Mechanical Systems, Inc. v. ND Paper, Inc.

CourtDistrict Court, W.D. Wisconsin
DecidedMay 5, 2022
Docket3:20-cv-00510
StatusUnknown

This text of Mechanical Systems, Inc. v. ND Paper, Inc. (Mechanical Systems, Inc. v. ND Paper, Inc.) is published on Counsel Stack Legal Research, covering District Court, W.D. Wisconsin primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Mechanical Systems, Inc. v. ND Paper, Inc., (W.D. Wis. 2022).

Opinion

IN THE UNITED STATES DISTRICT COURT FOR THE WESTERN DISTRICT OF WISCONSIN

MECHANICAL SYSTEMS, INC.,

Plaintiff and Counter-Defendant, OPINION AND ORDER v. 20-cv-510-wmc ND PAPER, INC.,

Defendant and Counter-Claimant,

and

ND PAPER, INC.,

Third-Party Plaintiff,

v.

TONY PUMPER, PAUL LESTER, BILLY OWENS, JASON KOESTER, and MIKE PRAHL,

Third-Party Defendants.

Among other, related claims, plaintiff Mechanical Systems, Inc. (“MSI”) asserts that defendant ND Paper, Inc., breached their contract by allegedly failing to pay for MSI’s construction of various large water towers at a paper mill owned and operated by ND Paper. In response to this lawsuit, ND Paper also asserts counterclaims against MSI sounding in breach of contract and tort for allegedly seizing certain equipment meant to be used in the construction of one of those towers. Finally, ND Paper asserts third-party claims against individual officers and employees of MSI based on the same alleged misconduct. Pending before the court presently are the parties’ cross-motions for summary judgment on ND Paper’s counterclaims and third-party claims. (Dkt. ##57, 63.) For the reasons that follow, the court will grant summary judgment to the MSI employees on the entirety of ND Paper’s third-party compaint and dismiss them from this lawsuit. The court will also grant partial summary judgment to plaintiff MSI on ND Paper’s conversion

counterclaim. As for ND Paper’s other counterclaims, however, the court must deny the remainder ND Paper’s motion for summary judgment, finding genuine issues of material fact surrounding MSI’s seizure and retention of equipment.

UNDISPUTED FACTS1 A. Overview of the Parties Mechanical Systems, Inc., is a Minnesota corporation, with its principal place of business in Dundas, Minnesota. As reflected by the events surrounding this lawsuit, MSI

regularly conducts business in Wisconsin, including in Wisconsin Rapids, where the project in dispute (“the Project”) was undertaken. For all times relevant to those events, Tony Pumper was MSI’s Vice President of Operations; Paul Lester was MSI’s Project Manager; Billy Owens was MSI’s Field Tank Superintendent (also referred to as the “foreman” of the project); Jason Koester was a truck driver for MSI; and Mike Prahl was the crane or

equipment operator on the Project. ND Paper, Inc., is a Delaware Corporation, with its principal place of business in Oakbrook Terrace, Illinois. ND Paper owns and operates a paper mill in Wisconsin Rapids, Wisconsin.

1 Unless otherwise noted, the court finds the following facts material and undisputed. B. Contract On April 22, 2019, MSI and ND Paper entered into a contract for the construction of two, 700 tons-per-day (“TPD”) water towers and one, 1,000 TPD water tower at MSI’s

Wisconsin Rapids paper mill, referred in the contract as “the Property,” “the Mill” or “Biron Mill.” (Compl., Ex. 1 (“Contract”) (dkt. #2-1).) In the Contract, MSI is referred to as “Contractor,” while “Owner” refers to ND Paper. The parties also refer to the towers under dispute interchangeably as “tanks.” The original value of the Contract totaled $2,499.072.00 and required payment of invoices by ND Paper within 30 days of receipt, although on July 22, 2019, it was amended to add construction of other items for an

additional $623,993.76. Material to ND Paper’s counterclaims and third-party complaint, Paragraph B of the Contract provides the following, general description of “Equipment”: The Contractor wishes to design, build, install and sell to the Owner, 700 TPD Dump Tower (1), 700 TPD OCC Storage Tower (1), and 1000 TPD White Water Tower – PM25 and all related equipment, components and part (which, unless the context requires otherwise, are collectively referred to in this Agreement as the “Equipment”) all as more particularly described in the technical specification (the “Technical Specifications”) attached as Schedule A, for use at the Mill. (Contract (dkt. #2-1) 2 (emphasis in original).) Section 6.1 of the Contract further provides: The Equipment in all stages of construction and all materials, machinery and equipment from time to time acquired by the Contractor or its suppliers or sub-contractors for the manufacture of the Equipment, whether located from time to time in the Contractor’s plant or elsewhere, shall be the property of the Owner to the extent that such Equipment has been paid for by the Owner, and Contractor agrees to perform all acts necessary to perfect and assure title, free and clear of all liens and encumbrances, in such Equipment in the Owner. The Contractor shall certify to the Owner on demand at reasonable intervals that title to such Equipment has passed to the Owner. Notwithstanding the foregoing, title to all Equipment for which payment has not been received by the Contractor shall pass to the Owner upon delivery of the Equipment to the Mill. (Id. at 4.) Finally, again relevant to the counterclaims and third-party complaint, the Contract incorporated “Schedule H -- the General Conditions,” including among other things, contains the following limitation of liability clause: Except in connection with a Party’s indemnification obligations under the Contract and a Party’s breach of GC 50 . . . in no event shall either Party, its affiliates, or their respective directors, officers, agents or employees, be liable to the other Party under any theory of tort, contract, strict liability or other legal or equitable theory for exemplary, punitive, indirect, special, lost profits, consequential or similar damages, each of which is hereby excluded by agreement of the Parties regardless of whether or not such Party has been advised of the possibility of such damages. (Dean Decl., Ex. 2 (dkt. #65-2) 39 at § 58.4.) C. Events Surrounding 1,000 TPD Tank Following execution of the Contract in the spring of 2019, MSI proceeded to bring materials for the construction of the 1,000 TPD tank falling within its description of “Equipment.” During the summer of 2019, ND Paper also made two payments to MSI for a total of $360,360.00 toward construction of the 1,000 TPD tank. While the parties agree these payments were made in connection with the construction of this tank, ND Paper contends these payments were solely for steel, and MSI contends that they were not solely for materials alone, but also covered “process costs for the material.” (MSI’s Resp. to ND Paper’s PFOFs (dkt. #83) ¶ 27.) Moreover, MSI contends that ND Paper has not paid in full for the materials and labor for the 1,000 TPD tank.2

MSI further represents that there were a number of design changes and engineering issues that resulted in a delay in finishing the 1,000 TPD tank, extending beyond its original, planned completion date of October 1, 2019. Moreover, MSI further represents that ND Paper failed to make payments timely, resulting in MSI discussing a halt to the project or “demobilizing” in November 2019, with that issue persisting into January 2020.

In contrast, ND Paper disputes that it “failed to pay any amounts actually due to MSI,” and further represents that by January 2020, it had paid in full for all of the steel needed to construct the 1,000 TPD tank. (ND Paper’s Resp. to MSI’s PFOFs (dkt. #75) ¶ 10.) On January 28, 2020, ND Paper emailed MSI about the 1,000 TPD tank, stating: We will not pay for any invoices regarding this tank and are with[h]olding funds until detailed construction drawings are received for all tanks. We paid for engineering and design and have not received or approved any detailed drawings. MSI is proceeding here at their own risk. (Dean Decl., Ex. 14 (dkt. #65-14) 1.) Still, in that same email, ND Paper, however, clarified that it was “not cancelling the contract and wanted MSI to continue,” but simply reiterating that it required “detailed drawings,” as had been provided for the other tanks

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Schreiber Foods, Inc. v. LEI WANG
651 F.3d 678 (Seventh Circuit, 2011)
Lindquist Ford, Inc. v. Middleton Motors, Inc.
557 F.3d 469 (Seventh Circuit, 2009)
Stuart v. Weisflog's Showroom Gallery, Inc.
2008 WI 22 (Wisconsin Supreme Court, 2008)
H. A. Friend & Co. v. Professional Stationery, Inc.
2006 WI App 141 (Court of Appeals of Wisconsin, 2006)
Hanmer v. Department of Industry Labor & Human Relations
284 N.W.2d 587 (Wisconsin Supreme Court, 1979)
Kailin v. Armstrong
2002 WI App 70 (Court of Appeals of Wisconsin, 2002)
Elbe v. Wausau Hospital Center
606 F. Supp. 1491 (W.D. Wisconsin, 1985)
Winslow v. Brown
371 N.W.2d 417 (Court of Appeals of Wisconsin, 1985)
Insurance Co. of North America v. Cease Electric Inc.
2004 WI 139 (Wisconsin Supreme Court, 2004)
Oxmans' Erwin Meat Co. v. Blacketer
273 N.W.2d 285 (Wisconsin Supreme Court, 1979)
Janken v. GM Hughes Electronics
46 Cal. App. 4th 55 (California Court of Appeal, 1996)
First Weber Group, Incorporate v. Jonathan Horsfall
738 F.3d 767 (Seventh Circuit, 2013)
Hotel 71 Mezz Lender LLC v. National Retirement Fund
778 F.3d 593 (Seventh Circuit, 2015)
Scott Weaver v. Champion Petfoods USA Inc.
3 F.4th 927 (Seventh Circuit, 2021)
Ferris v. Location 3 Corp.
2011 WI App 134 (Court of Appeals of Wisconsin, 2011)

Cite This Page — Counsel Stack

Bluebook (online)
Mechanical Systems, Inc. v. ND Paper, Inc., Counsel Stack Legal Research, https://law.counselstack.com/opinion/mechanical-systems-inc-v-nd-paper-inc-wiwd-2022.