.2d 886 (Indiana Supreme Court, 2004)
Merrillville Conservancy District v. Atlas Excavating, Inc.
764 N.E.2d 718 (Indiana Court of Appeals, 2002)
Johnson-Johnson, Inc. v. Farah
108 N.E.2d 638 (Indiana Court of Appeals, 1952)
Baldwin Locomotive Works v. Edward Hines Lumber Co.
125 N.E. 400 (Indiana Supreme Court, 1919)
Hoosier Brick Co. v. Floyd County Bank
116 N.E. 87 (Indiana Court of Appeals, 1917)
Hume v. Seattle Dock Co.
137 P. 752 (Oregon Supreme Court, 1914)

Cite This Page — Counsel Stack

Bluebook (online)
80 N.E. 678, 39 Ind. App. 653, 1907 Ind. App. LEXIS 187, Counsel Stack Legal Research, https://law.counselstack.com/opinion/george-b-swift-co-v-dolle-indctapp-1907.