Meredith v. Roman

141 P. 643, 49 Mont. 204, 1914 Mont. LEXIS 59
CourtMontana Supreme Court
DecidedMay 16, 1914
DocketNo. 3,382
StatusPublished
Cited by26 cases

This text of 141 P. 643 (Meredith v. Roman) is published on Counsel Stack Legal Research, covering Montana Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Meredith v. Roman, 141 P. 643, 49 Mont. 204, 1914 Mont. LEXIS 59 (Mo. 1914).

Opinion

MR. CHIEF JUSTICE BRANTLY

delivered the opinion of the court.

The defendant Bitter Root Yalley Irrigation Company, a corporation, hereafter referred to as “the company,” at the time of the occurrences out of which this controversy arose, was the owner of a storage reservoir at Lake Como, in Ravalli county, together with the right of way for a canal and a canal in course of construction thereon, extending from the reservoir northward through Bitter Root Yalley. The purpose for which the canal was being constructed was to convey water' to the lands lying along its course belonging to the company, to irrigate them. On October 18, 1909, it entered into a contract with defendant Thomas J. White, under the terms of which the latter agreed to do all the work necessary to complete a portion [207]*207of the canal described in specifications and plans attached to the contract. The work was to be done in compliance with the specifications and plaDS, to the entire satisfaction of the company. The compensation to be paid was fixed at a stipulated price per cubic yard for excavation work, varying in amount according to the nature of material to be moved, per square yard for grubbing, and per acre for plowing, etc. All the work was to be completed on or before May 1, 1910. Among other things it was stipulated: “If the work to be done under this contract shall be abandoned, or if at any time the company shall be of the opinion that the said work is unnecessarily delayed * * * or * # * the contractor fails to show such progress in the execution of the work as will give reasonable grounds for anticipating the completion within the required time, the said company shall have the power to notify the contractor to discontinue all work or any part thereof under this contract # * * and the said company shall thereupon have the right, at its discretion, to contract with other parties for the delivery or completion of all or any part of the work left uncompleted by said contractor, or for the correction of the whole or any part of said work. In case the expense incurred by said company is less than would have been payable under this contract if the same had been completed by said contractor, then said contractor shall be entitled to receive the difference.” On November 1, by contract with defendants Roman and Bennett, copartners, White sublet to them a portion of the work, including all that part of the canal between stations 2893 and 3083. On November 6 these defendants sublet to the plaintiffs that part of the work included between stations 2893 and 2999. The stations marked the sections of uniform length into which the whole line of canal was divided. In both of these latter contracts it was stipulated that the work covered by them should be completed on or before May 1, 1910, in conformity with the “specifications and plans” embodied in the contract of the company with White, to the entire satisfaction of the engineers of the defendant company. As the basis of compensation, the classification of ma[208]*208terial moved was to be made by the engineers of the company. Neither of them contained any other reference to the White contract.”

The complaint contains two causes of action and seeks recovery against all the defendants. In the first cause of action, after a recital of the facts above stated, it' is alleged, that immediately after entering into the contract, the plaintiffs began the work which they had agreed to perform thereunder, and continued the same until its completion, except when delayed by the defendants; that, in consideration of the completion thereof and the fulfillment of all the terms and conditions of the contract by plaintiffs; the defendants became indebted to them in the sum of $1,678.85; and that no part of this amount has been paid except the sum of $801.35, leaving a balance due of $876.50. Then follow allegations to the effect that, within the time prescribed by the statute and in conformity with its requirements, plaintiffs filed with the clerk of Ravalli county their notice of claim of lien upon the reservoir, canal, right of way, etc., of the company. The prayer demands that plaintiffs have judgment for the balance due, with costs; that the same be declared a lien upon the property of the company; and that the property be sold to satisfy the judgment in case the same shall not be satisfied by Roman and Bennett. At the trial the issues presented in connection with the second cause of action were resolved in favor of the defendants. It is therefore not necessary to state the nature of it or its purpose further than to say that it demanded damages for delay caused plaintiffs by interference by defendants with the prosecution of the work covered by the contract.

The action was commenced on October 5, 1910. The issues having been made up by answers by the defendants, the trial was set for October-, 1911. Upon stipulation by counsel the setting was vacated. Thereafter the date of the trial was fixed for March 18, 1912. After the order fixing the date of trial/ and on February 23, the defendants Roman and Bennett, without leave of court, filed and served upon counsel for plaintiffs a pleading which purports to be an amended answer, “cross-[209]*209complaint and counterclaim,” for affirmative relief. In the portion of this pleading designated as an answer, it is alleged that these defendants are entitled to a credit of $1,582.15 upon the amount earned by the plaintiffs under their contract, instead of $801.50, as alleged .in the complaint, leaving a balance due plaintiffs of $94.70. It is further alleged that the plaintiffs have fully and in all particulars performed all the terms, provisions and obligations of said contract on their part to be kept and performed, “save and except that it became necessary for these defendants to furnish to the said plaintiffs the use of their construction force at an agreed charge therefor of $780.80, which said sum is included in the above-named credit of $1,582.15.” The portion of the answer designated cross-complaint and counterclaim contains allegations appropriate to charge the defendant company and White for a balance due Roman and Bennett for work done under their contract of $9,-767.71, and judgment is demanded against them for this amount. It is alleged that the work done by the plaintiffs, for which they seek to charge the defendants Roman and Bennett, was done under the several contracts heretofore referred to, and is a joint liability against these defendants and the company and White. It is further alleged that in order to determine justly and equitably the rights of the plaintiffs against Roman and Bennett, and in order to avoid circuity of action and a multiplicity of suits, it is essential that the rights of these defendants as against the company and White be finally determined and fully adjudicated in this action. On March 5, 1912, on motion of plaintiffs, the portion of the so-called cross-complaint and counterclaim, seeking to charge the company and White for the balance alleged to be due Roman and Bennett, were stricken out on the ground that these allegations were redundant and did not constitute a defense or counterclaim to either cause of action set forth in the complaint. Thereupon the plaintiffs filed a reply denying the allegations of the answer wherein Roman and Bennett claim an additional credit of $780.80 for furnishing to plaintiffs their construction force. On February 24, by leave of court the company filed an amended [210]*210answer putting in issue all the allegations in the complaint charging liability against it in favor of plaintiffs.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

State Ex Rel. State Highway Commission v. Donovan
448 P.2d 671 (Montana Supreme Court, 1968)
Westfall v. Motors Insurance
348 P.2d 784 (Montana Supreme Court, 1960)
Strack v. Federal Land Bank of Spokane
218 P.2d 1052 (Montana Supreme Court, 1950)
Busquets v. Nieto
57 P.R. 820 (Supreme Court of Puerto Rico, 1941)
Turiana v. Nieto
57 P.R. Dec. 835 (Supreme Court of Puerto Rico, 1941)
O'Neill v. Wall
62 P.2d 672 (Montana Supreme Court, 1936)
State Ex Rel. Clark v. Bailey
44 P.2d 740 (Montana Supreme Court, 1935)
Grosfield v. Johnson
39 P.2d 660 (Montana Supreme Court, 1935)
State v. Ewert
219 N.W. 817 (South Dakota Supreme Court, 1928)
State v. Smart
262 P. 158 (Montana Supreme Court, 1927)
Meagher v. Harrington
254 P. 432 (Montana Supreme Court, 1927)
Ward v. Strowd
244 P. 1007 (Montana Supreme Court, 1926)
State v. Yegen
238 P. 603 (Montana Supreme Court, 1925)
State v. Cassill
227 P. 49 (Montana Supreme Court, 1924)
McCarthy v. Anaconda Copper Mining Co.
225 P. 391 (Montana Supreme Court, 1924)
Price v. Skylstead
222 P. 1059 (Montana Supreme Court, 1924)
Wasley v. Dryden
212 P. 491 (Montana Supreme Court, 1923)
McLean v. Rice
208 P. 252 (Montana Supreme Court, 1922)
Puckett v. Hopkins
206 P. 422 (Montana Supreme Court, 1922)

Cite This Page — Counsel Stack

Bluebook (online)
141 P. 643, 49 Mont. 204, 1914 Mont. LEXIS 59, Counsel Stack Legal Research, https://law.counselstack.com/opinion/meredith-v-roman-mont-1914.