MEMC II v. Cannon Storage Systems

CourtCourt of Appeals for the Tenth Circuit
DecidedFebruary 12, 2019
Docket18-6079
StatusUnpublished

This text of MEMC II v. Cannon Storage Systems (MEMC II v. Cannon Storage Systems) is published on Counsel Stack Legal Research, covering Court of Appeals for the Tenth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
MEMC II v. Cannon Storage Systems, (10th Cir. 2019).

Opinion

FILED United States Court of Appeals UNITED STATES COURT OF APPEALS Tenth Circuit

FOR THE TENTH CIRCUIT February 12, 2019 _________________________________ Elisabeth A. Shumaker Clerk of Court MEMC II, LLC; MIKE MCDANIEL,

Plaintiffs - Appellants,

v. No. 18-6079 (D.C. No. 5:18-CV-00143-C) CANNON STORAGE SYSTEMS, INC., (W.D. Okla.)

Defendant - Appellee. _________________________________

ORDER AND JUDGMENT* _________________________________

Before MATHESON, PHILLIPS, and EID, Circuit Judges. _________________________________

MEMC II, LLC and Mike McDaniel (collectively, “MEMC”) contracted to

have Cannon Storage Systems, Inc. (“Cannon”) build a commercial storage facility in

Dallas, Texas. The contract included precise design specifications and stipulated that

any disputes between the parties would be subject to binding arbitration. During

construction, Cannon deviated from the agreed-upon design specifications. In

response, MEMC withheld payments. The parties submitted their dispute to

* After examining the briefs and appellate record, this panel has determined unanimously that oral argument would not materially assist in the determination of this appeal. See Fed. R. App. P. 34(a)(2); 10th Cir. R. 34.1(G). The case is therefore ordered submitted without oral argument. This order and judgment is not binding precedent, except under the doctrines of law of the case, res judicata, and collateral estoppel. It may be cited, however, for its persuasive value consistent with Federal Rule of Appellate Procedure 32.1 and 10th Circuit Rule 32.1. arbitration, each raising claims for breach of contract. The arbitrator found that

Cannon had breached by varying from the design specifications, that MEMC had

breached by withholding payments, and that MEMC was liable to Cannon for

approximately $230,000 in damages.

MEMC applied for relief from the arbitration award in the United States

District Court for the Western District of Oklahoma. It argued that Cannon’s

deviation from the design specifications constituted material breach and thus excused

MEMC from its payment obligations under the contract. Accordingly, MEMC

requested that the court confirm the arbitrator’s finding of Cannon’s breach and

vacate the award of damages to Cannon. The district court denied MEMC’s

application, and MEMC timely appealed. Exercising jurisdiction under 28 U.S.C.

§1291, we affirm.

I. BACKGROUND

A. The Contract

On June 17, 2016, MEMC and Cannon entered into a construction industry

“Standard Form of Agreement Between Owner and Contractor” (“Contract”)

obligating Cannon to build a commercial storage facility in Dallas, Texas. The

Contract incorporated American Institute of Architects (“AIA”) Document

A201-2007, which provided general terms about insurance, tax liabilities, and other

miscellaneous topics. The Contract also listed express performance standards and

mandated Cannon’s compliance with a detailed set of design specifications. In

2 addition, the Contract specified payment terms and provided that MEMC would pay

Cannon in installments on the 15th day of each month.

The Contract also contained a section called “Binding Dispute Resolution,”

which mandated arbitration for any contractual disputes subject to but not resolved

by mediation. Specifically, the Contract incorporated Section 15.4 of AIA Document

A201-2007, which reads:

If the parties have selected arbitration as the method for binding dispute resolution in the Agreement, any Claim subject to, but not resolved by, mediation shall be subject to arbitration which, unless the parties mutually agree otherwise, shall be administered by the American Arbitration Association in accordance with its Construction Industry Arbitration Rules in effect on the date of the Agreement. . . . The award rendered by the arbitrator or arbitrators shall be final, and judgment may be entered upon it in accordance with applicable law in any court having jurisdiction thereof.

Id. at 69.

The parties agreed that Texas law would govern any contractual dispute. They

also agreed that “[p]ending final resolution of a claim, Cannon shall proceed

diligently with performance of the contract and [MEMC] shall continue to make

payments in accordance with payment terms.” Aplt. App. at 25.

B. The Dispute

After starting construction, Cannon decided that the plans specified in the

Contract were “inadequate.” Aplt. App. at 188. Accordingly, Cannon hired a new

engineer and changed the structural plans. When MEMC learned of the changes, it

refused to make further payments, arguing that Cannon had breached the Contract by

3 deviating from the design specifications. Cannon continued construction without

payment for nearly five months. On December 14, 2016, MEMC sent Cannon a

demand letter describing the perceived breach and warning that it planned to

“proceed with initiating the claim process.” Id. at 72. The letter yielded no results,

and Cannon eventually submitted the dispute to arbitration.

C. Arbitration

Cannon brought arbitration claims for breach of contract based on MEMC’s

nonpayment. MEMC responded with an affirmative defense, arguing that Cannon’s

departure from the design specifications was a material breach that discharged

MEMC’s payment obligations. MEMC also counter-claimed for breach of contract,

arguing that “Cannon failed to use the approved plans and specifications and did not

complete the construction in accordance with approved plans and specifications.” Id.

at 76.

The arbitrator issued a decision on January 12, 2018. She found that MEMC

breached the Contract by refusing to pay Cannon, and that Cannon breached the

contract by failing to construct the storage facility according to the agreed-upon

specifications. For both findings of breach, the arbitrator cited Bartush-Schnitzius

Foods Co. v. Cimco Refrigeration, Inc., 518 S.W.3d 432 (Tex. 2017) (“Cimco”),

which outlines the factors that Texas courts use to assess materiality.

4 Because she found that MEMC breached by withholding payments, the

arbitrator awarded Cannon $143,608.82 owed under the Contract.1 She also noted

that although “[MEMC] established that Cannon breached the contract by not getting

owner approval for several changes to the structural plans, evidence of the cost to

remediate the work related to [Cannon’s design] changes was insufficient.” Id. at

173 n.3. Accordingly, she found that MEMC could “recover nothing from Cannon.”

Id. at 173.

D. District Court Proceedings

On February 13, 2018, MEMC filed an application for relief regarding the

arbitration award in the United States District Court for the Western District of

Oklahoma. MEMC said that under Texas law, “a failure by a contracting party to

comply with expressly defined performance metrics . . . categorically operates as a

‘material’ breach.” Id. at 7. MEMC further argued that “[w]hen one party to a

contract materially breaches the contract, the non-breaching party is discharged or

excused from further performance of its duties.” Id.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Brown v. Coleman Company
220 F.3d 1180 (Tenth Circuit, 2000)
Mustang Pipeline Co. v. Driver Pipeline Co.
134 S.W.3d 195 (Texas Supreme Court, 2004)
Oxford Health Plans LLC v. Sutter
133 S. Ct. 2064 (Supreme Court, 2013)
Major League Baseball Players Assn. v. Garvey
532 U.S. 504 (Supreme Court, 2001)
Bartush-Schnitzius Foods Co. v. Cimco Refrigeration, Inc.
518 S.W.3d 432 (Texas Supreme Court, 2017)
THI of New Mexico at Vida Encantada, LLC v. Lovato
864 F.3d 1080 (Tenth Circuit, 2017)
Dish Network L.L.C. v. Ray
900 F.3d 1240 (Tenth Circuit, 2018)

Cite This Page — Counsel Stack

Bluebook (online)
MEMC II v. Cannon Storage Systems, Counsel Stack Legal Research, https://law.counselstack.com/opinion/memc-ii-v-cannon-storage-systems-ca10-2019.