MEMC II v. Cannon Storage Systems

Court of Appeals for the Tenth Circuit·Decided February 12, 2019·No. 18-6079·Unpublished

Opinion

FILED

United States Court of Appeals UNITED STATES COURT OF APPEALS Tenth Circuit

FOR THE TENTH CIRCUIT February 12, 2019

Elisabeth A. Shumaker

Clerk of Court

MEMC II, LLC; MIKE MCDANIEL,

Plaintiffs - Appellants,

v. No. 18-6079 (D.C. No. 5:18-CV-00143-C)

CANNON STORAGE SYSTEMS, INC., (W.D. Okla.)

Defendant - Appellee.

ORDER AND JUDGMENT*

Before MATHESON, PHILLIPS, and EID, Circuit Judges.

MEMC II, LLC and Mike McDaniel (collectively, “MEMC”) contracted to have Cannon Storage Systems, Inc. (“Cannon”) build a commercial storage facility in Dallas, Texas. The contract included precise design specifications and stipulated that any disputes between the parties would be subject to binding arbitration. During construction, Cannon deviated from the agreed-upon design specifications. In response, MEMC withheld payments. The parties submitted their dispute to

*

After examining the briefs and appellate record, this panel has determined unanimously that oral argument would not materially assist in the determination of this appeal. See Fed. R. App. P. 34(a)(2); 10th Cir. R. 34.1(G). The case is therefore ordered submitted without oral argument. This order and judgment is not binding precedent, except under the doctrines of law of the case, res judicata, and collateral estoppel. It may be cited, however, for its persuasive value consistent with Federal Rule of Appellate Procedure 32.1 and 10th Circuit Rule 32.1.

arbitration, each raising claims for breach of contract. The arbitrator found that Cannon had breached by varying from the design specifications, that MEMC had breached by withholding payments, and that MEMC was liable to Cannon for approximately $230,000 in damages.

MEMC applied for relief from the arbitration award in the United States District Court for the Western District of Oklahoma. It argued that Cannon’s deviation from the design specifications constituted material breach and thus excused MEMC from its payment obligations under the contract. Accordingly, MEMC requested that the court confirm the arbitrator’s finding of Cannon’s breach and vacate the award of damages to Cannon. The district court denied MEMC’s application, and MEMC timely appealed. Exercising jurisdiction under 28 U.S.C. §1291, we affirm.

I. BACKGROUND

A. The Contract

On June 17, 2016, MEMC and Cannon entered into a construction industry “Standard Form of Agreement Between Owner and Contractor” (“Contract”) obligating Cannon to build a commercial storage facility in Dallas, Texas. The Contract incorporated American Institute of Architects (“AIA”) Document A201-2007, which provided general terms about insurance, tax liabilities, and other miscellaneous topics. The Contract also listed express performance standards and mandated Cannon’s compliance with a detailed set of design specifications. In

addition, the Contract specified payment terms and provided that MEMC would pay Cannon in installments on the 15th day of each month.

The Contract also contained a section called “Binding Dispute Resolution,”

which mandated arbitration for any contractual disputes subject to but not resolved by mediation. Specifically, the Contract incorporated Section 15.4 of AIA Document A201-2007, which reads:

If the parties have selected arbitration as the method for binding dispute resolution in the Agreement, any Claim subject to, but not resolved by, mediation shall be subject to arbitration which, unless the parties mutually agree otherwise, shall be administered by the American Arbitration Association in accordance with its Construction Industry Arbitration Rules in effect on the date of the Agreement. . . . The award rendered by the arbitrator or arbitrators shall be final, and judgment may be entered upon it in accordance with applicable law in any court having jurisdiction thereof.

Id. at 69.

The parties agreed that Texas law would govern any contractual dispute. They also agreed that “[p]ending final resolution of a claim, Cannon shall proceed diligently with performance of the contract and [MEMC] shall continue to make payments in accordance with payment terms.” Aplt. App. at 25.

B. The Dispute

After starting construction, Cannon decided that the plans specified in the Contract were “inadequate.” Aplt. App. at 188. Accordingly, Cannon hired a new engineer and changed the structural plans. When MEMC learned of the changes, it refused to make further payments, arguing that Cannon had breached the Contract by

deviating from the design specifications. Cannon continued construction without payment for nearly five months. On December 14, 2016, MEMC sent Cannon a demand letter describing the perceived breach and warning that it planned to “proceed with initiating the claim process.” Id. at 72. The letter yielded no results, and Cannon eventually submitted the dispute to arbitration.

C. Arbitration

Cannon brought arbitration claims for breach of contract based on MEMC’s nonpayment. MEMC responded with an affirmative defense, arguing that Cannon’s departure from the design specifications was a material breach that discharged MEMC’s payment obligations. MEMC also counter-claimed for breach of contract, arguing that “Cannon failed to use the approved plans and specifications and did not complete the construction in accordance with approved plans and specifications.” Id. at 76.

The arbitrator issued a decision on January 12, 2018. She found that MEMC breached the Contract by refusing to pay Cannon, and that Cannon breached the contract by failing to construct the storage facility according to the agreed-upon specifications. For both findings of breach, the arbitrator cited Bartush-Schnitzius Foods Co. v. Cimco Refrigeration, Inc., 518 S.W.3d 432 (Tex. 2017) (“Cimco”), which outlines the factors that Texas courts use to assess materiality.

Because she found that MEMC breached by withholding payments, the arbitrator awarded Cannon $143,608.82 owed under the Contract.1 She also noted that although “[MEMC] established that Cannon breached the contract by not getting owner approval for several changes to the structural plans, evidence of the cost to remediate the work related to [Cannon’s design] changes was insufficient.” Id. at 173 n.3. Accordingly, she found that MEMC could “recover nothing from Cannon.” Id. at 173.

D. District Court Proceedings On February 13, 2018, MEMC filed an application for relief regarding the arbitration award in the United States District Court for the Western District of Oklahoma. MEMC said that under Texas law, “a failure by a contracting party to comply with expressly defined performance metrics . . . categorically operates as a ‘material’ breach.” Id. at 7. MEMC further argued that “[w]hen one party to a contract materially breaches the contract, the non-breaching party is discharged or excused from further performance of its duties.” Id. at 8 (citing Mustang Pipeline Co., Inc. v. Denver Pipeline Co., Inc., 134 S.W.3d 195, 196 (Tex. 2004)).

Because the arbitrator found that Cannon deviated from express “performance metrics,”2 MEMC contended that the arbitration decision operated as a finding of

1 The arbitrator also awarded Cannon $28,811.68 in interest, judicial foreclosure of its mechanic liens, $49,016.89 in attorney fees, and $6,914.50 in expert witness fees.

2 MEMC has used this term throughout the matter. See, e.g., Aplt. Br. at 3, 4, 10.

material breach. MEMC thus claimed that the arbitrator should not have awarded damages. It argued that, because Cannon “materially breached the contract first,” MEMC was excused from, and could not be held liable for, its payment obligations under the Contract. Id. at 11. MEMC asked the district court to vacate the damages award but “enforce” the arbitrator’s finding that Cannon had breached the Contract. Id. at 7.

The district court denied MEMC’s application. It explained “there exists [a]

Free access — add to your briefcase to read the full text and ask questions with AI

MEMC II v. Cannon Storage Systems, (10th Cir. 2019).

MEMC II v. Cannon Storage Systems (MEMC II v. Cannon Storage Systems) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Brown v. Coleman Company
220 F.3d 1180 (Tenth Circuit, 2000)
Mustang Pipeline Co. v. Driver Pipeline Co.
134 S.W.3d 195 (Texas Supreme Court, 2004)
Oxford Health Plans LLC v. Sutter
133 S. Ct. 2064 (Supreme Court, 2013)
Major League Baseball Players Assn. v. Garvey
532 U.S. 504 (Supreme Court, 2001)
Bartush-Schnitzius Foods Co. v. Cimco Refrigeration, Inc.
518 S.W.3d 432 (Texas Supreme Court, 2017)
THI of New Mexico at Vida Encantada, LLC v. Lovato
864 F.3d 1080 (Tenth Circuit, 2017)
Dish Network L.L.C. v. Ray
900 F.3d 1240 (Tenth Circuit, 2018)