This text of 855 A.2d 505 (LeTarte v. West Side Development Group, LLC) is published on Counsel Stack Legal Research, covering Supreme Court of New Hampshire primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
LeTarte v. West Side Development Group, LLC, 855 A.2d 505, 151 N.H. 291, 2004 N.H. LEXIS 139 (N.H. 2004).

Opinion

DUGGAN, J.

The plaintiff, Hank LeTarte, appeals an order of the Superior Court (O’Neill, J.) finding the defendant, West Side Development Group, LLC, in partial breach of paragraph one of their agreement and dismissing, without prejudice, his claim for breach of paragraph two of the agreement. We reverse and remand.

The parties agreed to the following facts. The plaintiff provided landscaping services to the defendant, the owner and developer of a subdivision known as “Hale Estates.” When the defendant needed additional financing to continue development of the subdivision, the plaintiff introduced the defendant to a lender who agreed to finance the defendant’s project. In consideration for the plaintiffs landscaping and financing services, the defendant entered into an agreement with the plaintiff on November 17,1999. Paragraph one of the agreement provides:

[293]*293West Side Development shall pay [LeTarte] the total sum of Thirty Five Thousand Dollars ($35,000.00). Said Thirty Five Thousand Dollars ($35,000.00) shall be paid in increments of not less than One Thousand Dollars ($1,000.00) which shall be paid upon the sale of individual house lots located within the Hale Estates Development. The Thirty Five Thousand Dollars ($35,000.00) shall be evidenced by means of a promissory note. The promissory note shall carry an [sic] five percent (5%) simple interest rate. West Side Development may prepay any or all of the note at any time without penalty.

Paragraph two of the agreement provides:

West Side Development shall convey to [LeTarte] a house lot located in Phase Three of the within development. [LeTarte] shall have first choice of all lots available within Phase Three. It is understood that the actual conveyance of said lot to [LeTarte] may not be able to be accomplished until such time as the outstanding indebtedness to Philip Rogers Trust is resolved and thereafter the lot will be conveyed. In any event, [LeTarte] shall take title to the house lot at such a time in such a manner that he receives good and marketable title free and clear of any and all encumbrances. The agreed value of the lot is Forty Thousand Dollars ($40,000.00), however the parties are not unmindful of the nature of selling priees/fluetuation of the market and neither party shall seek to be compensated for any such fluctuation in value at the time of the actual conveyance.

On March 4,2002, the plaintiff notified the defendant of his choice of Lot 47 in the Hale Estates development, pursuant to paragraph two of the agreement. On October 21, 2002, the defendant sold Lot 47 to a third party.

Additionally, the defendant failed to compensate the plaintiff pursuant to paragraph one of the agreement, even though since November 17,1999, the defendant had sold nineteen house lots. The plaintiff filed suit, seeking damages for the defendant’s alleged breach of contract under paragraphs one and two of the agreement. At the time of the lawsuit, the defendant still owed approximately $645,000 to Philip Rogers Trust.

The trial court ordered the defendant to pay the plaintiff $19,000, representing $1,000 for each of the nineteen lots the defendant had sold. The trial court, however, ruled that the plaintiff was not entitled to the entire $35,000 pursuant to paragraph one of the agreement, since there was no acceleration clause in the contract. The trial court also found that [294]*294the plaintiffs claim for breach of paragraph two was not ripe since the defendant had not resolved its indebtedness to Philip Rogers Trust and dismissed this claim without prejudice. The plaintiff moved unsuccessfully for reconsideration and clarification. This appeal followed.

The plaintiff first argues that he is entitled to the entire $35,000 pursuant to paragraph one of the agreement. Specifically, the plaintiff contends that the defendant’s failure to pay $1,000 for each of the first nineteen lots sold is an anticipatory breach by nonperformance and, thus, a total and immediate breach of paragraph one. We agree.

“Because the proper interpretation of a written agreement is ultimately a question of law for this court, we review the trial court’s interpretation of the agreement de novo.” Gen. Linen Servs. v. Franconia Inv. Assocs., 150 N.H. 595, 597 (2004). ‘We will sustain its findings and conclusions unless they are lacking in evidential support or tainted by error of law.” Id.

An anticipatory breach of a contract occurs when a promising party repudiates his obligations either through words or by voluntarily disabling himself from performing them before the time for performance. 9 A. Corbin, Contracts § 959 (Interim ed. 2002). In instances of anticipatory breach, the non-breaching party has the option to treat the repudiation as an immediate breach and maintain an action at once for the damages. Id.

In Hoyt v. Horst, 105 N.H. 380 (1964), we explained our view of the anticipatory breach doctrine. In Hoyt, the defendants’ business associate took a loan from the plaintiff. Hoyt, 105 N.H. at 384. After the business associate paid back a few installments, payment ended and the associate left the area. Id. The defendants arranged with the plaintiff to reimburse her for their business associate’s loan. Id. at 384-85. After a few small installments were paid on the loan, the defendants also ceased making payments and the plaintiff sued for the entire amount due on the loan. Id. at 385. The issue was whether a breach can be “such that the plaintiff can regard it as ‘total’ and maintain action for her entire injury, however uncertain in amount and however far into the future it may occur.” Id. at 389 (quotation, brackets and ellipsis omitted).

Our analysis in Hoyt was twofold. First, we looked to the theory of successive breaches of a continuing contract, see CORBIN, supra § 956, to see if the breach was total. Hoyt, 105 N.H. at 389. Successive breaches of a continuing contract, while generally viewed as a series of partial breaches, can result in a total breach when there is a repudiation or a material failure of performance. Corbin, supra § 956. In applying this theory, we made two observations. First, after the initial installments, the defendants failed to make any more payments under the contract. Hoyt, 105 N.H. at [295]*295389. Second, “[t]here was not the slightest indication that any further installments would ever be received by the plaintiff.” Id. Thus, because of the defendants’ material failure to perform, we held that the contract was in total breach. Id.

Second, we addressed anticipatory breach of unilateral contracts, see CORBIN, supra §§ 963, 966, to determine if there was an immediate cause of action. Hoyt, 105 N.H. at 389. We recognized that there was authority for the view that where a contract is fully executed by the non-breaching party, no relief for anticipatory breach can be granted until the time for payment arrives. Id. That is the view of the RESTATEMENT. See Restatement (Second) of Contracts § 253 comment c at 287 (1981). However, we found that an immediate cause of action for the plaintiffs entire injury was proper because “courts should be able to deal with such a situation as here exists so as to avoid endless delays and multiplicity of suits.” Hoyt, 105 N.H. at 389.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Slania Enterprises, Inc. v. Appledore Medical Group, Inc.
186 A.3d 222 (Supreme Court of New Hampshire, 2018)
In Re Chemtura Corp.
448 B.R. 635 (S.D. New York, 2011)
McNeal v. Lebel
953 A.2d 396 (Supreme Court of New Hampshire, 2008)
Lakeview Neurorehabilitation v. Care
2008 DNH 109 (D. New Hampshire, 2008)
Syncom Industries, Inc. v. Wood
920 A.2d 1178 (Supreme Court of New Hampshire, 2007)
Enterasys v. Clarendon Insurance
2006 DNH 098 (D. New Hampshire, 2006)
Pope v. Lee
879 A.2d 735 (Supreme Court of New Hampshire, 2005)
Merrimack Valley Wood Products, Inc. v. Near
876 A.2d 757 (Supreme Court of New Hampshire, 2005)

Cite This Page — Counsel Stack

Bluebook (online)
855 A.2d 505, 151 N.H. 291, 2004 N.H. LEXIS 139, Counsel Stack Legal Research, https://law.counselstack.com/opinion/letarte-v-west-side-development-group-llc-nh-2004.