McNamee v. Hunt

87 F. 298, 30 C.C.A. 653, 1898 U.S. App. LEXIS 1795
Court of Appeals for the Fourth Circuit·Decided May 3, 1898·No. No. 248·Published·Cited by 7 cases

Opinion

SIMONTON, Circuit Judge.

This case comes up by writ of error to the circuit: court of the United States for the Western district of North Carolina. The action was brought against the owner pf a lot of land in the city of Asheville, N. C., for whom an excavation was, being made for the foundation of a building in that city. This excavation was effected by blasting; and the plaintiff below (defendant in error here) alleges that a piece of rock thrown out by the blasting broke his leg, and inflicted serious injuries on him. The case was tried before a jury, on complaint, answer, and testimony; and a verdict was found for the plaintiff below in the sum of $8,500. After making a motion for a new trial, without avail, the plaintiff in error obtained his writ of error; and the case is before us on 2-1 assignments of error.

The defendant below was the legal owner of the lot in Asheville, lie desired to erect a brick building thereon for the use of a Young Men’s Institute, and to that end obtained the consent of the city authorities to excavate a foundation and erect the building. lie advertised for bids for the excavating work, and finally agreed with one Britt, a contractor, for the completion of the work for a lump sum of $6-15. It is important to know the precise terms of the contract, and it is inserted here:

“Biltmore, N. 0., April 19th, 1892.
“Bids will bo received by the undersigned, up to and including the 23d April, for excavation of lot southeast corner of Eagle and Market streets. Lot is to be excavated entire length, 50 feet wide, from the line of Market street, and an average depth of 9 feet. Particulars can be obtained from the undersigned. Bids of stated sum for the entire work are preferred to those for cubic yard. Charles McNamee.”
“Asheville, N. C., April 21st, 1892.
“A bid for excavation of lot southeast corner of Eagle and Market street. Lot is to be excavated the entire 50 feet wide from line of Market street, and average depth of 9 feet, for the sum of nineteen cents (19c.) per cubic yard for earth; loose rock and hardpan, for the sum of twenty-five cenis (25c) per cubic yard; hard rock, for the sum of sixty cents per cubic yard; or 8015.00 (six hundred and forty-five), lump job.
“Yours, truly, E. II. Britt & Co.
“To Charles McNamee, Biltmore, N. C.”

Upon the receipt of which answer the said defendant, McNamee, wrote the said Britt as follows1:

“Biltmore, N. C., April 301h, ‘1892.
“Mr. Elilra H. Britt, Asheville. N. C. — Dear Sir: Your offer to excavate for 8015.90 lot at tlie southeast corner of Eagle and Market streets, in accordance with the plans of the building, which you have seen, which show an excavation generally of about nine feet in depth the whole length of the lot, and fifty wide, is accepted, upon the following conditions: First. The work is to be fully completed by the 21st day of May, 1892, under penalty of $5.00 for each day’s delay after that date. Second. The excavation is to be done absolutely in accordance with the drawings: and your bid includes the digging of a trench around the exterior lines of the excavation, as shown on the "plans, of the depth required by the architect. Third. The work to be neatly done) to the full satisfaction of the architect, Mr. R. S. Smith, and is to be paid for only upon his certificate that the work lias been properly completed. Fourth. The lines of the excavation and all the trenches are to be given by the engineer, — probably, Mr. Olney. Please let me know if the terms of this letter are agreed to. If they are, you may begin work Monday morning.
“Yours, truly, Charles McNamee.”

[300] The gist of this action is that Britt was a negligent and careless man, within the knowledge, or means of knowledge, of McNamee; that no provision was made in the contract for the observance of proper precautions in doing a piece of work which necessarily required blasting with explosive substances in the heart of a city; that in fact the contractor did this work without taking such precautions, and so negligently that a piece of rock was thrown out by the blast, and struck the leg of the plaintiff below, who was at the door of an hotel on a public street, out of sight of the blasting. The suit proceeded upon the principle of the exception to the rule that employers are not generally liable for the acts of contractors. It rests on the exception, which is that:

“When a person is engaged in a work, in the ordinary doing of which a. nuisance necessarily occurs, the person is liable for any injury which may occur to third persons from carelessness or negligence, though the work may be done by a contractor.” Ware v. St. Paul Water Co., Fed. Cas. No. 17,172.

In affirming this case, the supreme court says:

“Where the obstruction or defect caused or created ini the street is purely collateral to the work contracted to be done and is entirely the result of the wrongful acts of the contractor or his workmen, the rule is that the employer is not responsible. But where the obstruction or defect which occasioned the injury results directly from the acts which the contractor agreed and was authorized to do, the person who employs the contractor, and authorizes him to do those acts, is equally liable to the injured party.” Water Co. v. Ware, 16 Wall. 576.

The court adopts the language in City of Chicago v. Robbins, 2 Black, 428:

“If the nuisance occurs necessarily in the' ordinary mode of doing 'the work, the occupant or owner is' liable. But, if it is from the negligence of the contractor or his servants, then he alone should be responsible.”

And adds:

“Common justice requires the enforcement of that rule, as, if the contractor does the thing which he is employed to do, the employer is as responsible for the thing as if he had done it himself; but if the act complained of is purely collateral to the matter contracted to be done, and arises indirectly in the course of the performance of the work, the employer is not liable, because he never authorized the work to be done.”

Free access — add to your briefcase to read the full text and ask questions with AI

McNamee v. Hunt, 87 F. 298, 30 C.C.A. 653, 1898 U.S. App. LEXIS 1795 (4th Cir. 1898).

87 F. 298 (McNamee v. Hunt) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Bonet v. Municipality of Barceloneta
87 P.R. 74 (Supreme Court of Puerto Rico, 1963)
Bonet v. Municipio de Barceloneta
87 P.R. Dec. 81 (Supreme Court of Puerto Rico, 1963)
Lintner v. Wiles
141 P. 871 (Oregon Supreme Court, 1914)
Pierson v. Chicago, R. I. & P. Ry. Co.
170 F. 271 (Eighth Circuit, 1909)
Huntt v. McNamee
141 F. 293 (Fourth Circuit, 1905)