McNeal v. Lebel

953 A.2d 396, 157 N.H. 458
CourtSupreme Court of New Hampshire
DecidedJuly 11, 2008
Docket2007-291
StatusPublished
Cited by11 cases

This text of 953 A.2d 396 (McNeal v. Lebel) is published on Counsel Stack Legal Research, covering Supreme Court of New Hampshire primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
McNeal v. Lebel, 953 A.2d 396, 157 N.H. 458 (N.H. 2008).

Opinion

HlCKS, J.

The plaintiffs, Jonathan and Paula McNeal, appeal an order of the Superior Court {McHugh, J.) in their action against the defendants, Pullman Modular Industries, Inc. (Pullman) and Robert M. Lebel d/b/a RML General Contractor (Lebel), arising out of the allegedly improper manufacture and/or construction of a modular home. We affirm in part, reverse in part, and remand.

The trial court found or the record supports the following facts. In April 2004, the plaintiffs contracted with Lebel for the construction of a modular home. The eventual contract price was $359,042. The plaintiffs and Lebel decided to purchase the home from Pullman. The home was to be constructed near the plaintiffs’ existing home, allowing them to move into the new home and raze the old one upon completion.

Pullman manufactured the home and delivered it to the plaintiffs’ property in August 2004. Mr. McNeal and Lebel noticed several problems, most prominently that the plaintiffs had expected different kitchen cabinets, the beam and joists for the attic did not allow for installation of a flat floor, and Pullman did not deliver any of the three sets of stairs it was to supply. Pullman eventually delivered, or built on-site, the stairs that it was responsible for supplying and Lebel built two sets of basement stairs as he had contracted to do. Once built, some of the sets of stairs failed to satisfy the applicable building code.

The terms of the plaintiffs’ construction financing required the loan to be paid by September 30, 2004, but the home was not ready for occupancy by that date. In fact, by October 1, each of the parties had become, in the trial court’s words, “somewhat disappointed and distrustful of one another.” *461 Lebel informed the plaintiffs that he would not continue construction unless he was assured payment for work done after October 1. He requested that funds be placed in escrow, but the plaintiffs were not willing to do so.

On October 4, 2004, the plaintiffs’ attorney sent a letter to Lebel requesting that he prioritize his work to the exterior of the home. Lebel interpreted this letter to amount to his termination, and, as of October 7, 2004, stopped work on the home. The plaintiffs did not obtain a certificate of occupancy for the new home until July 2005.

The plaintiffs sued Lebel for breach of contract, and both defendants for negligence and violation of RSA 205-B:2 (2000) and RSA chapter 358-A (1995 & Supp. 2007). Lebel counterclaimed for amounts due under the contract and for unpaid work performed.

With respect to the common law theories, the court concluded that “none of the parties [is] without fault” and awarded damages as follows:

[T]he Court awards the plaintiffs a verdict of $9,250.00 against defendant Lebel on their claims of breach of contract and negligence. The Court awards the plaintiffs a verdict of $9,250.00 against Pullman on their claim of negligence. The Court awards Lebel a verdict of $16,500.00 on his counterclaim against the plaintiffs as it finds that they breached their contract with him by not paying him for all the work that he did and by not allowing him to complete his work. Thus the plaintiffs owe Lebel $7,250.00 at present and Pullman owes the plaintiffs $9,250.00 at present.

On reconsideration, the court ruled that the plaintiffs were entitled to credit for $1,978.36 they paid Lebel for a change order, and reduced the damage award to Lebel by that amount. The trial court found that the evidence did not support the claimed statutory violations.

On appeal, the plaintiffs argue that the trial court erred in: (1) ruling that they breached the contract; (2) making certain factual findings; (3) determining damages; (4) ruling that the home contained no “substantial defects” as that phrase is used in RSA 205-B:2; and (5) ruling that neither defendant committed any unfair or deceptive trade practices as contemplated by RSA 358-A:2 (1995). We will uphold the trial court’s factual findings and rulings of law unless they lack evidentiary support or constitute a clear error of law. Barrows v. Boles, 141 N.H. 382, 389 (1996).

The plaintiffs first challenge the trial court’s determinations of contractual liability, asserting that Lebel materially breached and they committed no breach. They contend that Lebel breached the contract by leaving the job prior to completing his work after insisting upon conditions not contemplated in the contract; specifically, the placement of funds in escrow *462 and assurance of end financing. They further contend that these were material breaches, relieving them of further contractual obligations.

The trial court found that on September 30,2004, the plaintiffs’ construction lender informed Lebel that it “would not be [disbursing] any more monies for the Plaintiffs’] project because they were [two] months behind in [their] interest payments.” The court also ruled that “Lebel performed his work in accordance with the contract until funding was withdrawn by the finance company” and that the plaintiffs’ “unwillingness to escrow sufficient funds to enable Lebel to complete the project was unreasonable.”

We read the court’s order as implicitly ruling that the cessation of disbursements under the construction loan was an apparent anticipatory breach or repudiation of the plaintiffs’ contractual obligations, entitling Lebel to seek assurance of payment before continuing his performance. “An anticipatory breach of contract occurs when a promising party repudiates his obligations either through words or by voluntarily disabling himself from performing them before the time for performance.” Syncom Indus. v. Wood, 155 N.H. 73, 83-84 (2007). Interestingly, as we noted in Syncom, the action constituting anticipatory breach in both of our leading cases on the subject, LeTarte v. West Side Development Group, LLC, 151 N.H. 291 (2004), and Hoyt v. Horst, 105 N.H. 380 (1964), was the failure to make payments under the contract. Id. at 84.

Our cases note that “[i]n instances of anticipatory breach, the non-breaching party has the option to treat the repudiation as an immediate breach and maintain an action at once for the damages.” LeTarte, 151 N.H. at 294. As other courts have recognized, however, where the actions of the apparently repudiating party are equivocal or uncertain, this option presents the non-breaching party with a dilemma. See Norcon Power v. Niagara Mohawk Power, 705 N.E.2d 656, 659 (N.Y. 1998).

If the promisee regards the apparent repudiation as an anticipatory repudiation, terminates his or her own performance and sues for breach, the promisee is placed in jeopardy of being found to have breached if the court determines that the apparent repudiation was not sufficiently clear and unequivocal to constitute an anticipatory repudiation justifying nonperformance.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Under Wild Skies v. NRA
Supreme Court of Virginia, 2025
Kyle Guay v. P Sig Sauer, Inc.
2022 DNH 109 (D. New Hampshire, 2022)
Guay v. Sig Sauer, Inc.
D. New Hampshire, 2022
S & W Roofing, LLC v. Scott Shepperson
Supreme Court of New Hampshire, 2020
Alfred Charest, III & a. v. Kym Blaisdell
Supreme Court of New Hampshire, 2017
Geoffrey Fowler v. Annabella Morse
Supreme Court of New Hampshire, 2015
Ellis v. Candia Trailers & Snow Equipment, Inc.
58 A.3d 1164 (Supreme Court of New Hampshire, 2012)
Franchi v. New Hampton School
656 F. Supp. 2d 252 (D. New Hampshire, 2009)

Cite This Page — Counsel Stack

Bluebook (online)
953 A.2d 396, 157 N.H. 458, Counsel Stack Legal Research, https://law.counselstack.com/opinion/mcneal-v-lebel-nh-2008.